71-3-532. Content of notice of right to claim lien

71-3-532. Content of notice of right to claim lien. (1) The notice of the right to claim a lien must be in writing and state that it is a notice of a right to claim a lien against real estate for services or materials furnished in connection with improvement of the real estate.
(2) The notice must contain a description sufficient to identify the real estate against which the lien may be claimed.
(3) The notice must contain the following information:
(a) date of mailing;
(b) owner's name;
(c) owner's address;
(d) name of person filing notice;
(e) address of person filing notice;
(f) a description sufficient to identify the property that is being improved; and
(g) the following notice:
NOTICE OF THE RIGHT TO CLAIM A LIEN
WARNING: READ THIS NOTICE. PROTECT YOURSELF FROM PAYING ANY CONTRACTOR OR SUPPLIER TWICE FOR THE SAME SERVICE. This is to inform you that .......... has begun to provide .......... (description of services or materials) ordered by .......... for improvements to property you own. The property is located at ......... . If ......... is not paid, a lien may be filed against the property. THIS IS NOT A LIEN. It is a notice sent to you for your protection in compliance with the construction lien laws of the state of Montana.
This notice has been sent to you by:
NAME: ..............
ADDRESS: ...........
TELEPHONE: .........
Under Montana's laws, those who work on your property or provide materials and are not paid have a right to enforce their claim for payment against your property. This claim is known as a construction lien.
If your contractor fails to pay subcontractors or material suppliers or neglects to make other legally required payments, the people who are owed money may look to your property for payment, even if you have paid your contractor in full.
The law states that all people hired by a contractor to provide you with services or materials are required to give you a notice of the right to claim a lien to let you know what they have provided.
WAYS TO PROTECT YOURSELF ARE:
-- RECOGNIZE that this notice of delivery of services or materials may result in a lien against your property unless all those supplying a notice of the right to lien have been paid.
-- LEARN more about the construction lien laws and the meaning of this notice by contacting an attorney or the firm sending this notice.
-- WHEN PAYING your contractor for services or materials, you may make checks payable jointly to the contractor and the firm furnishing services or materials for which you have received a notice of the right to claim a lien.
-- OBTAIN EVIDENCE that all firms from whom you have received a notice of the right to claim a lien have been paid or have waived the right to claim a lien against your property.
-- CONSULT an attorney, a professional escrow company, or your mortgage lender.
History: En. Sec. 8, Ch. 202, L. 1987; amd. Sec. 2, Ch. 484, L. 1991; amd. Sec. 2, Ch. 357, L. 1999.

Structure Montana Code Annotated

Montana Code Annotated

Title 71. Mortgages, Pledges, and Liens

Chapter 3. Liens

Part 5. Construction Liens

71-3-501. Repealed

71-3-502. Repealed

71-3-503. Repealed

71-3-504. Renumbered 71-3-561

71-3-505. Renumbered 71-3-562

71-3-506. through 71-3-510 reserved

71-3-511. Repealed

71-3-512. Renumbered 71-3-533

71-3-513. Renumbered 71-3-534

71-3-514. Repealed

71-3-515. Renumbered 71-3-537

71-3-516. Renumbered 71-3-551

71-3-517. Renumbered 71-3-552

71-3-518. Renumbered 71-3-553

71-3-519. Renumbered 71-3-563

71-3-520. reserved

71-3-521. Scope

71-3-522. Definitions

71-3-523. Who may claim construction lien -- limitation

71-3-524. Limitation of lien for materials supplied

71-3-525. Extent of lien

71-3-526. Amount of lien

71-3-527. through 71-3-530 reserved

71-3-531. Notice of right to claim lien required -- exceptions

71-3-532. Content of notice of right to claim lien

71-3-533. Notice of completion

71-3-534. Filing with county clerk -- notification of owner

71-3-535. Attachment of lien -- filing

71-3-536. Content of lien notice

71-3-537. Acknowledgment of satisfaction of lien -- penalty

71-3-538. Release of notice of right to claim lien

71-3-539. and 71-3-540 reserved

71-3-541. Priority among holders of construction liens

71-3-542. Priority of construction liens as against claims other than construction lien claims

71-3-543. through 71-3-550 reserved

71-3-551. Substitution of bond allowed -- filing -- amount -- condition

71-3-552. Lien discharged upon filing of bond

71-3-553. Action upon bond -- period of limitation same

71-3-554. through 71-3-560 reserved

71-3-561. Parties

71-3-562. Limitation on actions

71-3-563. Rules of practice

71-3-564. Arbitration of lien disputes