(a) Except as provided in AS 46.14.220 or in regulations adopted under AS 46.14.140(a)(7), after receipt of a complete application, and after notice and opportunity for public comment and hearing, the department shall issue or deny
(1) a construction permit within 30 days after the close of the public comment period;
(2) an operating permit, other than a general operating permit or temporary operating permit, within 12 months after receipt of the complete application by the department.
(b) [Repealed, ยง 82 ch 41 SLA 2009.]
(c) Failure by the department to act within the time limits established in or under (a) or (d) of this section is considered to be a final agency action, but only for the purpose of judicial review to determine whether the court will require that action be taken by the department.
(d) The department shall issue or deny a minor permit under AS 46.14.130(c) within 30 days after the close of the public comment period or within 30 days after receipt of the complete application by the department if a public comment period is not required under this chapter.
Structure Alaska Statutes
Title 46. Water, Air, Energy, and Environmental Conservation
Chapter 14. Air Quality Control
Article 2. Emission Control Permit Program.
Sec. 46.14.120. Permits for construction, installation, modification, or operation.
Sec. 46.14.130. Stationary sources requiring permits.
Sec. 46.14.140. Emission control permit program regulations.
Sec. 46.14.150. Time for submission of operating permit applications.
Sec. 46.14.160. Completeness determination.
Sec. 46.14.170. Administrative actions regarding permits.
Sec. 46.14.190. Single permit.
Sec. 46.14.200. Review of permit action.
Sec. 46.14.210. General operating permits.
Sec. 46.14.211. General minor permits.
Sec. 46.14.215. Temporary operations.
Sec. 46.14.220. Objection by federal administrator.
Sec. 46.14.230. Duration of operating permits.
Sec. 46.14.235. Federal termination, modification, or revocation and reissuance of permits.
Sec. 46.14.240. Permit administration fees.
Sec. 46.14.250. Emission fees.
Sec. 46.14.255. Interest and sanctions for nonpayment.
Sec. 46.14.260. Clean air protection fund.
Sec. 46.14.265. Emission control permit receipts account.
Sec. 46.14.270. Clean air protection account.
Sec. 46.14.275. Timely and complete application as shield.
Sec. 46.14.285. Amendment and modification of permit upon request of permittee.