Sec. 13. Except as otherwise allowed by IC 36-7-4-1109, if a project owner installs a CSE system in a unit, all cables of up to thirty-four and one-half (34.5) kilovolts that are located between inverter locations and project substations shall be located and maintained underground, as feasible. Other solar infrastructure, such as module-to-module collection cables, transmission lines, substations, junction boxes, and other typical aboveground infrastructure may be located and maintained above ground. Buried cables shall be at a depth of at least thirty-six (36) inches below grade or, if necessitated by onsite conditions, at a greater depth. Cables and lines located outside of the CSE system project site may:
(1) be located above ground; or
(2) in the case of cables or lines of up to thirty-four and one-half (34.5) kilovolts, be buried underground at:
(A) a depth of at least forty-eight (48) inches below grade, so as to not interfere with drainage tile or ditch repairs; or
(B) another depth, as necessitated by conditions;
as determined in consultation with the landowner.
As added by P.L.90-2022, SEC.2.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 42. Default Standards for Commercial Solar Energy Systems

8-1-42-1. Applicability; "Solar Energy Ready Community"

8-1-42-2. "Commercial Solar Energy System"

8-1-42-3. "Commercial Solar Regulation"

8-1-42-4. "Dwelling"

8-1-42-5. "Nonparticipating Property"

8-1-42-6. "Permit Authority"

8-1-42-7. "Project Owner"

8-1-42-8. "Unit"

8-1-42-9. Permit Authority Responsible for Enforcing Compliance With Standards; Authority to Adopt Less Restrictive Standards or to Waive or Make Less Restrictive Existing Standards; Unit's Planning and Zoning Powers Not Affected

8-1-42-10. Setback Requirements; Highways, Collector Roads, and Local Roads; Nonparticipating Properties; Landscape Buffer; Height Restriction; Waiver of Setback and Buffer Requirements With Consent of Nonparticipating Property Owner

8-1-42-11. Ground Cover; Vegetation Plan

8-1-42-12. Fencing

8-1-42-13. Underground Cables; Aboveground Infrastructure; Depth of Buried Cables; Cables and Lines Outside of Project Site

8-1-42-14. Glare Minimization; Adjacent Properties and Roadways; Vehicular Traffic

8-1-42-15. Signal Interference

8-1-42-16. Sound Level Limitations; Waiver of Requirement With Consent of Owners of Adjacent Nonparticipating Properties

8-1-42-17. Damage to Drainage Infrastructure; Repair; Installation of New Infrastructure

8-1-42-18. Decommissioning and Site Restoration Plan; Posting of Surety Bond or Equivalent Security; Required Posting Increments; Adjustment of Bond or Security After Periodic Reevaluation of Decommissioning Costs; Costs to Be Net of Estimated Salvag...

8-1-42-19. Cse System's Failure to Generate Electricity; Presumed Abandonment; Required Removal of Project Assets; Project Owner's Failure to Remove Assets; Removal of Assets by Permit Authority; Recovery of Costs

8-1-42-20. "Force Majeure Event"; Cessation of Electricity Generation; Project Owner's Notice to Permit Authority; Failure to Resume Operations; Presumed Abandonment; Project Owner's Failure to Remove Assets; Removal of Assets by Permit Authority; Re...