Sec. 13. (a) If a public utility makes a substantial change in a cost and schedule estimate for developing and implementing an environmental compliance plan or a modified environmental compliance plan after the estimate has been approved by the commission under this chapter, the public utility shall file with the commission for the commission's review and approval the revised cost and schedule estimate.
(b) To the extent the commission approves a revised cost and schedule estimate, the estimate shall be the approved cost and schedule estimate for the plan.
As added by P.L.76-1991, SEC.1.
Structure Indiana Code
Title 8. Utilities and Transportation
Article 1. Utilities Generally
Chapter 27. Environmental Compliance Plans
8-1-27-1. "Clean Air Act" Defined
8-1-27-2. "Clean Air Act Amendments of 1990" Defined
8-1-27-3. "Environmental Compliance Plan" Defined
8-1-27-4. "Indiana Coal" Defined
8-1-27-5. "Public Utility" Defined
8-1-27-5.5. "Change of Fuel Type" Defined
8-1-27-6. Environmental Compliance Plan; Required Information
8-1-27-7. Public Hearing on Plan; Notice
8-1-27-8. Order Approving Plan; Conditions
8-1-27-9. Rejection of Plan; Modified Plan; Withdrawal of Plan Without Prejudice
8-1-27-10. Submission of Plan to Government Environmental Agency; Conflicts
8-1-27-11. Modification of Previously Approved Plan; Review by Commission
8-1-27-12. Recovery of Costs by Public Utility for Capital Projects or Implemented Plan
8-1-27-16. Utility's Recovery of Expenditures Due to Plan Modification
8-1-27-18. Review of Plan by Commission; Withdrawal of Approval or Modification of Plan
8-1-27-20. Annual Plan Review; Compliance With Ic 8-1-27-8
8-1-27-22. Contract for Sale and Purchase of Coal; Effect of Chapter