Maine Revised Statutes
Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES
35-A §3132-C. Nonwires alternatives investigation and recommendations

§3132-C. Nonwires alternatives investigation and recommendations
1.  Investigation required.  The nonwires alternative coordinator shall conduct an investigation of and make recommendations regarding nonwires alternatives to a wires project under section 3132, 3132‑A or 3132‑B in accordance with this section. The investigation must be conducted in coordination with the Efficiency Maine Trust. For the purposes of this section, "wires project" means a transmission line and associated infrastructure subject to the requirements of section 3132, a transmission project as defined in section 3132‑A or a small transmission project or distribution project covered by section 3132‑B.  
[PL 2019, c. 298, §14 (NEW).]
2.  Investigation methods; benefit-cost analysis.  An investigation under subsection 1 must set forth the total projected costs and annual carrying costs of the wires project and the nonwires alternatives over the effective life of the wires project. The investigation must include a benefit-cost analysis that evaluates the cost-effectiveness of nonwires alternatives as compared to the wires project, under which:  
A. Benefits and costs are measured in net present value;   [PL 2019, c. 298, §14 (NEW).]
B. Benefits reflect total, quantifiable avoided costs and are calculated from the perspective of the investor-owned transmission and distribution utility and ratepayers, including any deferral value; and   [PL 2019, c. 298, §14 (NEW).]
C. Costs are calculated from the perspective of the investor-owned transmission and distribution utility. For a nonwires alternative, costs include the utility's cost of any contracts required to deliver the nonwires alternative but do not include any ratepayer contributions to the cost of the nonwires alternative.   [PL 2019, c. 298, §14 (NEW).]
[PL 2019, c. 298, §14 (NEW).]
3.  Data.  An investor-owned transmission and distribution utility shall provide data requested by the Public Advocate or the Efficiency Maine Trust, subject to enforcement by the commission, to allow the nonwires alternative coordinator, in conjunction with the trust, to carry out investigation and analysis under this section. The trust shall use utility ratepayer usage data to identify cost-effective nonwires alternatives on the customer side of the meter. An investor-owned transmission and distribution utility may request a protective order if necessary to protect the confidentiality of data provided under this section in accordance with section 1311‑A.  
[PL 2019, c. 298, §14 (NEW).]
4.  Recommendations.  On the basis of the investigation under subsection 1, the nonwires alternative coordinator shall develop and provide to the commission or to an investor-owned transmission and distribution utility, as appropriate, recommendations regarding cost-effective nonwires alternatives to the wires project, including a proposed plan for procurement of the recommended nonwires alternatives. The proposed procurement plan must be consistent with the provisions of section 3132‑D.  
[PL 2019, c. 298, §14 (NEW).]
SECTION HISTORY
PL 2019, c. 298, §14 (NEW).

Structure Maine Revised Statutes

Maine Revised Statutes

TITLE 35-A: PUBLIC UTILITIES

Part 3: ELECTRIC POWER

Chapter 31: GENERAL PROVISIONS

Subchapter 2: ENERGY PLANNING; CONSTRUCTION; PURCHASES

35-A §3131. Definitions

35-A §3132. Construction of transmission lines prohibited without prior order of the commission

35-A §3132-A. Construction of transmission projects prohibited without approval of the commission

35-A §3132-B. Small transmission and distribution projects

35-A §3132-C. Nonwires alternatives investigation and recommendations

35-A §3132-D. Nonwires alternatives procurement

35-A §3133. Purchase of transmission capacity prohibited without prior order of the commission

35-A §3133-A. Significant agreements and contracts relating to transmission capacity prohibited without prior order of the commission

35-A §3134. Long-range plan

35-A §3134-A. New England Electric Power Pool Agreement (REPEALED)

35-A §3135. Physical connection between lines of utilities authorized

35-A §3136. Transmission and distribution utilities have eminent domain; approval

35-A §3137. Area within which domestic transmission and distribution utility may transmit electricity; taxation by other states

35-A §3138. Joint ownership of facility; waiver of right to partition

35-A §3139. Powers of foreign electric utility (REPEALED)

35-A §3140. Regulation of foreign electric utility

35-A §3141. Taxation

35-A §3142. Registration required to market retail electric service (REPEALED)

35-A §3143. Declaration of policy on smart grid infrastructure

35-A §3144. Emergency response plans

35-A §3145. State energy storage policy goals

35-A §3146. Climate change protection plan

35-A §3147. Integrated grid planning