Maine Revised Statutes
Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES
35-A §3132-B. Small transmission and distribution projects

§3132-B. Small transmission and distribution projects
For the purposes of this section, "small transmission project" means any proposed transmission line and associated infrastructure capable of operating at less than 69 kilovolts and projected to cost $5,000,000 or less.   [PL 2019, c. 298, §13 (NEW).]
1.  Planning study.  Each investor-owned transmission and distribution utility in this State shall annually complete and submit to the Office of the Public Advocate, for review by the nonwires alternative coordinator, a planning study for small transmission projects and distribution projects. In completing the planning study, an investor-owned transmission and distribution utility shall develop and use system planning models. The study must:  
A. Analyze system needs for the next 5 years and provide a schedule of proposed projects and associated costs;   [PL 2019, c. 298, §13 (NEW).]
B. Describe system capacity and load by substation and circuit; and   [PL 2019, c. 298, §13 (NEW).]
C. Identify corresponding planned and anticipated growth-related investments.   [PL 2019, c. 298, §13 (NEW).]
After review of a planning study submitted under this subsection, the nonwires alternative coordinator may provide comments or recommendations, which may include recommendations to achieve the policy goals established in section 3143. An investor-owned transmission and distribution utility may, at its discretion, incorporate recommendations on a planning study made by the nonwires alternative coordinator. Failure to incorporate recommendations made by the nonwires alternative coordinator may not result in a presumption of imprudence.  
[PL 2019, c. 298, §13 (NEW).]
2.  Nonwires alternatives investigation.  Except as provided in subsection 3, for a proposed project presented in a planning study under subsection 1, the nonwires alternative coordinator:  
A. Shall investigate nonwires alternatives if the project is a small transmission project or is a distribution project estimated to cost $500,000 or more; and   [PL 2019, c. 298, §13 (NEW).]
B. May investigate nonwires alternatives if the project is a distribution project estimated to cost less than $500,000 and, in the judgment of the nonwires alternative coordinator, there is a reasonable likelihood that a nonwires alternative would be more cost-effective than the proposed distribution project.   [PL 2019, c. 298, §13 (NEW).]
An investigation of nonwires alternatives under this subsection must be conducted in accordance with section 3132‑C.  
[PL 2019, c. 298, §13 (NEW).]
3.  Excluded projects; criteria.  The commission, by rule, shall develop criteria to exclude from investigation by the nonwires alternative coordinator small transmission projects and distribution projects best suited to transmission and distribution investments, including but not limited to projects that are:  
A. Necessary for redundant supply to a radial load;   [PL 2019, c. 298, §13 (NEW).]
B. Necessary to address maintenance, asset condition or safety needs;   [PL 2019, c. 298, §13 (NEW).]
C. Necessary to address stability or short circuit problems; or   [PL 2019, c. 298, §13 (NEW).]
D. Required to be in service within one year based on the controlling load forecast.   [PL 2019, c. 298, §13 (NEW).]
[PL 2019, c. 298, §13 (NEW).]
4.  Nonwires alternatives recommendations.  Based on the investigation under subsection 2, the nonwires alternative coordinator shall make recommendations to the investor-owned transmission and distribution utility regarding nonwires alternatives to proposed small transmission projects and distribution projects. The nonwires alternative coordinator and the utility shall attempt to reach a good faith agreement regarding the adoption of nonwires alternatives that are most cost-effective. If agreement is reached, the utility shall pursue the agreed-upon nonwires alternatives. If there is no agreement, the utility shall petition the commission to resolve the dispute.  
[PL 2019, c. 298, §13 (NEW).]
5.  Dispute resolution.  In responding to a petition by an investor-owned transmission and distribution utility pursuant to subsection 4, the commission shall review the planning study prepared under subsection 1 and the recommendations of the nonwires alternative coordinator under subsection 4. In resolving the dispute, the commission shall give preference to nonwires alternatives that are identified as able to address the identified need for the proposed small transmission project or distribution project and are most cost-effective. Of the identified nonwires alternatives, the commission shall give preference to the lowest-cost nonwires alternatives. When the costs to ratepayers in this State of the identified nonwires alternatives are reasonably equal, the commission shall give preference to the nonwires alternatives that produce the lowest amount of local air emissions, including greenhouse gas emissions.  
[PL 2019, c. 298, §13 (NEW).]
SECTION HISTORY
PL 2019, c. 298, §13 (NEW).

Structure Maine Revised Statutes

Maine Revised Statutes

TITLE 35-A: PUBLIC UTILITIES

Part 3: ELECTRIC POWER

Chapter 31: GENERAL PROVISIONS

Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES

35-A §3131. Definitions

35-A §3132. Construction of transmission lines prohibited without prior order of the commission

35-A §3132-A. Construction of transmission projects prohibited without approval of the commission

35-A §3132-B. Small transmission and distribution projects

35-A §3132-C. Nonwires alternatives investigation and recommendations

35-A §3132-D. Nonwires alternatives procurement

35-A §3133. Purchase of transmission capacity prohibited without prior order of the commission

35-A §3133-A. Significant agreements and contracts relating to transmission capacity prohibited without prior order of the commission

35-A §3134. Long-range plan

35-A §3134-A. New England Electric Power Pool Agreement (REPEALED)

35-A §3135. Physical connection between lines of utilities authorized

35-A §3136. Transmission and distribution utilities have eminent domain; approval

35-A §3137. Area within which domestic transmission and distribution utility may transmit electricity; taxation by other states

35-A §3138. Joint ownership of facility; waiver of right to partition

35-A §3139. Powers of foreign electric utility (REPEALED)

35-A §3140. Regulation of foreign electric utility

35-A §3141. Taxation

35-A §3142. Registration required to market retail electric service (REPEALED)

35-A §3143. Declaration of policy on smart grid infrastructure

35-A §3144. Emergency response plans

35-A §3145. State energy storage policy goals

35-A §3146. Climate change protection plan

35-A §3147. Integrated grid planning