Sec. 13. Except as otherwise allowed by IC 36-7-4-1109, if a project owner installs a CSE system in a unit, all cables of up to thirty-four and one-half (34.5) kilovolts that are located between inverter locations and project substations shall be located and maintained underground, as feasible. Other solar infrastructure, such as module-to-module collection cables, transmission lines, substations, junction boxes, and other typical aboveground infrastructure may be located and maintained above ground. Buried cables shall be at a depth of at least thirty-six (36) inches below grade or, if necessitated by onsite conditions, at a greater depth. Cables and lines located outside of the CSE system project site may:
(1) be located above ground; or
(2) in the case of cables or lines of up to thirty-four and one-half (34.5) kilovolts, be buried underground at:
(A) a depth of at least forty-eight (48) inches below grade, so as to not interfere with drainage tile or ditch repairs; or
(B) another depth, as necessitated by conditions;
as determined in consultation with the landowner.
As added by P.L.90-2022, SEC.2.
Structure Indiana Code
Title 8. Utilities and Transportation
Article 1. Utilities Generally
Chapter 42. Default Standards for Commercial Solar Energy Systems
8-1-42-1. Applicability; "Solar Energy Ready Community"
8-1-42-2. "Commercial Solar Energy System"
8-1-42-3. "Commercial Solar Regulation"
8-1-42-5. "Nonparticipating Property"
8-1-42-11. Ground Cover; Vegetation Plan
8-1-42-14. Glare Minimization; Adjacent Properties and Roadways; Vehicular Traffic
8-1-42-15. Signal Interference
8-1-42-17. Damage to Drainage Infrastructure; Repair; Installation of New Infrastructure