Montana Code Annotated
Part 4. Special Conditions -- Standard Prevailing Rate of Wages
18-2-407. Forfeiture for failure to pay standard prevailing rate of wages

18-2-407. Forfeiture for failure to pay standard prevailing rate of wages. (1) Except as provided in 18-2-403, a contractor, subcontractor, or employer who pays workers or employees at less than the standard prevailing rate of wages as established under the public works contract shall forfeit to the department a penalty at a rate of up to 20% of the delinquent wages plus fringe benefits, attorney fees, audit fees, and court costs. Money collected by the department under this section must be deposited in the general fund. A contractor, subcontractor, or employer shall also forfeit to the employee the amount of wages owed plus $25 a day for each day that the employee was underpaid.
(2) Whenever it appears to the contracting agency or to the commissioner that there is insufficient money due to the contractor or the employer under the terms of the contract to cover penalties, the commissioner may, within 90 days after the filing of notice of completion of the project and its acceptance by the contracting agency, maintain an action in district court to recover all penalties and forfeitures due. This part does not prevent the individual worker who has been underpaid or the commissioner on behalf of all the underpaid workers from maintaining an action for recovery of the wages due under the contract as provided in Title 39, chapter 3, part 2.
History: En. Sec. 1, Ch. 102, L. 1931; re-en. Sec. 3043.1, R.C.M. 1935; amd. Sec. 1, Ch. 32, L. 1955; amd. Sec. 1, Ch. 43, L. 1961; amd. Sec. 1, Ch. 265, L. 1969; amd. Sec. 1, Ch. 375, L. 1973; amd. Sec. 1, Ch. 531, L. 1975; R.C.M. 1947, 41-701(3); amd. Sec. 5, Ch. 554, L. 1989; amd. Sec. 4, Ch. 609, L. 1993; amd. Sec. 4, Ch. 90, L. 1995; amd. Sec. 13, Ch. 389, L. 1999; amd. Sec. 2, Ch. 467, L. 2003; amd. Sec. 14, Ch. 277, L. 2009.

Structure Montana Code Annotated

Montana Code Annotated

Title 18. Public Contracts

Chapter 2. Construction Contracts

Part 4. Special Conditions -- Standard Prevailing Rate of Wages

18-2-401. Definitions

18-2-402. Standard prevailing rate of wages

18-2-403. Preference of Montana labor in public works -- wages -- tax-exempt project -- federal exception

18-2-404. Approval of public works contract -- bond

18-2-405. Repealed

18-2-406. Posting wage scale and fringe benefits

18-2-407. Forfeiture for failure to pay standard prevailing rate of wages

18-2-408. Renumbered 18-2-432

18-2-409. Montana residents to be employed on state construction contracts

18-2-410. reserved

18-2-411. Creation of prevailing wage rate districts

18-2-412. Method for payment of standard prevailing wage

18-2-413. Standard prevailing rate of wages for building construction services

18-2-414. Standard prevailing rate of wages for heavy construction services and for highway construction services -- definition

18-2-415. Standard prevailing rate of wages for nonconstruction services -- survey

18-2-416. Wages paid to registered apprentices

18-2-417. Wage rate adjustments for multiyear contracts

18-2-418. Wage rates based on project classification

18-2-419. Zone pay and per diem

18-2-420. reserved

18-2-421. Notice

18-2-422. Bid specification and public works contract to contain standard prevailing wage rate and payroll record notification

18-2-423. Submission of payroll records

18-2-424. Enforcement

18-2-425. Prohibition -- project labor agreement

18-2-426. through 18-2-430 reserved

18-2-431. Rulemaking authority

18-2-432. Penalty for violation