Sec. 13. If the commissioner approves or modifies and approves a proposed voluntary remediation work plan under this chapter, the commissioner shall notify the applicant in writing, under the applicable provisions set forth in IC 4-21.5-3-5(b) and IC 4-21.5-3-5(c), of the following:
(1) That the voluntary remediation work plan has been approved or modified and approved.
(2) The date:
(A) the applicant may begin implementing the work plan; and
(B) by which the work plan must be completed.
(3) The applicant's right to appeal the commissioner's decision under IC 4-21.5.
[Pre-1996 Recodification Citation: 13-7-8.9-15(d).]
As added by P.L.1-1996, SEC.15.
Structure Indiana Code
Article 25. Hazardous Substances
Chapter 5. Voluntary Remediation of Hazardous Substances and Petroleum
13-25-5-2. Application; Confidentiality; Conditions; Fee
13-25-5-3. Environmental Assessment; Contents
13-25-5-4. Determination of Applicant Eligibility
13-25-5-5. Rejection of Application; Reasons; Completeness; List of Information; Department Duties
13-25-5-6. Rejection of Application; Appeal; Submission of Completed Application; Refund
13-25-5-7. Voluntary Remediation Investigation Plan; Voluntary Remediation Work Plan; Contents
13-25-5-9. Review and Evaluation; Additional or Corrected Information
13-25-5-10. Voluntary Remediation Work Plan; Approval, Modification, or Rejection
13-25-5-12. Voluntary Remediation Work Plan; Rejection; Notice; Appeal
13-25-5-13. Voluntary Remediation Work Plan; Approval or Modification; Notice
13-25-5-14. Voluntary Remediation Work Plan; Implementation; Notice
13-25-5-15. Voluntary Remediation Work Plan; Implementation; Reports
13-25-5-16. Certificate of Completion
13-25-5-17. Notice of Unsuccessful Completion
13-25-5-19. Withdrawing Commissioner's Approval of Voluntary Remediation Work Plan; Appeal
13-25-5-20. Third Party Actions or Claims; Liability for Claims for Contribution