39.04.210 - Correctional facilities construction and repair—Findings.

RCW 39.04.210
Correctional facilities construction and repair—Findings.

The legislature recognizes that fair and open competition is a basic tenet of public works procurement, that such competition reduces the appearance of and opportunity for favoritism and inspires public confidence that contracts are awarded equitably and economically, and that effective monitoring mechanisms are important means of curbing any improprieties and establishing public confidence in the process by which contractual services are procured. The legislature finds that there will continue to exist a need for additional correctional facilities due to the inadequate capacity of existing correctional facilities to accommodate the predicted growth of offender populations and that it is necessary to provide public works contract options for the effective construction and repair of additional department of corrections facilities.

[ 1994 c 80 § 1; 1991 c 130 § 1.]
NOTES:

Severability—1994 c 80: "If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected." [ 1994 c 80 § 4.]


Effective date—1994 c 80: "This act is necessary for the immediate preservation of the public peace, health, or safety, or support of the state government and its existing public institutions, and shall take effect immediately [March 23, 1994]." [ 1994 c 80 § 5.]


Severability—1991 c 130: "If any provision of this act or its application to any person or circumstance is held invalid, the remainder of the act or the application of the provision to other persons or circumstances is not affected." [ 1991 c 130 § 4.]

Structure Revised Code of Washington

Revised Code of Washington

Title 39 - Public Contracts and Indebtedness

Chapter 39.04 - Public Works.

39.04.010 - Definitions.

39.04.015 - Adjustment to bid price—Conditions.

39.04.020 - Plans and specifications—Estimates—Publication—Emergencies.

39.04.040 - Work to be executed according to plans—Supplemental plans.

39.04.050 - Contents of original estimates.

39.04.060 - Supplemental estimates.

39.04.070 - Account and record of cost.

39.04.080 - Certified copy to be filed—Engineers' certificate.

39.04.100 - Records open to public inspection—Certified copies.

39.04.105 - Competitive bidding—Written protests—Notice of contract execution.

39.04.107 - Competitive bidding—Bidder claiming error.

39.04.110 - Penalty for false entries.

39.04.120 - Change orders due to environmental protection requirements—Costs—Dispute resolution.

39.04.130 - Application of RCW 39.04.120.

39.04.133 - State capital improvement or construction projects—Product standards.

39.04.135 - Demolition projects—Recycling or reuse of materials.

39.04.155 - Small works roster contract procedures—Limited public works process—Definitions.

39.04.156 - Small works roster manual—Notification to local governments.

39.04.160 - Contracts subject to requirements established under office of minority and women's business enterprises.

39.04.162 - Awards of procurement contracts to veteran-owned businesses.

39.04.170 - Application of chapter to performance-based contracts for energy equipment.

39.04.175 - Application of chapter to certain agreements relating to water pollution control, solid waste handling facilities.

39.04.180 - Trench excavations—Safety systems required.

39.04.190 - Purchase contract process—Other than formal sealed bidding.

39.04.200 - Small works roster or purchase contracts—Listing of contracts awarded required.

39.04.210 - Correctional facilities construction and repair—Findings.

39.04.220 - Correctional facilities construction and repair—Use of general contractor/construction manager method for awarding contracts—Demonstration projects.

39.04.230 - Correctional facilities construction and repair—Alternative contracting method to remain in force until contracts completed.

39.04.235 - Public works contracts—Unit priced contracts—When authorized—Bidding requirements.

39.04.240 - Public works contracts—Awarding of attorneys' fees.

39.04.250 - Payments received on account of work performed by subcontractor—Disputed amounts—Remedies.

39.04.260 - Private construction performed pursuant to contract for rental, lease, or purchase by state—Must comply with prevailing wage law.

39.04.270 - Electronic data processing and telecommunications systems—Municipalities—Acquisition method—Competitive negotiation—Findings, intent.

39.04.280 - Competitive bidding requirements—Exemptions.

39.04.290 - Contracts for building engineering systems.

39.04.300 - Apprenticeship training programs—Purpose.

39.04.310 - Apprenticeship training programs—Definitions.

39.04.320 - Apprenticeship training programs—Public works contracts—Adjustment of specific projects—Report and collection of agency data—Apprenticeship utilization advisory committee created.

39.04.330 - Use of wood products—Compliance with chapter 39.35D RCW.

39.04.340 - Apprenticeship and training council outreach effort.

39.04.350 - Bidder responsibility criteria—Sworn statement—Supplemental criteria.

39.04.360 - Payment of undisputed claims.

39.04.370 - Contract requirements—Off-site prefabricated items—Submission of information.

39.04.380 - Preference for resident contractors.

39.04.400 - Repair or replacement of structurally deficient bridges.

39.04.410 - Public works projects—Pollinator habitat.

39.04.420 - Signage for 988 national suicide prevention and mental health crisis hotline.

39.04.900 - Rights may not be waived—Construction—1992 c 223.

39.04.901 - Application—1992 c 223.