Section 58-33-185. Additional requirements regarding acquisition of a major utility facility.

(A) The Public Service Authority may not enter into a contract for the acquisition of a major utility facility without approval of the Public Service Commission of South Carolina, provided that the approval is required only to the extent the transaction is not subject to the exclusive jurisdiction of the Federal Energy Regulatory Commission or any other federal agency.
(B)(1) In acting upon any petition by the Public Service Authority pursuant to this section, the Public Service Authority must prove by a preponderance of the evidence that the proposed transaction constitutes a more cost-effective means for serving direct serve and wholesale customers than other feasibly available long-term power supply alternatives and provides less ratepayer risk while maintaining safe and reliable electric service than other feasibly available long-term power supply alternatives. The commission shall consider any previous analysis performed pursuant to Section 58-37-40 in acting upon any petition by the Public Service Authority pursuant to this section. The commission shall also take into account the Public Service Authority's arrangements with other electric utilities for interchange of power, pooling of plants, purchase of power and other alternative methods for providing reliable, efficient, and economical electric service.
(2) Available long-term power supply alternatives may include, but not be limited to, power purchase agreements of a different duration than proposed, competitive procurement of renewable energy, joint dispatch agreements, market purchases from an existing regional transmission organization, joining or creating a new regional transmission organization, using best available technology for energy generation, transmission, storage and distribution, or any combination thereof.
(C) Application for the approval of the commission shall be made by the Public Service Authority and shall contain a concise statement of the proposed action, the reasons therefor, and such other information as may be required by the commission.
(D) Upon the receipt of an application, the commission shall promptly fix a date for the commencement of a public hearing, not less than sixty nor more than ninety days after the receipt, and shall conclude the proceedings as expeditiously as practicable. The commission shall establish notice requirements and proceedings shall include an opportunity for intervention, discovery, filed comments or testimony, and an evidentiary hearing.
(E) The commission shall render a decision upon the record either granting or denying the application as filed, or granting it upon such terms, conditions or modifications as the commission may deem appropriate.
(F)(1) The commission may not grant approval unless it shall find and determine that the Public Service Authority satisfied all requirements of this section and the proposed transaction is in the best interests of the retail and wholesale customers of the Public Service Authority.
(2) The commission also may require compliance with any provision of Article 3, Chapter 33, Title 58 that the commission determines necessary to grant approval.
HISTORY: 2021 Act No. 90 (H.3194), Section 20, eff January 1, 2022.

Structure South Carolina Code of Laws

South Carolina Code of Laws

Title 58 - Public Utilities, Services and Carriers

Chapter 33 - Utility Facility Siting And Environmental Protection

Section 58-33-10. Short title.

Section 58-33-20. Definitions.

Section 58-33-110. Certificate required before construction of major utility facility; transfer and amendment of certificate; exceptions; emergency certificates.

Section 58-33-120. Application for certificate; service on and notice to municipalities, government agencies and other persons of application.

Section 58-33-130. Hearings.

Section 58-33-140. Parties to certification proceedings; limited appearances; intervention.

Section 58-33-150. Record of proceedings; consolidation of representation of parties.

Section 58-33-160. Decision of Commission.

Section 58-33-170. Opinion of Commission.

Section 58-33-180. Additional requirements regarding construction of a major utility facility.

Section 58-33-185. Additional requirements regarding acquisition of a major utility facility.

Section 58-33-190. Additional requirements regarding purchase of a major utility facility.

Section 58-33-210. Citation and applicability of article.

Section 58-33-220. Definitions.

Section 58-33-225. Project development applications; prudency determinations; disallowance of imprudent costs; deferral of costs of abandoned project.

Section 58-33-230. Filing applications for proposed construction with commission; copy to and role of Office of Regulatory Staff; application for certificate under Utility Facility Siting and Environmental Protection Act for plants inside South Carol...

Section 58-33-240. Applicability of procedural requirements for general rate proceedings; notice; burden of proof as to prudence of decision to build plant; deadlines.

Section 58-33-250. Application for baseline review; contents.

Section 58-33-260. Combined application; contents.

Section 58-33-270. Base load review orders; contents; petition for modification; settlement agreements between Office of Regulatory Staff and applicant.

Section 58-33-275. Base load review orders; parameters; challenges; recovery of capital costs.

Section 58-33-277. Reports; contents; on-going monitoring by Office of Regulatory Staff.

Section 58-33-280. Requests for approval of revised rates.

Section 58-33-285. Review of revised rates order or failure to issue such order; Office of Regulatory Staff as party; intervention.

Section 58-33-287. Review proceedings; consideration of settlement; discovery; contents and time for issuance of final order.

Section 58-33-290. Effect of denial of or failure to seek project development application; filing new or amended applications.

Section 58-33-295. Office of Regulatory staffing; expert witnesses.

Section 58-33-298. Application of limitations on rate filings in Section 58-27-870(E).

Section 58-33-310. Appeal from final order or decision.

Section 58-33-320. Jurisdiction of courts.

Section 58-33-410. Authority of other agencies or local governments; application of other laws.

Section 58-33-420. Joint hearings with agencies from other states; agreements and compacts; joint investigations.

Section 58-33-430. Annual reports shall be furnished by public utilities.