(A) A combined application must contain:
(1) an introduction;
(2) material required by law or regulation to be contained in an application filed under the Utility Facility Siting and Environmental Protection Act, except that combined applications associated with plants located outside South Carolina shall address only Section 58-33-160(1)(a), 58-33-160(1)(d), and 58-33-160(1)(f) and information pertaining to the environmental impacts of the plant may not be included in the combined application;
(3) the material required by law or regulation to be contained in an application under this article, including the material required under Section 58-33-250;
(4) if combined with a general rate proceeding, the material required to be filed by law or regulation in applications for the establishment of new rates under Section 58-27-860; and
(5) if the plant is located outside South Carolina, a copy of the order from the host state granting a certificate or other authorization similar to that granted under the Utility Facility Siting and Environmental Protection Act.
(B) Where the same information is required in different sections of the combined application, it may be set forth once and cross-referenced as appropriate.
HISTORY: 2007 Act No. 16, Section 2, eff upon approval (became law without the Governor's signature on May 3, 2007).
Structure South Carolina Code of Laws
Title 58 - Public Utilities, Services and Carriers
Chapter 33 - Utility Facility Siting And Environmental Protection
Section 58-33-10. Short title.
Section 58-33-20. Definitions.
Section 58-33-140. Parties to certification proceedings; limited appearances; intervention.
Section 58-33-150. Record of proceedings; consolidation of representation of parties.
Section 58-33-160. Decision of Commission.
Section 58-33-170. Opinion of Commission.
Section 58-33-180. Additional requirements regarding construction of a major utility facility.
Section 58-33-185. Additional requirements regarding acquisition of a major utility facility.
Section 58-33-190. Additional requirements regarding purchase of a major utility facility.
Section 58-33-210. Citation and applicability of article.
Section 58-33-220. Definitions.
Section 58-33-250. Application for baseline review; contents.
Section 58-33-260. Combined application; contents.
Section 58-33-275. Base load review orders; parameters; challenges; recovery of capital costs.
Section 58-33-277. Reports; contents; on-going monitoring by Office of Regulatory Staff.
Section 58-33-280. Requests for approval of revised rates.
Section 58-33-295. Office of Regulatory staffing; expert witnesses.
Section 58-33-298. Application of limitations on rate filings in Section 58-27-870(E).
Section 58-33-310. Appeal from final order or decision.
Section 58-33-320. Jurisdiction of courts.
Section 58-33-410. Authority of other agencies or local governments; application of other laws.
Section 58-33-430. Annual reports shall be furnished by public utilities.