(a)    (1)    (i)    After completion of all coal removal, backfilling, regrading, and planting on the permit, the operator shall file with the Department a completion report on a form furnished by the Department no later than the time the next mining and reclamation progress report required by § 15–508(b) of this subtitle is to be submitted.
            (ii)    The report shall identify the operation, the area of land affected by the strip mining operation, and identify any area proposed to be reserved for deep mining or any other lawful purpose in accordance with subsection (b) of this section.
        (2)    The completion report shall be accompanied by a completion map. The map shall be prepared and certified by a registered professional engineer or registered land surveyor and contain the following information:
            (i)    The information required by the map under § 15–505(c)(2) of this subtitle;
            (ii)    The surveyed boundaries of the areas affected on the permit;
            (iii)    The surveyed boundaries of all areas which have been backfilled and planted on the permit and indicate the month and year each area was planted;
            (iv)    The surveyed boundaries of any areas proposed to be reserved for deep mining or other purposes under subsection (b) of this section; and
            (v)    A legend which indicates the total acres of the permit, acres affected on the permit, the acres remaining open on the permit, and the acres reserved for deep mining or other purposes.
        (3)    (i)    The Department shall review the completion report.
            (ii)    If the Department determines the report is correct, the report shall be approved.
            (iii)    If the report is not approved, the Department shall notify the operator, in writing, setting forth the reasons for disapproval and identify the action necessary to secure approval.
            (iv)    The operator shall take the action necessary to secure approval of the report.
            (v)    Approval of the completion report by the Department exempts the operator from the filing of further mining and reclamation progress reports on the permit pursuant to § 15–508(b) of this subtitle.
    (b)    If the operator or any other person desires to conduct deep mining on the premises or use a portion of the permit area for haulageways or any other lawful purpose, the operator may designate a location, subject to the Department’s approval, to be used for one or more of these purposes. At a designated and approved location it is not necessary to backfill as required by this subtitle until the deep mining or other use is completed. During this time the bond on file for that portion of the operation may not be released unless a bond as required by Subtitle 6 of this title is filed with the Department. The area of each reserved opening and its location shall be described in the completion report and designated on the attached map. Before commencing operation of a deep mine, a permit must be obtained and a bond filed as required by Subtitle 6 of this title.
    (c)    If within two years after the completion of the strip mining operation deep mining has not been initiated at the proposed location, reclamation shall be completed in accordance with this subtitle.

Structure Maryland Statutes

Maryland Statutes

Environment

Title 15 - Mines and Mining

Subtitle 5 - Strip Mining

Section 15-501 - Definitions

Section 15-502 - Declaration of Policy

Section 15-503 - Rules and Regulations Generally

Section 15-504 - Open-Pit Mining Operator's License

Section 15-505 - Open-Pit Mining Permit Generally

Section 15-506 - Designation of Areas as Unsuitable for Strip Mining

Section 15-507 - Bonds

Section 15-508 - Monthly Report; Annual Report; Mining and Reclamation Progress Report; Inspections and Enforcement Generally; Cease and Desist Orders; Review

Section 15-509 - Mine Reclamation Surcharge; Bond Supplement Surcharge

Section 15-510 - Grading; Sealing Off Openings; Impounding Water; Backfilling and Planting Generally; Alternative Plans for Reclamation; Interference With Operator

Section 15-511 - Completion Report; Reservation for Deep Mining or Other Use; Limitation on Initiation of Deep Mining

Section 15-512 - State Participation in Cost of Revegetation

Section 15-513 - Backfilling and Planting Report; Inspection; Release of Bonds; Continued Liability for Revegetation

Section 15-514 - Revocation of Permit and Forfeiture on Bond

Section 15-514.1 - Reissuance of Permit to Another Qualified Operator

Section 15-515 - Disposition of Funds; Right of Entry

Section 15-516 - Water Supply Replacement Reserve

Section 15-517 - Bond Supplement Reserve

Section 15-518 - Prospecting for Coal

Section 15-519 - Assumption of Certain Costs by Department

Section 15-520 - Penalties Under Subtitle

Section 15-521 - Civil Penalties

Section 15-522 - Liability of Officers or Agents for Corporate Violations

Section 15-523 - Enforcement or Enjoining Violation of Order, Notice, Rule, Regulation, or Permit

Section 15-524 - Protection of Interest in Water Resources; Replacement of Water Supply

Section 15-525 - Blasting or Use of Explosives

Section 15-526 - Oaths and Subpoenas; Record of Hearing

Section 15-527 - State Employees Not to Have Financial Interest

Section 15-528 - Civil Actions

Section 15-529 - Severability