Florida Statutes
Part II - Electrical Power Plant and Transmission Line Siting (Ss. 403.501-403.539)
403.5312 - Filing of notice of certified corridor route.


(1) Within 60 days after certification of a transmission line corridor under ss. 403.52-403.5365, the applicant shall file with the department and, in accordance with s. 28.222, with the clerk of the circuit court for each county through which the corridor will pass, a notice of the certified route.
(2) The notice must consist of maps or aerial photographs in the scale of 1:24,000 which clearly show the location of the certified route and must state that the certification of the corridor will result in the acquisition of rights-of-way within the corridor. Each clerk shall record the filing in the official record of the county for the duration of the certification or until such time as the applicant certifies to the department and the clerk that all lands required for the transmission line rights-of-way within the corridor have been acquired within the county, whichever is sooner.
(3) The recording of this notice does not constitute a lien, cloud, or encumbrance on real property.
History.—s. 12, ch. 81-131; s. 40, ch. 90-331; s. 61, ch. 2006-230; s. 91, ch. 2008-227.

Structure Florida Statutes

Florida Statutes

Title XXIX - Public Health

Chapter 403 - Environmental Control

Part II - Electrical Power Plant and Transmission Line Siting (Ss. 403.501-403.539)

403.501 - Short title.

403.502 - Legislative intent.

403.503 - Definitions relating to Florida Electrical Power Plant Siting Act.

403.504 - Department of Environmental Protection; powers and duties enumerated.

403.5055 - Application for permits pursuant to s. 403.0885.

403.506 - Applicability, thresholds, and certification.

403.5063 - Notice of intent to file application.

403.5064 - Application; schedules.

403.5065 - Appointment of administrative law judge; powers and duties.

403.5066 - Determination of completeness.

403.50663 - Informational public meetings.

403.50665 - Land use consistency.

403.507 - Preliminary statements of issues, reports, project analyses, and studies.

403.508 - Land use and certification hearings, parties, participants.

403.509 - Final disposition of application.

403.5095 - Alteration of time limits.

403.510 - Superseded laws, regulations, and certification power.

403.511 - Effect of certification.

403.5112 - Filing of notice of certified corridor route.

403.5113 - Postcertification amendments and review.

403.5115 - Public notice.

403.5116 - County and municipal authority unaffected by ch. 75-22.

403.512 - Revocation or suspension of certification.

403.513 - Review.

403.514 - Enforcement of compliance.

403.515 - Availability of information.

403.516 - Modification of certification.

403.517 - Supplemental applications for sites certified for ultimate site capacity.

403.5175 - Existing electrical power plant site certification.

403.518 - Fees; disposition.

403.5185 - Law applicable to applications processed under ss. 403.501-403.518.

403.519 - Exclusive forum for determination of need.

403.52 - Short title.

403.521 - Legislative intent.

403.522 - Definitions relating to the Florida Electric Transmission Line Siting Act.

403.523 - Department of Environmental Protection; powers and duties.

403.524 - Applicability; certification; exemptions.

403.525 - Administrative law judge; appointment; powers and duties.

403.5251 - Application; schedules.

403.5252 - Determination of completeness.

403.526 - Preliminary statements of issues, reports, and project analyses; studies.

403.527 - Certification hearing, parties, participants.

403.5271 - Alternate corridors.

403.5272 - Informational public meetings.

403.5275 - Amendment to the application.

403.528 - Alteration of time limits.

403.529 - Final disposition of application.

403.531 - Effect of certification.

403.5312 - Filing of notice of certified corridor route.

403.5315 - Modification of certification.

403.5317 - Postcertification activities.

403.532 - Revocation or suspension of certification.

403.533 - Enforcement of compliance.

403.536 - Superseded laws, regulations, and certification power.

403.5363 - Public notices; requirements.

403.5365 - Fees; disposition.

403.537 - Determination of need for transmission line; powers and duties.

403.539 - Certification admissible in eminent domain proceedings; attorney’s fees and costs.