(1) Before award of a public works contract, a bidder must meet the following responsibility criteria to be considered a responsible bidder and qualified to be awarded a public works project. The bidder must:
(a) At the time of bid submittal, have a certificate of registration in compliance with chapter 18.27 RCW;
(b) Have a current state unified business identifier number;
(c) If applicable, have industrial insurance coverage for the bidder's employees working in Washington as required in Title 51 RCW; an employment security department number as required in Title 50 RCW; and a state excise tax registration number as required in Title 82 RCW;
(d) Not be disqualified from bidding on any public works contract under RCW 39.06.010 or 39.12.065(3);
(e) If bidding on a public works project subject to the apprenticeship utilization requirements in RCW 39.04.320, not have been found out of compliance by the Washington state apprenticeship and training council for working apprentices out of ratio, without appropriate supervision, or outside their approved work processes as outlined in their standards of apprenticeship under chapter 49.04 RCW for the one-year period immediately preceding the date of the bid solicitation;
(f) Have received training on the requirements related to public works and prevailing wage under this chapter and chapter 39.12 RCW. The bidder must designate a person or persons to be trained on these requirements. The training must be provided by the department of labor and industries or by a training provider whose curriculum is approved by the department. The department, in consultation with the prevailing wage advisory committee, must determine the length of the training. Bidders that have completed three or more public works projects and have had a valid business license in Washington for three or more years are exempt from this subsection. The department of labor and industries must keep records of entities that have satisfied the training requirement or are exempt and make the records available on its website. Responsible parties may rely on the records made available by the department regarding satisfaction of the training requirement or exemption; and
(g) Within the three-year period immediately preceding the date of the bid solicitation, not have been determined by a final and binding citation and notice of assessment issued by the department of labor and industries or through a civil judgment entered by a court of limited or general jurisdiction to have willfully violated, as defined in RCW 49.48.082, any provision of chapter 49.46, 49.48, or 49.52 RCW.
(2) Before award of a public works contract, a bidder shall submit to the contracting agency a signed statement in accordance with chapter 5.50 RCW verifying under penalty of perjury that the bidder is in compliance with the responsible bidder criteria requirement of subsection (1)(g) of this section. A contracting agency may award a contract in reasonable reliance upon such a sworn statement.
(3) In addition to the bidder responsibility criteria in subsection (1) of this section, the state or municipality may adopt relevant supplemental criteria for determining bidder responsibility applicable to a particular project which the bidder must meet.
(a) Supplemental criteria for determining bidder responsibility, including the basis for evaluation and the deadline for appealing a determination that a bidder is not responsible, must be provided in the invitation to bid or bidding documents.
(b) In a timely manner before the bid submittal deadline, a potential bidder may request that the state or municipality modify the supplemental criteria. The state or municipality must evaluate the information submitted by the potential bidder and respond before the bid submittal deadline. If the evaluation results in a change of the criteria, the state or municipality must issue an addendum to the bidding documents identifying the new criteria.
(c) If the bidder fails to supply information requested concerning responsibility within the time and manner specified in the bid documents, the state or municipality may base its determination of responsibility upon any available information related to the supplemental criteria or may find the bidder not responsible.
(d) If the state or municipality determines a bidder to be not responsible, the state or municipality must provide, in writing, the reasons for the determination. The bidder may appeal the determination within the time period specified in the bidding documents by presenting additional information to the state or municipality. The state or municipality must consider the additional information before issuing its final determination. If the final determination affirms that the bidder is not responsible, the state or municipality may not execute a contract with any other bidder until two business days after the bidder determined to be not responsible has received the final determination.
(e) If the bidder has a history of receiving monetary penalties for not achieving the apprentice utilization requirements pursuant to RCW 39.04.320, or is habitual in utilizing the good faith effort exception process, the bidder must submit an apprenticeship utilization plan within ten business days immediately following the notice to proceed date.
(4) The capital projects advisory review board created in RCW 39.10.220 shall develop suggested guidelines to assist the state and municipalities in developing supplemental bidder responsibility criteria. The guidelines must be posted on the board's website.

[ 2020 c 255 § 2; 2019 c 232 § 15; 2018 c 243 § 1; 2017 c 258 § 2; 2010 c 276 § 2; 2009 c 197 § 2; 2007 c 133 § 2.]
NOTES:

Effective date—2018 c 243: "This act takes effect July 1, 2019." [ 2018 c 243 § 2.]


Findings—2017 c 258: "The legislature finds that government contracts should not be awarded to those who knowingly and intentionally violate state laws. The legislature also finds that businesses that follow the law and pay their workers appropriately are placed at a competitive disadvantage to those who reduce costs by willfully violating the minimum wage act and wage payment act. In order to create a level playing field for businesses and avoid taxpayer contracts going to those that willfully violate the law and illegally withhold money from workers, the state should amend the state responsible bidder criteria to consider whether a company has willfully violated the state's wage payment laws over the previous three years." [ 2017 c 258 § 1.]


Rules—Implementation—2009 c 197: See note following RCW 39.04.320.

Structure Revised Code of Washington

Revised Code of Washington

Title 39 - Public Contracts and Indebtedness

Chapter 39.04 - Public Works.

39.04.010 - Definitions.

39.04.015 - Adjustment to bid price—Conditions.

39.04.020 - Plans and specifications—Estimates—Publication—Emergencies.

39.04.040 - Work to be executed according to plans—Supplemental plans.

39.04.050 - Contents of original estimates.

39.04.060 - Supplemental estimates.

39.04.070 - Account and record of cost.

39.04.080 - Certified copy to be filed—Engineers' certificate.

39.04.100 - Records open to public inspection—Certified copies.

39.04.105 - Competitive bidding—Written protests—Notice of contract execution.

39.04.107 - Competitive bidding—Bidder claiming error.

39.04.110 - Penalty for false entries.

39.04.120 - Change orders due to environmental protection requirements—Costs—Dispute resolution.

39.04.130 - Application of RCW 39.04.120.

39.04.133 - State capital improvement or construction projects—Product standards.

39.04.135 - Demolition projects—Recycling or reuse of materials.

39.04.155 - Small works roster contract procedures—Limited public works process—Definitions.

39.04.156 - Small works roster manual—Notification to local governments.

39.04.160 - Contracts subject to requirements established under office of minority and women's business enterprises.

39.04.162 - Awards of procurement contracts to veteran-owned businesses.

39.04.170 - Application of chapter to performance-based contracts for energy equipment.

39.04.175 - Application of chapter to certain agreements relating to water pollution control, solid waste handling facilities.

39.04.180 - Trench excavations—Safety systems required.

39.04.190 - Purchase contract process—Other than formal sealed bidding.

39.04.200 - Small works roster or purchase contracts—Listing of contracts awarded required.

39.04.210 - Correctional facilities construction and repair—Findings.

39.04.220 - Correctional facilities construction and repair—Use of general contractor/construction manager method for awarding contracts—Demonstration projects.

39.04.230 - Correctional facilities construction and repair—Alternative contracting method to remain in force until contracts completed.

39.04.235 - Public works contracts—Unit priced contracts—When authorized—Bidding requirements.

39.04.240 - Public works contracts—Awarding of attorneys' fees.

39.04.250 - Payments received on account of work performed by subcontractor—Disputed amounts—Remedies.

39.04.260 - Private construction performed pursuant to contract for rental, lease, or purchase by state—Must comply with prevailing wage law.

39.04.270 - Electronic data processing and telecommunications systems—Municipalities—Acquisition method—Competitive negotiation—Findings, intent.

39.04.280 - Competitive bidding requirements—Exemptions.

39.04.290 - Contracts for building engineering systems.

39.04.300 - Apprenticeship training programs—Purpose.

39.04.310 - Apprenticeship training programs—Definitions.

39.04.320 - Apprenticeship training programs—Public works contracts—Adjustment of specific projects—Report and collection of agency data—Apprenticeship utilization advisory committee created.

39.04.330 - Use of wood products—Compliance with chapter 39.35D RCW.

39.04.340 - Apprenticeship and training council outreach effort.

39.04.350 - Bidder responsibility criteria—Sworn statement—Supplemental criteria.

39.04.360 - Payment of undisputed claims.

39.04.370 - Contract requirements—Off-site prefabricated items—Submission of information.

39.04.380 - Preference for resident contractors.

39.04.400 - Repair or replacement of structurally deficient bridges.

39.04.410 - Public works projects—Pollinator habitat.

39.04.420 - Signage for 988 national suicide prevention and mental health crisis hotline.

39.04.900 - Rights may not be waived—Construction—1992 c 223.

39.04.901 - Application—1992 c 223.