Indiana Code
Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals
8-1-39-9. Petition for Tdsic; Annual Plan Update; Recovery and Deferral of Tdsic Costs; Limits on Timing of Petitions

Sec. 9. (a) Subject to subsection (d), a public utility that provides electric or gas utility service may file with the commission rate schedules establishing a TDSIC that will allow the periodic automatic adjustment of the public utility's basic rates and charges to provide for timely recovery of eighty percent (80%) of approved capital expenditures and TDSIC costs. The petition must:
(1) use the customer class revenue allocation factor based on firm load approved in the public utility's most recent retail base rate case order;
(2) include the public utility's TDSIC plan for eligible transmission, distribution, and storage system improvements; and
(3) identify projected effects of the plan described in subdivision (2) on retail rates and charges.
The public utility shall provide a copy of the petition to the office of the utility consumer counselor when the petition is filed with the commission.
(b) The public utility shall update the public utility's TDSIC plan under subsection (a)(2) at least annually. An update may include a petition for approval of:
(1) a targeted economic development project under section 11 of this chapter; or
(2) transmission, distribution, and storage system improvements not described in the public utility's TDSIC plan most recently approved by the commission under section 10 of this chapter.
(c) A public utility that recovers capital expenditures and TDSIC costs under subsection (a) shall defer the remaining twenty percent (20%) of approved capital expenditures and TDSIC costs, including depreciation, allowance for funds used during construction, and post in service carrying costs, and shall recover those capital expenditures and TDSIC costs as part of the next general rate case that the public utility files with the commission.
(d) Except as provided in section 15 of this chapter, a public utility may not file a petition under subsection (a) within nine (9) months after the date on which the commission issues an order changing the public utility's basic rates and charges with respect to the same type of utility service.
(e) A public utility that implements a TDSIC under this chapter shall, before the expiration of the public utility's approved TDSIC plan, petition the commission for review and approval of the public utility's basic rates and charges with respect to the same type of utility service.
(f) A public utility may file a petition under this section not more than one (1) time every six (6) months.
(g) Actual capital expenditures and TDSIC costs that exceed the approved capital expenditures and TDSIC costs require specific justification by the public utility and specific approval by the commission before being authorized for recovery in customer rates.
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.3.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals

8-1-39-1. Application of Definitions in Ic 8-1-2-1

8-1-39-2. "Eligible Transmission, Distribution, and Storage System Improvements"

8-1-39-3. "Pretax Return"

8-1-39-4. "Public Utility"

8-1-39-5. "Targeted Economic Development Project"

8-1-39-6. "Tdsic"

8-1-39-7. "Tdsic Costs"

8-1-39-7.8. "Tdsic Plan"

8-1-39-8. "Tdsic Revenues"

8-1-39-9. Petition for Tdsic; Annual Plan Update; Recovery and Deferral of Tdsic Costs; Limits on Timing of Petitions

8-1-39-10. Petition for Approval of Tdsic Plan; Notice, Hearing, and Order; Approval and Authorization of Tdsic Treatment; Targeted Economic Development Projects; Termination of Existing Plan

8-1-39-11. Extension of Gas or Electric Service to Targeted Economic Development Project; Approval by Indiana Economic Development Corporation of Costs as Tdsic Costs; Rural Gas Service

8-1-39-12. Commission Hearing and Order on Tdsic Petition; Examination by Utility Consumer Counselor and Intervenors; New Projects or Improvements

8-1-39-13. Determination of Pretax Return

8-1-39-14. Limit on Increase in Utility's Total Retail Revenues Resulting From Tdsic; Combined Revenue Impact of Tdsic Under Terminated Plan and Tdsic Under New Plan

8-1-39-15. Revised Rate Schedule Following General Increase in Rates and Charges

8-1-39-16. Exclusions From General Increase in Basic Rates and Charges

8-1-39-17. Adoption of Rules