New Mexico Statutes
Article 5 - Appropriation and Use of Surface Water
Section 72-5-25 - Emergency; change of point of diversion; procedure.

A. An appropriator of water may change the place of diversion, storage or use of water upon application to and approval of the state engineer without following the requirements of Section 72-5-23 NMSA 1978 relating to publication of notice if an emergency exists in which the delay caused by following the provisions of Section 72-5-23 NMSA 1978 would result in crop loss or other serious economic loss to the appropriator and if the state engineer determines that no foreseeable detriment exists to rights of others having valid and existing rights to the use of the waters of the stream system. An application under this section shall be in the form and manner prescribed by the state engineer and shall contain specific facts supporting the existence of the emergency.
B. An applicant for approval of a change of place of diversion, storage or use of water under this section shall, within thirty days of an approval granted under this section by the state engineer, comply with the requirements of Section 72-5-23 NMSA 1978.
C. The emergency approval provided under this section shall continue in effect only until the state engineer enters his final decision in accordance with Section 72-5-24 NMSA 1978.
History: 1953 Comp., § 75-5-23.1, enacted by Laws 1971, ch. 162, § 1.
Cross references. — For state engineer, see 72-2-1 NMSA 1978.
Law reviews. — For article, "New Mexico Water Law: An Overview and Discussion of Current Issues," see 22 Nat. Resources J. 1045 (1982).
For article, "Prior Appropriation, Impairment, Replacements, Models and Markets," see 23 Nat. Resources J. 25 (1983).

Structure New Mexico Statutes

New Mexico Statutes

Chapter 72 - Water Law

Article 5 - Appropriation and Use of Surface Water

Section 72-5-1 - Application for permit; rules; surveys, etc.

Section 72-5-2 - Existing community ditches.

Section 72-5-3 - Application; amendment; refiling.

Section 72-5-4 - Notice; publication.

Section 72-5-5 - Objections to applications; filing of protests; definition of standing.

Section 72-5-5.1 - Purposes.

Section 72-5-6 - Hearing; approval; permit.

Section 72-5-7 - Application; rejection; noncompliance with rules; conservation and public welfare.

Section 72-5-8 - Construction of works; additional time.

Section 72-5-9 - Supervision; inspection; completion of works; alterations.

Section 72-5-10 - [State engineer's certificate of construction.]

Section 72-5-11 - Inspection and correction of unsafe works.

Section 72-5-12 - Failure to comply with state engineer order; penalty.

Section 72-5-13 - [Issuance of license to appropriate water.]

Section 72-5-14 - Time for construction; extension.

Section 72-5-15 - [Common use; enlargement and maintenance of works; lien for costs.]

Section 72-5-16 - [Priority of liens.]

Section 72-5-17 - Excess waters; sale.

Section 72-5-18 - Water allowance.

Section 72-5-19 - [Standards for measuring flow and volume of water.]

Section 72-5-20 - Headgates and measuring devices.

Section 72-5-21 - [Recording of permits, decrees and documents; certified copies.]

Section 72-5-22 - [Transfer of water rights.]

Section 72-5-23 - Water appurtenant to land; change of place of use.

Section 72-5-24 - Change of purpose; change of point of diversion.

Section 72-5-24.1 - Acequias and community ditches; changes in point of diversion or place or purpose of use.

Section 72-5-25 - Emergency; change of point of diversion; procedure.

Section 72-5-26 - [Diversion from watershed or into another stream.]

Section 72-5-27 - Artificial water; no right of continuance of supply.

Section 72-5-28 - Failure to use water; forfeiture.

Section 72-5-29 - [Rights of residents of upper valleys of stream systems.]

Section 72-5-30 - [Effect of return flow above diversion or storage works of other appropriators.]

Section 72-5-31 - [Appeal; prior rights not impaired.]

Section 72-5-32 - Construction and operation of dams; state engineer authority.

Section 72-5-33 - Federal reclamation projects; appropriation for.

Section 72-5-34 - State transportation commission; change of water use; application, notice and hearing.

Section 72-5-35 - State transportation commission; advance water withdrawal.

Section 72-5-36 - State transportation commission; unused water accrual; withdrawal rate; accounting.

Section 72-5-37 - State transportation commission; transfer of water rights to unused water; reversion.

Section 72-5-38 - [State water rights for highway purposes and airports; nonforfeiture for failure to use.]

Section 72-5-39 - Illegal application of water; injunction or other relief.