Connecticut General Statutes
Chapter 277a - Public Utility Environmental Standards Act
Section 16-50bb. - Municipal participation account.

(a) There is established an account to be known as the “municipal participation account”, within the General Fund, which shall be a separate, nonlapsing account. There shall be deposited in the account the municipal participation fees received pursuant to subsection (a) of section 16-50l. The interest derived from the investment of the account shall be credited to the account. Any balance remaining in the account at the end of any fiscal year shall be carried forward in the account for the fiscal year next succeeding.

(b) Payments from the account shall be made upon authorization by the State Treasurer. An application for reimbursement shall be submitted not later than sixty days after the conclusion of a certification proceeding, except for a facility described in subdivisions (5) and (6) of subsection (a) of section 16-50i, by each municipality entitled to receive a copy of an application under section 16-50l in order to defray expenses incurred by such municipalities in participating as a party to a certification proceeding, except for a proceeding on an application for a facility described in subdivision (5) or (6) of subsection (a) of section 16-50i. Any moneys remaining after payments to municipalities in accordance with this section shall be refunded to the applicant in even amounts. Where more than one municipality seeks moneys from such account, the council shall evenly distribute such moneys among the municipalities. No municipality may receive moneys from the account in excess of twenty-five thousand dollars. No municipality may receive moneys from the account in excess of the dollar amount such municipality has expended from its own municipal funds.
(c) In administering the moneys in the account, the State Treasurer shall verify that the subject municipality (1) actually participated as a party to the subject certification proceeding, and (2) actually spent the money it claims to have spent on participating in the subject certification proceeding.
(P.A. 03-140, S. 15; P.A. 04-236, S. 8; P.A. 12-165, S. 3; P.A. 13-5, S. 5; P.A. 14-94, S. 37.)
History: P.A. 03-140 effective July 1, 2003, and applicable to applications for a certificate of environmental compatibility and public need filed after that date; P.A. 04-236 amended Subsec. (a) to make a technical change, effective June 8, 2004; P.A. 12-165 amended Subsec. (b) to change deadline for payments from the account from not later than 60 days after receipt of an application to not later than 60 days after the conclusion of a certification proceeding, to replace provision re moneys remaining at end of proceeding with provision re moneys remaining after payments to municipalities and to delete provision re refund of excess moneys to the account, effective June 15, 2012; P.A. 13-5 amended Subsec. (b) to make a technical change, effective May 8, 2013; P.A. 14-94 amended Subsec. (a) by deleting “subdivisions (1) and (3) of” re reference to Sec. 16-50l(a), effective June 6, 2014.

Structure Connecticut General Statutes

Connecticut General Statutes

Title 16 - Public Service Companies

Chapter 277a - Public Utility Environmental Standards Act

Section 16-50aa. - Tower sharing: Policy, requests, feasibility proceeding, compensation, expenses.

Section 16-50bb. - Municipal participation account.

Section 16-50cc. - Reconfiguration or burial of electric transmission facility.

Section 16-50dd. - State-wide telecommunications coverage data base.

Section 16-50ee. - State-wide telecommunications coverage plan.

Section 16-50ff. - Local telecommunications coverage assessments.

Section 16-50g. - Legislative finding and purpose.

Section 16-50gg. - Municipal location preferences.

Section 16-50h. - Short title.

Section 16-50hh. - Restoration and revegetation of the right-of-way.

Section 16-50i. - Definitions.

Section 16-50ii. - Electric generating facility: Flammable gas to clean piping prohibited; requirements prior to issuance of certificate to build. Penalty.

Section 16-50j. - Connecticut Siting Council. Membership. Regulations. Consultation with state agencies.

Section 16-50jj. - Meeting conducted during construction of electric generating facility.

Section 16-50k. - Certificate of environmental compatibility and public need. Transfer. Amendment. Excepted matters. Waiver.

Section 16-50kk. - Regulations re wind-powered generation.

Section 16-50l. - Application for certificate. Notice. Application or resolution for amendment of certificate. Consultation with municipality.

Section 16-50ll. - Annual report re backup power for telecommunications towers and antennas during electric service outages. Study re feasibility of backup power requirements.

Section 16-50m. - Public hearing. Notice.

Section 16-50n. - Parties to a certification or amendment proceeding or a declaratory ruling. Grouping of parties. Intervenors. Counsel and consultant to council. Limited appearances.

Section 16-50o. - Record of hearing. Rights of parties. Administrative notice re electromagnetic fields.

Section 16-50p. - Certification proceeding decisions: Timing, opinion, factors considered. Telecommunications and community antenna television facilities: Additional factors considered, conditions. Modification of location. Amendment proceeding decis...

Section 16-50q. - Judicial review.

Section 16-50r. - Report of forecast of loads and resources. Confidential information. Regulations. Investigation of life-cycle costs for overhead and underground transmission lines: Scope, hearings, consultants, assessment.

Section 16-50s. - Expenditures by utilities as consideration in proceedings.

Section 16-50t. - Regulations and standards. Hearing. Certain expenditures excluded in computation of fair net return.

Section 16-50u. - Enforcement of certificate and standards requirements.

Section 16-50v. - Administration expenses. Assessments. Fees. Staff. Consultants. Late fees.

Section 16-50w. - Conflicting provisions.

Section 16-50x. - Exclusive jurisdiction of council; exception. Eminent domain after certification. Municipal regulation of proposed location.

Section 16-50y. - Location application for electric generating facilities.

Section 16-50z. - Acquisition of real property for transmission facility. Regulations. Public service company acquisition of residential real property by condemnation.