Sec. 19. (a) This chapter does not prohibit or limit the commissioner from withdrawing the commissioner's approval of a voluntary remediation work plan at any time during the implementation of the work plan if:
(1) the person implementing the work plan fails substantially to comply with the terms and conditions of:
(A) the voluntary remediation work plan; or
(B) a voluntary remediation agreement; or
(2) a hazardous substance or petroleum becomes an imminent and substantial threat to human health or the environment.
(b) The withdrawal of the approval of a voluntary remediation work plan may be appealed under IC 4-21.5.
[Pre-1996 Recodification Citation: 13-7-8.9-19.]
As added by P.L.1-1996, SEC.15. Amended by P.L.59-1997, SEC.22.

Structure Indiana Code

Indiana Code

Title 13. Environment

Article 25. Hazardous Substances

Chapter 5. Voluntary Remediation of Hazardous Substances and Petroleum

13-25-5-1. Intent of Chapter

13-25-5-2. Application; Confidentiality; Conditions; Fee

13-25-5-3. Environmental Assessment; Contents

13-25-5-4. Determination of Applicant Eligibility

13-25-5-5. Rejection of Application; Reasons; Completeness; List of Information; Department Duties

13-25-5-6. Rejection of Application; Appeal; Submission of Completed Application; Refund

13-25-5-7. Voluntary Remediation Investigation Plan; Voluntary Remediation Work Plan; Contents

13-25-5-8. Voluntary Remediation Agreement; Contents; Failure to Reach Accord Within Reasonable Time After Good Faith Negotiations

13-25-5-8.5. Voluntary Remediation Work Plan Objectives; Additional Action to Protect Human Health and the Environment Not Necessary Under Certain Circumstances; Risk Based Remediation Objectives and Proposals

13-25-5-9. Review and Evaluation; Additional or Corrected Information

13-25-5-10. Voluntary Remediation Work Plan; Approval, Modification, or Rejection

13-25-5-11. Voluntary Remediation Work Plan; Placement in Public Library; Notice; Comment Period; Hearing

13-25-5-12. Voluntary Remediation Work Plan; Rejection; Notice; Appeal

13-25-5-13. Voluntary Remediation Work Plan; Approval or Modification; Notice

13-25-5-14. Voluntary Remediation Work Plan; Implementation; Notice

13-25-5-15. Voluntary Remediation Work Plan; Implementation; Reports

13-25-5-16. Certificate of Completion

13-25-5-17. Notice of Unsuccessful Completion

13-25-5-18. Covenant Not to Sue; Conditions in Covenants Not to Sue and Certificates of Completion; Immunity From Actions; Exceptions

13-25-5-19. Withdrawing Commissioner's Approval of Voluntary Remediation Work Plan; Appeal

13-25-5-20. Third Party Actions or Claims; Liability for Claims for Contribution

13-25-5-21. Voluntary Remediation Fund

13-25-5-22. Repealed

13-25-5-23. Rules