(1)(a) If, subsequent to certification, a licensee proposes any material change to the application or prior amendments, the licensee shall submit to the department a written request for amendment and description of the proposed change to the application. The department shall, within 30 days after the receipt of the request for the amendment, determine whether the proposed change to the application requires a modification of the conditions of certification.
(b) If the department concludes that the change would not require a modification of the conditions of certification, the department shall notify, in writing, the licensee, all agencies, and all parties of the approval of the amendment.
(c) If the department concludes that the change would require a modification of the conditions of certification, the department shall notify the licensee that the proposed change to the application requires a request for modification under s. 403.5315.
(2) Postcertification submittals filed by a licensee with one or more agencies are for the purpose of monitoring for compliance with the issued certification. Each submittal must be reviewed by each agency on an expedited and priority basis because each facility certified under this act is a critical infrastructure facility. Postcertification review may not be completed more than 90 days after complete information for a segment of the certified transmission line is submitted to the reviewing agencies.
History.—s. 63, ch. 2006-230.
Structure Florida Statutes
Chapter 403 - Environmental Control
Part II - Electrical Power Plant and Transmission Line Siting (Ss. 403.501-403.539)
403.503 - Definitions relating to Florida Electrical Power Plant Siting Act.
403.504 - Department of Environmental Protection; powers and duties enumerated.
403.5055 - Application for permits pursuant to s. 403.0885.
403.506 - Applicability, thresholds, and certification.
403.5063 - Notice of intent to file application.
403.5064 - Application; schedules.
403.5065 - Appointment of administrative law judge; powers and duties.
403.5066 - Determination of completeness.
403.50663 - Informational public meetings.
403.50665 - Land use consistency.
403.507 - Preliminary statements of issues, reports, project analyses, and studies.
403.508 - Land use and certification hearings, parties, participants.
403.509 - Final disposition of application.
403.5095 - Alteration of time limits.
403.510 - Superseded laws, regulations, and certification power.
403.511 - Effect of certification.
403.5112 - Filing of notice of certified corridor route.
403.5113 - Postcertification amendments and review.
403.5116 - County and municipal authority unaffected by ch. 75-22.
403.512 - Revocation or suspension of certification.
403.514 - Enforcement of compliance.
403.515 - Availability of information.
403.516 - Modification of certification.
403.517 - Supplemental applications for sites certified for ultimate site capacity.
403.5175 - Existing electrical power plant site certification.
403.5185 - Law applicable to applications processed under ss. 403.501-403.518.
403.519 - Exclusive forum for determination of need.
403.522 - Definitions relating to the Florida Electric Transmission Line Siting Act.
403.523 - Department of Environmental Protection; powers and duties.
403.524 - Applicability; certification; exemptions.
403.525 - Administrative law judge; appointment; powers and duties.
403.5251 - Application; schedules.
403.5252 - Determination of completeness.
403.526 - Preliminary statements of issues, reports, and project analyses; studies.
403.527 - Certification hearing, parties, participants.
403.5271 - Alternate corridors.
403.5272 - Informational public meetings.
403.5275 - Amendment to the application.
403.528 - Alteration of time limits.
403.529 - Final disposition of application.
403.531 - Effect of certification.
403.5312 - Filing of notice of certified corridor route.
403.5315 - Modification of certification.
403.5317 - Postcertification activities.
403.532 - Revocation or suspension of certification.
403.533 - Enforcement of compliance.
403.536 - Superseded laws, regulations, and certification power.
403.5363 - Public notices; requirements.
403.537 - Determination of need for transmission line; powers and duties.
403.539 - Certification admissible in eminent domain proceedings; attorney’s fees and costs.