Indiana Code
Chapter 27. Environmental Compliance Plans
8-1-27-16. Utility's Recovery of Expenditures Due to Plan Modification

Sec. 16. If the commission issues an order under sections 8, 11, or 18 of this chapter that approves modifications to a public utility's environmental compliance plan, the commission shall, absent fraud, concealment, gross mismanagement, or inadequate quality control, allow the public utility to recover under sections 12(a) and 12(b) of this chapter, to the extent permitted under sections 12(a) and 12(b) of this chapter, the following:
(1) The public utility's expenditures made under the environmental compliance plan before the date the commission issued the order approving the modified environmental compliance plan.
(2) The public utility's expenditures made under the modified environmental compliance plan after the date the commission issued the order approving the modified environmental compliance plan.
As added by P.L.76-1991, SEC.1.

Structure Indiana Code

Indiana Code

Title 8. Utilities and Transportation

Article 1. Utilities Generally

Chapter 27. Environmental Compliance Plans

8-1-27-1. "Clean Air Act" Defined

8-1-27-2. "Clean Air Act Amendments of 1990" Defined

8-1-27-3. "Environmental Compliance Plan" Defined

8-1-27-4. "Indiana Coal" Defined

8-1-27-5. "Public Utility" Defined

8-1-27-5.5. "Change of Fuel Type" Defined

8-1-27-6. Environmental Compliance Plan; Required Information

8-1-27-7. Public Hearing on Plan; Notice

8-1-27-8. Order Approving Plan; Conditions

8-1-27-9. Rejection of Plan; Modified Plan; Withdrawal of Plan Without Prejudice

8-1-27-10. Submission of Plan to Government Environmental Agency; Conflicts

8-1-27-11. Modification of Previously Approved Plan; Review by Commission

8-1-27-12. Recovery of Costs by Public Utility for Capital Projects or Implemented Plan

8-1-27-13. Revised Cost and Schedule Estimate for Developing and Implementing Plan; Submission to Commission

8-1-27-14. Plan Exceeding Clean Air Act Amendments of 1990 Requirements; Credits or Additional Benefits

8-1-27-15. General Rate Proceedings; Consideration of Change in Risk to Utility Following Approval of Plan

8-1-27-16. Utility's Recovery of Expenditures Due to Plan Modification

8-1-27-17. Recovery of Costs Incurred by Utility in Implementing Measure Set Forth in Plan but Disapproved by Commission Upon Review

8-1-27-18. Review of Plan by Commission; Withdrawal of Approval or Modification of Plan

8-1-27-19. Ongoing Review of Cost and Implementation of Plan; Progress Report; Recovery of Costs; Approval or Disapproval by Commission; Effect

8-1-27-20. Annual Plan Review; Compliance With Ic 8-1-27-8

8-1-27-21. Repealed

8-1-27-22. Contract for Sale and Purchase of Coal; Effect of Chapter

8-1-27-23. Voluntary Nature of Chapter Procedures