Section 4b-103. - Construction manager at-risk project delivery contracts.

(a) In order to carry out any provision of this title for the construction, renovation or alteration of buildings or facilities, the Commissioner of Administrative Services may enter into a construction manager at-risk project delivery contract.

(b) Except as provided in subsections (c) and (d) of this section, the Commissioner of Administrative Services shall not enter into a construction manager at-risk project delivery contract that does not provide for a maximum guaranteed price for the cost of construction that shall be determined not later than the time of the receipt and approval by the commissioner of the trade contractor bids. Each construction manager at-risk shall invite bids and give notice of opportunities to bid on project elements on the State Contracting Portal. Each bid shall be kept sealed until opened publicly at the time and place as set forth in the notice soliciting such bid. The construction manager at-risk shall, after consultation with and approval by the commissioner, award any related contracts for project elements to the responsible qualified contractor submitting the lowest bid in compliance with the bid requirements, provided (1) the construction manager at-risk shall not be eligible to submit a bid for any such project element, and (2) construction shall not begin prior to the determination of the maximum guaranteed price, except for the project elements of site preparation and demolition that have been previously put out to bid and awarded.
(c) Construction may begin prior to the determination of the maximum guaranteed price for the project elements of site preparation, demolition, public utility installation and connections, and building envelope components, including the roof, doors, windows and exterior walls, provided (1) the project is the renovation of an existing building or facility; (2) the project element or elements involved in such early work have been previously put out to bid and awarded; and (3) the total cost of construction of the early work does not exceed twenty-five per cent of the estimated cost of construction for the entire project.
(d) If such project involves the renovation of an existing building or facility that will be performed in multiple phases while such building or facility remains occupied, the Commissioner of Administrative Services may enter into a construction manager at-risk project delivery contract that provides for the maximum guaranteed price to be determined for each phase of the project, prior to beginning each such phase, provided all requirements of subsection (b) of this section other than the timing of the determination of the maximum guaranteed price are complied with.
(P.A. 06-134, S. 21; P.A. 11-51, S. 90; P.A. 13-247, S. 200; P.A. 14-188, S. 6.)
History: P.A. 06-134 effective July 1, 2006; pursuant to P.A. 11-51, “Commissioner of Public Works” was changed editorially by the Revisors to “Commissioner of Construction Services”, effective July 1, 2011; pursuant to P.A. 13-247, “Commissioner of Construction Services” was changed editorially by the Revisors to “Commissioner of Administrative Services”, effective July 1, 2013; P.A. 14-188 amended Subsec. (b) to add exception re Subsecs. (c) and (d) and to replace provision re newspaper advertisement with provision re State Contracting Portal, and added Subsec. (c) re construction prior to determination of maximum guaranteed price and Subsec. (d) re multiple phase determination of maximum guaranteed price, effective July 1, 2014.

Structure Connecticut General Statutes

Connecticut General Statutes

Title 4b - State Real Property

Chapter 60 - Construction and Alterations of State Buildings

Section 4b-51. (Formerly Sec. 4-131). - Alterations, repairs or additions to real assets. Selection of consultants for certain projects.

Section 4b-51a. - Recycled content requirements for construction materials.

Section 4b-52. (Formerly Sec. 4-132). - Repairs or changes to state premises. Exception for emergency conditions. Renegotiation of leases.

Section 4b-53. (Formerly Sec. 4-131a). - Allocation of bond proceeds for art work in construction or remodeling of state buildings. State building works of art account. Maintenance account. Regulations.

Section 4b-54. (Formerly Sec. 4-134). - Designs of public structures to be submitted to Commissioner of Administrative Services. Work of art for Capitol to be submitted to Legislative Management Committee.

Section 4b-55. (Formerly Sec. 4-134a). - State Construction Services Selection Panel; Connecticut Health and Education Facilities Authority Construction Services Panel. Definitions.

Section 4b-55a. - Contracting for environmental evaluations for priority higher education facility projects.

Section 4b-56. (Formerly Sec. 4-134b). - State construction services selection panels, and Connecticut Health and Education Facilities Authority construction services panels, established. Membership.

Section 4b-57. (Formerly Sec. 4-134c). - Consultant services. Invitation of responses. Consideration by selection panel.

Section 4b-58. (Formerly Sec. 4-134d). - Contracting for consultant services.

Section 4b-59. (Formerly Sec. 4-134e). - Commissioner to adopt regulations.

Section 4b-60. - State Commission on Capitol Preservation and Restoration.

Section 4b-61. (Formerly Sec. 4-24m). - Contracting for design professional services.

Section 4b-62. (Formerly Sec. 4-135). - Trusts for erecting and maintaining memorials.

Section 4b-63. (Formerly Sec. 4-36b). - Demolition of state buildings. Notice to municipalities.

Section 4b-64. (Formerly Sec. 4-36c). - Notice of intent to dispose of, demolish or transfer certain structures to be given to Department of Economic and Community Development and affected municipality.

Section 4b-65. - Buildings adjacent to Capitol.

Section 4b-66. (Formerly Sec. 4-24c). - Connecticut Capitol Center. Master plan for development. Exceptions. Review of plan by Connecticut Capitol Center Commission. Reports.

Section 4b-66a. - Connecticut Capitol Center Commission: Membership, duties.

Section 4b-67. (Formerly Sec. 4-24d). - Consultation with the Joint Committee on Legislative Management and other state agencies.

Section 4b-68. (Formerly Sec. 4-24e). - Amendment of master plan.

Section 4b-69. (Formerly Sec. 4-24f). - Development of Connecticut Capitol Center except Legislative Office Building: Approval of preliminary plans.

Section 4b-70. (Formerly Sec. 4-24g). - Commissioner of Administrative Services to review construction.

Section 4b-71. (Formerly Sec. 4-24h). - Approvals prerequisite to acquisition or development of property within Capitol Center District.

Section 4b-72. (Formerly Sec. 4-24i). - Acquisition of property within district by Commissioner of Administrative Services.

Section 4b-73. (Formerly Sec. 4-24j). - Relocation of displaced persons.

Section 4b-74. (Formerly Sec. 4-24k). - Approval of building or zoning permits for property within district.

Section 4b-75. - Status report on emergency correctional facility projects.

Section 4b-76. - Public or special act authorizations for acquisition of real property.

Section 4b-77. - Installation of level two electric vehicle charging stations at state facility. Inclusion of electric vehicle charging infrastructure at certain buildings in municipalities.

Section 4b-91. (Formerly Sec. 4-137a). - Process for bidding for public works contracts. Prequalification requirements. Exceptions.

Section 4b-92. (Formerly Sec. 4-137b). - “Lowest responsible and qualified bidder” defined. Bid bonds, certified checks, when forfeited.

Section 4b-93. (Formerly Sec. 4-137c). - Contract specifications; subtrades, subcontracts.

Section 4b-94. (Formerly Sec. 4-137d). - Rejection of bids.

Section 4b-95. (Formerly Sec. 4-137e). - General bid form requirements. Selection by awarding authority. Subcontractors.

Section 4b-95a. - Listing of general bidder as a subcontractor on bid form.

Section 4b-96. (Formerly Sec. 4-137g). - Subcontract, form. Procedure on failure of subcontractor to execute subcontract. General bidder's responsibilities.

Section 4b-97. (Formerly Sec. 4-126c). - Arbitration of public works contracts.

Section 4b-98, 4b-98a and 4b-99. - Definitions. Large public building projects; bidding procedures, contracts and payrolls. Construction management services; invitation of responses and contracts for; regulations.

Section 4b-100. - Regulations.

Section 4b-100a. - Construction services award panels. Screening, interview and selection of contractors. Memoranda re selection. Regulations.

Section 4b-101. - Information re contractors and subcontractors to be provided to Commissioner of Revenue Services.

Section 4b-101a. - Awarding authorities to prepare report on status of certain projects and property management contracts. When.

Section 4b-102. - Bidding for certain construction contracts for the Connecticut State University System.

Section 4b-103. - Construction manager at-risk project delivery contracts.