1. Any subcontractor or person furnishing labor or material to the general contractor or subcontractor, may give a preliminary notice in writing to the owner or his agent or the general contractor, stating the nature and character of his contract and the probable amount of his claim.
2. Additionally, if such subcontractor, or person furnishing labor or material shall at any time after the work is done or material furnished by him and before the expiration of thirty days from the time such building or structure is completed or the work thereon otherwise terminated furnish the owner thereof or his agent and also the general contractor, or the general contractor alone in case he is the only one notified, with a second notice stating a correct account, verified by affidavit, of his actual claim against the general contractor or subcontractor, for work done or materials furnished and of the amount due, then the owner, or the general contractor, if he alone was notified, shall be personally liable to the claimant for the actual amount due to the subcontractor or persons furnishing labor or material by the general contractor or subcontractor, provided the same does not exceed the sum in which the owner is indebted to the general contractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor, or in case the general contractor alone is notified the sum in which he is indebted to the subcontractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor. But the amount which a person supplying labor or material to a subcontractor can claim shall not exceed the amount for which such subcontractor could file his claim.
3. Any bona fide agreement for deductions by the owner because of the failure or refusal of the general contractor to comply with his contract shall be binding upon such subcontractor, laborer or materialman.
4. The provisions of this section are subject to the qualification that before any such personal liability of the owner or general contractor herein provided for shall be binding the two notices herein required, with such returns thereon as is sufficient under § 8.01-325, shall be recorded and indexed as provided in § 43-4.1 in the appropriate clerk's office; or the two notices herein required shall be mailed by registered or certified mail to and received by the owner or general contractor upon whom personal liability is sought to be imposed, and a return receipt therefor showing delivery to the addressee shall be prima facie evidence of receipt.
1924, p. 658; Michie Code 1942, § 6429a; 1968, c. 568; 2002, c. 772.
Structure Code of Virginia
Title 43 - Mechanics' and Certain Other Liens
Chapter 1 - Mechanics' and Materialmen's Liens
§ 43-2. Structures, materials, etc., deemed permanently annexed to freehold
§ 43-3. Lien for work done and materials furnished; waiver of right to file or enforce lien
§ 43-4. Perfection of lien by general contractor; recordation and notice
§ 43-4.1. Liens to be recorded in deed books and indexed in general index of deeds
§ 43-5. Sufficiency of memorandum and affidavit required by § 43-4
§ 43-8. Sufficiency of memorandum, affidavit and notice required by § 43-7
§ 43-10. Sufficiency of memorandum, affidavit and notice required by § 43-9
§ 43-13.1. Use of lien waiver form; forgery or signing without authority
§ 43-13.2. When an affidavit or a signed statement of payment required of owner prior to sale
§ 43-15. Inaccuracies in memorandum or description not affecting lien
§ 43-16. What owner may do when contractor fails or refuses to complete building, etc.
§ 43-17. Limitation on suit to enforce lien
§ 43-17.1. Hearing on validity of lien
§ 43-18. Lien of general contractor to inure to benefit of subcontractor
§ 43-19. Validity and priority of lien not affected by assignments
§ 43-20. Extent of lien where owner has less than fee in land
§ 43-21. Priorities between mechanics' and other liens