403.501 - Short title. - History.—s. 1, ch. 73-33; s. 1, ch. 76-76; s. 1,...
403.502 - Legislative intent. - (1) To assure the citizens of Florida that operation safeguards...
403.503 - Definitions relating to Florida Electrical Power Plant Siting Act. - (1) “Act” means the Florida Electrical Power Plant Siting Act....
403.504 - Department of Environmental Protection; powers and duties enumerated. - (1) To adopt rules pursuant to ss. 120.536(1) and 120.54...
403.5055 - Application for permits pursuant to s. 403.0885. - (1) The procedural requirements set forth in 40 C.F.R. s....
403.506 - Applicability, thresholds, and certification. - (1) The provisions of this act shall apply to any...
403.5063 - Notice of intent to file application. - (1) To expedite the processing of the application which may...
403.5064 - Application; schedules. - (1) The formal date of filing of a certification application...
403.5065 - Appointment of administrative law judge; powers and duties. - (1) Within 7 days after receipt of an application, the...
403.5066 - Determination of completeness. - (1)(a) Within 30 days after the filing of an application,...
403.50663 - Informational public meetings. - (1) A local government within whose jurisdiction the power plant...
403.50665 - Land use consistency. - (1) The applicant shall include in the application a statement...
403.507 - Preliminary statements of issues, reports, project analyses, and studies. - (1) Each affected agency identified in paragraph (2)(a) shall submit...
403.508 - Land use and certification hearings, parties, participants. - (1)(a) Within 5 days after the filing of a petition...
403.509 - Final disposition of application. - (1)(a) If the administrative law judge has granted a request...
403.5095 - Alteration of time limits. - History.—s. 8, ch. 76-76; s. 13, ch. 90-331; s. 142,...
403.510 - Superseded laws, regulations, and certification power. - (1) If any provision of this act is in conflict...
403.511 - Effect of certification. - (1) Subject to the conditions set forth therein, any certification...
403.5112 - Filing of notice of certified corridor route. - (1) Within 60 days after certification of an associated linear...
403.5113 - Postcertification amendments and review. - (1) POSTCERTIFICATION AMENDMENTS.— (a) If, subsequent to certification by the...
403.5115 - Public notice. - (1) The following notices are to be published by the...
403.5116 - County and municipal authority unaffected by ch. 75-22. - History.—s. 22, ch. 75-22; s. 17, ch. 90-331. Note.—Former s....
403.512 - Revocation or suspension of certification. - (1) For any material false statement in the application or...
403.513 - Review. - History.—s. 1, ch. 73-33; s. 12, ch. 76-76; s. 29,...
403.514 - Enforcement of compliance. - History.—s. 1, ch. 73-33; s. 12, ch. 76-76; s. 20,...
403.515 - Availability of information. - History.—s. 1, ch. 73-33.
403.516 - Modification of certification. - (1) A certification may be modified after issuance in any...
403.517 - Supplemental applications for sites certified for ultimate site capacity. - (1)(a) Supplemental applications may be submitted for certification of the...
403.5175 - Existing electrical power plant site certification. - (1) An electric utility that owns or operates an existing...
403.518 - Fees; disposition. - (1) A fee for a notice of intent pursuant to...
403.5185 - Law applicable to applications processed under ss. 403.501-403.518. - History.—s. 42, ch. 2006-230.
403.519 - Exclusive forum for determination of need. - (1) On request by an applicant or on its own...
403.52 - Short title. - History.—s. 1, ch. 80-65; s. 25, ch. 90-331; s. 45,...
403.521 - Legislative intent. - History.—s. 1, ch. 80-65; s. 2, ch. 83-222; s. 26,...
403.522 - Definitions relating to the Florida Electric Transmission Line Siting Act. - (1) “Act” means the Florida Electric Transmission Line Siting Act....
403.523 - Department of Environmental Protection; powers and duties. - (1) To adopt procedural rules pursuant to ss. 120.536(1) and...
403.524 - Applicability; certification; exemptions. - (1) This act applies to each transmission line, except a...
403.525 - Administrative law judge; appointment; powers and duties. - (1)(a) Within 7 days after receipt of an application, whether...
403.5251 - Application; schedules. - (1)(a) The formal date of the filing of the application...
403.5252 - Determination of completeness. - (1)(a) Within 30 days after the filing of an application,...
403.526 - Preliminary statements of issues, reports, and project analyses; studies. - (1) Each affected agency that is required to file a...
403.527 - Certification hearing, parties, participants. - (1)(a) No later than 145 days after the application is...
403.5271 - Alternate corridors. - (1) No later than 45 days before the originally scheduled...
403.5272 - Informational public meetings. - (1) A local government whose jurisdiction is to be crossed...
403.5275 - Amendment to the application. - (1) Any amendment made to the application before certification shall...
403.528 - Alteration of time limits. - (1) Any time limitation in this act may be altered...
403.529 - Final disposition of application. - (1)(a) If the administrative law judge has granted a request...
403.531 - Effect of certification. - (1) Subject to the conditions set forth therein, certification shall...
403.5312 - Filing of notice of certified corridor route. - (1) Within 60 days after certification of a transmission line...
403.5315 - Modification of certification. - (1) The board may delegate to the department the authority...
403.5317 - Postcertification activities. - (1)(a) If, subsequent to certification, a licensee proposes any material...
403.532 - Revocation or suspension of certification. - (1) For any material false statement in the application or...
403.533 - Enforcement of compliance. - History.—s. 1, ch. 80-65; s. 42, ch. 90-331.
403.536 - Superseded laws, regulations, and certification power. - (1) If any provision of this act is in conflict...
403.5363 - Public notices; requirements. - (1)(a) The applicant shall arrange for the publication of the...
403.5365 - Fees; disposition. - (1) An application fee. (a) The application fee shall be...
403.537 - Determination of need for transmission line; powers and duties. - (1)(a) Upon request by an applicant or upon its own...
403.539 - Certification admissible in eminent domain proceedings; attorney’s fees and costs. - (1) Certification pursuant to ss. 403.52-403.5365 shall be admissible as...