18-2-421. Notice. When a public works project is accepted by the public contracting agency, a notice of acceptance and the completion date of the project must be sent to the department. However, in the case of public works contracts that amount to $50,000 or less in cost, the notice of acceptance and the completion date of the project is not required unless the department requests that information. The 90-day limitation for filing an action in district court, as provided in 18-2-407, does not begin until the public contracting agency notifies the department of its acceptance of the public works project.
History: En. Sec. 3, Ch. 139, L. 1981; amd. Sec. 4, Ch. 522, L. 1997.
Structure Montana Code Annotated
Chapter 2. Construction Contracts
Part 4. Special Conditions -- Standard Prevailing Rate of Wages
18-2-402. Standard prevailing rate of wages
18-2-404. Approval of public works contract -- bond
18-2-406. Posting wage scale and fringe benefits
18-2-407. Forfeiture for failure to pay standard prevailing rate of wages
18-2-409. Montana residents to be employed on state construction contracts
18-2-411. Creation of prevailing wage rate districts
18-2-412. Method for payment of standard prevailing wage
18-2-413. Standard prevailing rate of wages for building construction services
18-2-415. Standard prevailing rate of wages for nonconstruction services -- survey
18-2-416. Wages paid to registered apprentices
18-2-417. Wage rate adjustments for multiyear contracts
18-2-418. Wage rates based on project classification
18-2-419. Zone pay and per diem
18-2-423. Submission of payroll records
18-2-425. Prohibition -- project labor agreement
18-2-426. through 18-2-430 reserved