(A) After issuance of a base load review order approving rate recovery for capital costs related to the plant, the utility will file reports with the Office of Regulatory Staff quarterly until the plant begins commercial operation. These reports must be filed no later than forty-five days after the close of a quarter, shall not be combined with any other filing, and shall contain the following information:
(1) the progress of construction of the plant;
(2) updated construction schedules;
(3) schedules of the capital costs incurred including updates to the information required by Section 58-33-270(B)(5);
(4) updated schedules of the anticipated capital costs; and
(5) other information as the Office of Regulatory Staff may require.
(B) The Office of Regulatory Staff shall conduct on-going monitoring of the construction of the plant and expenditure of capital through review and audit of the quarterly reports under this article, and shall have the right to inspect the books and records regarding the plant and the physical progress of construction upon reasonable notice to the utility.
HISTORY: 2007 Act No. 16, Section 2, eff upon approval (became law without the Governor's signature on May 3, 2007).
Structure South Carolina Code of Laws
Title 58 - Public Utilities, Services and Carriers
Chapter 33 - Utility Facility Siting And Environmental Protection
Section 58-33-10. Short title.
Section 58-33-20. Definitions.
Section 58-33-140. Parties to certification proceedings; limited appearances; intervention.
Section 58-33-150. Record of proceedings; consolidation of representation of parties.
Section 58-33-160. Decision of Commission.
Section 58-33-170. Opinion of Commission.
Section 58-33-180. Additional requirements regarding construction of a major utility facility.
Section 58-33-185. Additional requirements regarding acquisition of a major utility facility.
Section 58-33-190. Additional requirements regarding purchase of a major utility facility.
Section 58-33-210. Citation and applicability of article.
Section 58-33-220. Definitions.
Section 58-33-250. Application for baseline review; contents.
Section 58-33-260. Combined application; contents.
Section 58-33-275. Base load review orders; parameters; challenges; recovery of capital costs.
Section 58-33-277. Reports; contents; on-going monitoring by Office of Regulatory Staff.
Section 58-33-280. Requests for approval of revised rates.
Section 58-33-295. Office of Regulatory staffing; expert witnesses.
Section 58-33-298. Application of limitations on rate filings in Section 58-27-870(E).
Section 58-33-310. Appeal from final order or decision.
Section 58-33-320. Jurisdiction of courts.
Section 58-33-410. Authority of other agencies or local governments; application of other laws.
Section 58-33-430. Annual reports shall be furnished by public utilities.