Maine Revised Statutes
Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES
35-A §3146. Climate change protection plan

§3146. Climate change protection plan
No later than December 31, 2023, and every 3 years thereafter, a transmission and distribution utility shall submit to the commission a 10-year plan that includes specific actions for addressing the expected effects of climate change on the utility's assets needed to transmit and distribute electricity to its customers. The commission shall provide a process to allow for the input from interested parties on the transmission and distribution utility's plan. The commission may use the plan and the input received from interested parties in rate cases or other proceedings involving the transmission and distribution utility.   [PL 2021, c. 702, §7 (NEW).]
SECTION HISTORY
PL 2021, c. 702, §7 (NEW).

Structure Maine Revised Statutes

Maine Revised Statutes

TITLE 35-A: PUBLIC UTILITIES

Part 3: ELECTRIC POWER

Chapter 31: GENERAL PROVISIONS

Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES

35-A §3131. Definitions

35-A §3132. Construction of transmission lines prohibited without prior order of the commission

35-A §3132-A. Construction of transmission projects prohibited without approval of the commission

35-A §3132-B. Small transmission and distribution projects

35-A §3132-C. Nonwires alternatives investigation and recommendations

35-A §3132-D. Nonwires alternatives procurement

35-A §3133. Purchase of transmission capacity prohibited without prior order of the commission

35-A §3133-A. Significant agreements and contracts relating to transmission capacity prohibited without prior order of the commission

35-A §3134. Long-range plan

35-A §3134-A. New England Electric Power Pool Agreement (REPEALED)

35-A §3135. Physical connection between lines of utilities authorized

35-A §3136. Transmission and distribution utilities have eminent domain; approval

35-A §3137. Area within which domestic transmission and distribution utility may transmit electricity; taxation by other states

35-A §3138. Joint ownership of facility; waiver of right to partition

35-A §3139. Powers of foreign electric utility (REPEALED)

35-A §3140. Regulation of foreign electric utility

35-A §3141. Taxation

35-A §3142. Registration required to market retail electric service (REPEALED)

35-A §3143. Declaration of policy on smart grid infrastructure

35-A §3144. Emergency response plans

35-A §3145. State energy storage policy goals

35-A §3146. Climate change protection plan

35-A §3147. Integrated grid planning