Indiana Code
Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals
8-1-39-2. "Eligible Transmission, Distribution, and Storage System Improvements"

Sec. 2. (a) As used in this chapter, "eligible transmission, distribution, and storage system improvements" means new or replacement electric or gas transmission, distribution, or storage utility projects that:
(1) a public utility undertakes for purposes of safety, reliability, system modernization, or economic development, including the extension of gas service to rural areas;
(2) were not included in the public utility's rate base in its most recent general rate case; and
(3) either were:
(A) described in the public utility's TDSIC plan and approved by the commission under section 10 of this chapter and authorized for TDSIC treatment;
(B) described in the public utility's update to the public utility's TDSIC plan under section 9 of this chapter and authorized for TDSIC treatment by the commission; or
(C) approved as a targeted economic development project under section 11 of this chapter.
(b) The term includes:
(1) projects that do not include specific locations or an exact number of inspections, repairs, or replacements, including inspection based projects such as pole or pipe inspection projects, and pole or pipe replacement projects; and
(2) projects involving advanced technology investments to support the modernization of a transmission, distribution, or storage system, such as advanced metering infrastructure, information technology systems, or distributed energy resource management systems.
As added by P.L.133-2013, SEC.5. Amended by P.L.89-2019, SEC.1.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 39. Transmission, Distribution, and Storage System Improvement Charges and Deferrals

8-1-39-1. Application of Definitions in Ic 8-1-2-1

8-1-39-2. "Eligible Transmission, Distribution, and Storage System Improvements"

8-1-39-3. "Pretax Return"

8-1-39-4. "Public Utility"

8-1-39-5. "Targeted Economic Development Project"

8-1-39-6. "Tdsic"

8-1-39-7. "Tdsic Costs"

8-1-39-7.8. "Tdsic Plan"

8-1-39-8. "Tdsic Revenues"

8-1-39-9. Petition for Tdsic; Annual Plan Update; Recovery and Deferral of Tdsic Costs; Limits on Timing of Petitions

8-1-39-10. Petition for Approval of Tdsic Plan; Notice, Hearing, and Order; Approval and Authorization of Tdsic Treatment; Targeted Economic Development Projects; Termination of Existing Plan

8-1-39-11. Extension of Gas or Electric Service to Targeted Economic Development Project; Approval by Indiana Economic Development Corporation of Costs as Tdsic Costs; Rural Gas Service

8-1-39-12. Commission Hearing and Order on Tdsic Petition; Examination by Utility Consumer Counselor and Intervenors; New Projects or Improvements

8-1-39-13. Determination of Pretax Return

8-1-39-14. Limit on Increase in Utility's Total Retail Revenues Resulting From Tdsic; Combined Revenue Impact of Tdsic Under Terminated Plan and Tdsic Under New Plan

8-1-39-15. Revised Rate Schedule Following General Increase in Rates and Charges

8-1-39-16. Exclusions From General Increase in Basic Rates and Charges

8-1-39-17. Adoption of Rules