§ 43-5. Sufficiency of memorandum and affidavit required by § 43-4

The memorandum and affidavit required by § 43-4 shall be sufficient if substantially in form and effect as follows:
Memorandum for Mechanic's Lien Claimed by General Contractor.
Name of owner: ___________________________________________________________________________
Address of owner: ___________________________________________________________________________
Name of claimant: ___________________________________________________________________________
Address of claimant: ___________________________________________________________________________
Contractor license or certificate number of claimant
(if applicable): ___________________________________________________________________________
Issuance date of license or certificate
(if applicable): ___________________________________________________________________________
Expiration date of license or certificate
(if applicable): ___________________________________________________________________________
If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.
1. Type of materials or services furnished: ___________________________________________________________________________ ___________________________________________________________________________ ___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
2. Amount claimed: $ ___________________________________________________________________________
If any part of the Amount claimed is not due as of the date of this mechanic's lien, identify the date or event upon which it will be due and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________
3. Type of structure on which work done or materials furnished: ___________________________________________________________________________
___________________________________________________________________________
4. Brief description and location of real property:
___________________________________________________________________________
5. Date from which interest on the above amount is claimed:
Date: _______________________
It is the intent of the claimant to claim the benefit of a lien.
The undersigned hereby certifies that he has mailed a copy of this memorandum of lien to the owner of the property at the owner's last known address: .................................. (address), on ........ (date of mailing).
___________________________________________________________________________ (Name of claimant).
Affidavit.
State of Virginia,
County (or city) of .................., to wit:
I, _______________________ (notary or other officer) for the county (or city) aforesaid, do certify that ...................... claimant, or ................, agent for claimant, this day made oath before me in my county (or city) aforesaid that ..................... (the owner) is justly indebted to claimant in the sum of .............. dollars, for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.
Given under my hand this the ........ day of ................., 20....
___________________________________________________________________________ (Notary Public or Magistrate, et cetera.)
Code 1919, § 6427; 1940, p. 402; 1968, c. 568; 2007, c. 504; 2013, c. 293; 2019, c. 243.

Structure Code of Virginia

Code of Virginia

Title 43 - Mechanics' and Certain Other Liens

Chapter 1 - Mechanics' and Materialmen's Liens

§ 43-1. Definitions

§ 43-2. Structures, materials, etc., deemed permanently annexed to freehold

§ 43-3. Lien for work done and materials furnished; waiver of right to file or enforce lien

§ 43-4. Perfection of lien by general contractor; recordation and notice

§ 43-4.1. Liens to be recorded in deed books and indexed in general index of deeds

§ 43-4.01. Posting of building permit; identification of mechanics' lien agent in building permit; notice to mechanics' lien agent; effect of notice

§ 43-5. Sufficiency of memorandum and affidavit required by § 43-4

§ 43-6. Repealed

§ 43-7. Perfection of lien by subcontractor; extent of lien; affirmative defense; provisions relating to time-share estates

§ 43-8. Sufficiency of memorandum, affidavit and notice required by § 43-7

§ 43-9. Perfection of lien by person performing labor or furnishing materials for a subcontractor; extent of lien

§ 43-10. Sufficiency of memorandum, affidavit and notice required by § 43-9

§ 43-11. How owner or general contractor made personally liable to subcontractor, laborer or materialman

§ 43-12. Repealed

§ 43-13. Funds paid to general contractor or subcontractor must be used to pay persons performing labor or furnishing material

§ 43-13.1. Use of lien waiver form; forgery or signing without authority

§ 43-13.2. When an affidavit or a signed statement of payment required of owner prior to sale

§ 43-13.3. An affidavit or a signed statement of payment required of owner prior to sale or refinance; penalty

§ 43-14. Repealed

§ 43-14.1. Service of notices

§ 43-15. Inaccuracies in memorandum or description not affecting lien

§ 43-16. What owner may do when contractor fails or refuses to complete building, etc.

§ 43-17. Limitation on suit to enforce lien

§ 43-17.1. Hearing on validity of lien

§ 43-18. Lien of general contractor to inure to benefit of subcontractor

§ 43-19. Validity and priority of lien not affected by assignments

§ 43-20. Extent of lien where owner has less than fee in land

§ 43-21. Priorities between mechanics' and other liens

§ 43-22. How liens enforced

§ 43-23. Priority among liens perfected under this chapter

§ 43-23.1. Forfeiture of lien

§ 43-23.2. Remedies cumulative