Indiana Code
Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals
8-1-39-14. Limit on Increase in Utility's Total Retail Revenues Resulting From Tdsic; Combined Revenue Impact of Tdsic Under Terminated Plan and Tdsic Under New Plan

Sec. 14. (a) The commission may not approve a TDSIC that would result in an average aggregate increase in a public utility's total retail revenues of more than two percent (2%) in a twelve (12) month period. For purposes of this subsection, a public utility's total retail revenues do not include TDSIC revenues associated with a targeted economic development project.
(b) If a public utility incurs TDSIC costs under the public utility's TDSIC plan that exceed the percentage increase in a TDSIC approved by the commission, the public utility shall defer recovery of the TDSIC costs as set forth in section 9(c) of this chapter.
(c) For purposes of subsection (a), in the case of a public utility that terminates a TDSIC plan under section 10(d) of this chapter, the commission shall consider the combined twelve (12) month revenue impact of the TDSIC approved under the terminated plan and the TDSIC approved under any new TDSIC plan.
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.7.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals

8-1-39-1. Application of Definitions in Ic 8-1-2-1

8-1-39-2. "Eligible Transmission, Distribution, and Storage System Improvements"

8-1-39-3. "Pretax Return"

8-1-39-4. "Public Utility"

8-1-39-5. "Targeted Economic Development Project"

8-1-39-6. "Tdsic"

8-1-39-7. "Tdsic Costs"

8-1-39-7.8. "Tdsic Plan"

8-1-39-8. "Tdsic Revenues"

8-1-39-9. Petition for Tdsic; Annual Plan Update; Recovery and Deferral of Tdsic Costs; Limits on Timing of Petitions

8-1-39-10. Petition for Approval of Tdsic Plan; Notice, Hearing, and Order; Approval and Authorization of Tdsic Treatment; Targeted Economic Development Projects; Termination of Existing Plan

8-1-39-11. Extension of Gas or Electric Service to Targeted Economic Development Project; Approval by Indiana Economic Development Corporation of Costs as Tdsic Costs; Rural Gas Service

8-1-39-12. Commission Hearing and Order on Tdsic Petition; Examination by Utility Consumer Counselor and Intervenors; New Projects or Improvements

8-1-39-13. Determination of Pretax Return

8-1-39-14. Limit on Increase in Utility's Total Retail Revenues Resulting From Tdsic; Combined Revenue Impact of Tdsic Under Terminated Plan and Tdsic Under New Plan

8-1-39-15. Revised Rate Schedule Following General Increase in Rates and Charges

8-1-39-16. Exclusions From General Increase in Basic Rates and Charges

8-1-39-17. Adoption of Rules