Connecticut General Statutes
Chapter 277a - Public Utility Environmental Standards Act
Section 16-50n. - Parties to a certification or amendment proceeding or a declaratory ruling. Grouping of parties. Intervenors. Counsel and consultant to council. Limited appearances.

(a) The parties to a certification or amendment proceeding or to a declaratory ruling proceeding shall include: (1) The applicant, certificate holder, or petitioner; (2) each person entitled to receive a copy of the application or resolution under section 16-50l, if such person has filed with the council a notice of intent to be a party; (3) any domestic or qualified nonprofit corporation or association formed in whole or in part to promote conservation or natural beauty, to protect the environment, personal health or biological values, to preserve historical sites, to promote consumer interests, to represent commercial and industrial groups or to promote the orderly development of the areas in which the facility is to be located, if it has filed with the council a notice of intent to be a party; and (4) such other persons as the council may at any time deem appropriate.

(b) The council may permit any person to participate as an intervenor, in accordance with the provisions of section 4-177a, in a certification or amendment proceeding or a declaratory ruling proceeding.
(c) The council in its discretion may provide for the grouping of parties and intervenors with the same interests. If such a group does not designate an agent for the service of notice and documents, the council shall designate such an agent, and notice and documents need be served only on the designated agent. Notwithstanding the provisions of this subsection, any party or intervenor who has been included in a group may, at any time by oral or written notice to the council, elect not to be a member of the group to the extent specified in such notice.
(d) The Attorney General shall appoint an assistant attorney general or a special assistant attorney general to act as counsel for the Connecticut Siting Council.
(e) Upon receipt of the application, the council may employ one or more independent consultants to study and measure the consequences of the proposed facility on the environment. The council shall direct such consultant or consultants to study any matter that the council deems important to an adequate appraisal of the application. Any such study and any report issued as a result thereof shall be part of the record of the proceeding.
(f) Any person may make a limited appearance at a hearing held pursuant to the provisions of section 16-50m, prior thereto or within thirty days thereafter, entitling such person to file a statement in writing. At the discretion of the council any person may make a limited appearance at any such hearing to present an oral statement under oath. All papers and matters filed by a person making a limited appearance shall become part of the record. No person making a limited appearance, and not otherwise entitled to be a party, shall be a party or shall have the right to cross-examine witnesses, parties or intervenors.
(1971, P.A. 575, S. 8; P.A. 73-458, S. 7; P.A. 75-375, S. 5, 12; P.A. 79-537, S. 3; P.A. 86-187, S. 6, 10; P.A. 89-45, S. 3, 4; P.A. 90-230, S. 84, 101.)
History: P.A. 73-458 amended Subsec. (a)(2) to include as parties persons giving notice of intent to be a party, rather than persons who have not given notice that they do not want to be parties and clarified limited appearances in Subsec. (d) by replacing reference to appearance “at any time in the proceeding” with reference to appearance before hearing or within 30 days after hearing and provided that persons making limited appearance are not subject to cross-examination; P.A. 75-375 deleted 15-day deadline for filing of intent to be a party in Subsec. (a)(2), inserted new Subsec. (b) re grouping of parties and relettered former Subsecs. (b) to (d) as (c) to (e); P.A. 79-537 added references to amendment proceedings, certificate holders and resolutions in Subsec. (a) and deleted 20-day deadline for filing of notice of intent by nonprofit corporations under Subsec. (a)(3); P.A. 86-187 replaced power facility evaluation council with Connecticut siting council in Subsec. (c); P.A. 89-45 included provision in Subsec. (a) allowing council to issue declaratory rulings, added Subsec. (b) permitting intervenors in council proceeding, included provision in Subsec. (f) re limited appearances at hearings to present oral statement and relettered Subsecs. (b), (c), (d) and (e) as Subsecs. (c), (d), (e) and (f); P.A. 90-230 made technical change to Subsec. (b).
Cited. 177 C. 623.
Cited. 20 CA 474.

Structure Connecticut General Statutes

Connecticut General Statutes

Title 16 - Public Service Companies

Chapter 277a - Public Utility Environmental Standards Act

Section 16-50aa. - Tower sharing: Policy, requests, feasibility proceeding, compensation, expenses.

Section 16-50bb. - Municipal participation account.

Section 16-50cc. - Reconfiguration or burial of electric transmission facility.

Section 16-50dd. - State-wide telecommunications coverage data base.

Section 16-50ee. - State-wide telecommunications coverage plan.

Section 16-50ff. - Local telecommunications coverage assessments.

Section 16-50g. - Legislative finding and purpose.

Section 16-50gg. - Municipal location preferences.

Section 16-50h. - Short title.

Section 16-50hh. - Restoration and revegetation of the right-of-way.

Section 16-50i. - Definitions.

Section 16-50ii. - Electric generating facility: Flammable gas to clean piping prohibited; requirements prior to issuance of certificate to build. Penalty.

Section 16-50j. - Connecticut Siting Council. Membership. Regulations. Consultation with state agencies.

Section 16-50jj. - Meeting conducted during construction of electric generating facility.

Section 16-50k. - Certificate of environmental compatibility and public need. Transfer. Amendment. Excepted matters. Waiver.

Section 16-50kk. - Regulations re wind-powered generation.

Section 16-50l. - Application for certificate. Notice. Application or resolution for amendment of certificate. Consultation with municipality.

Section 16-50ll. - Annual report re backup power for telecommunications towers and antennas during electric service outages. Study re feasibility of backup power requirements.

Section 16-50m. - Public hearing. Notice.

Section 16-50n. - Parties to a certification or amendment proceeding or a declaratory ruling. Grouping of parties. Intervenors. Counsel and consultant to council. Limited appearances.

Section 16-50o. - Record of hearing. Rights of parties. Administrative notice re electromagnetic fields.

Section 16-50p. - Certification proceeding decisions: Timing, opinion, factors considered. Telecommunications and community antenna television facilities: Additional factors considered, conditions. Modification of location. Amendment proceeding decis...

Section 16-50q. - Judicial review.

Section 16-50r. - Report of forecast of loads and resources. Confidential information. Regulations. Investigation of life-cycle costs for overhead and underground transmission lines: Scope, hearings, consultants, assessment.

Section 16-50s. - Expenditures by utilities as consideration in proceedings.

Section 16-50t. - Regulations and standards. Hearing. Certain expenditures excluded in computation of fair net return.

Section 16-50u. - Enforcement of certificate and standards requirements.

Section 16-50v. - Administration expenses. Assessments. Fees. Staff. Consultants. Late fees.

Section 16-50w. - Conflicting provisions.

Section 16-50x. - Exclusive jurisdiction of council; exception. Eminent domain after certification. Municipal regulation of proposed location.

Section 16-50y. - Location application for electric generating facilities.

Section 16-50z. - Acquisition of real property for transmission facility. Regulations. Public service company acquisition of residential real property by condemnation.