Sec. 11. (a) Before the commissioner approves or rejects a proposed voluntary remediation work plan under section 10 of this chapter, the commissioner must:
(1) notify local government units located in a county affected by the proposed voluntary remediation work plan of the work plan;
(2) provide that a copy of the proposed voluntary remediation work plan be placed in at least one (1) public library in a county affected by the work plan; and
(3) publish a notice requesting comments concerning the proposed voluntary remediation work plan.
(b) A comment period of at least thirty (30) days must follow publication of a notice under this section. During a comment period, interested persons may do the following:
(1) Submit written comments to the commissioner concerning the proposed voluntary remediation work plan.
(2) Request a public hearing concerning the proposed voluntary remediation work plan.
(c) If the commissioner receives at least one (1) written request, the commissioner may hold a public hearing in the geographical area affected by the proposed voluntary remediation work plan on the question of whether to approve or reject the work plan. The commissioner shall consider all written comments and public testimony.
[Pre-1996 Recodification Citation: 13-7-8.9-15(b).]
As added by P.L.1-1996, SEC.15.
Structure Indiana Code
Article 25. Hazardous Substances
Chapter 5. Voluntary Remediation of Hazardous Substances and Petroleum
13-25-5-2. Application; Confidentiality; Conditions; Fee
13-25-5-3. Environmental Assessment; Contents
13-25-5-4. Determination of Applicant Eligibility
13-25-5-5. Rejection of Application; Reasons; Completeness; List of Information; Department Duties
13-25-5-6. Rejection of Application; Appeal; Submission of Completed Application; Refund
13-25-5-7. Voluntary Remediation Investigation Plan; Voluntary Remediation Work Plan; Contents
13-25-5-9. Review and Evaluation; Additional or Corrected Information
13-25-5-10. Voluntary Remediation Work Plan; Approval, Modification, or Rejection
13-25-5-12. Voluntary Remediation Work Plan; Rejection; Notice; Appeal
13-25-5-13. Voluntary Remediation Work Plan; Approval or Modification; Notice
13-25-5-14. Voluntary Remediation Work Plan; Implementation; Notice
13-25-5-15. Voluntary Remediation Work Plan; Implementation; Reports
13-25-5-16. Certificate of Completion
13-25-5-17. Notice of Unsuccessful Completion
13-25-5-19. Withdrawing Commissioner's Approval of Voluntary Remediation Work Plan; Appeal
13-25-5-20. Third Party Actions or Claims; Liability for Claims for Contribution