(a) The department shall review every application submitted under this chapter for completeness. To be determined complete, an application must provide the information identified by the department in regulations adopted under AS 46.14.140 and in standard application forms provided by the department under AS 46.14.140(a)(1) and must be certified true and correct by the owner and operator.
(b) The department shall notify the applicant in writing whether the application is complete. Unless the department notifies the applicant within 60 days of receipt of an application that the application is incomplete, the application is considered to be complete.
(c) If, during the processing of an application after it has been determined or considered to be complete, the department finds that additional information is necessary to evaluate or take action on that application, the information may be requested in writing from the owner and operator. A request for information under this subsection does not render the application incomplete. However, notwithstanding AS 46.14.275, an owner and operator may be found in violation of this chapter for operating without a valid permit if they fail to provide timely additional information.
Structure Alaska Statutes
Title 46. Water, Air, Energy, and Environmental Conservation
Chapter 14. Air Quality Control
Article 2. Emission Control Permit Program.
Sec. 46.14.120. Permits for construction, installation, modification, or operation.
Sec. 46.14.130. Stationary sources requiring permits.
Sec. 46.14.140. Emission control permit program regulations.
Sec. 46.14.150. Time for submission of operating permit applications.
Sec. 46.14.160. Completeness determination.
Sec. 46.14.170. Administrative actions regarding permits.
Sec. 46.14.190. Single permit.
Sec. 46.14.200. Review of permit action.
Sec. 46.14.210. General operating permits.
Sec. 46.14.211. General minor permits.
Sec. 46.14.215. Temporary operations.
Sec. 46.14.220. Objection by federal administrator.
Sec. 46.14.230. Duration of operating permits.
Sec. 46.14.235. Federal termination, modification, or revocation and reissuance of permits.
Sec. 46.14.240. Permit administration fees.
Sec. 46.14.250. Emission fees.
Sec. 46.14.255. Interest and sanctions for nonpayment.
Sec. 46.14.260. Clean air protection fund.
Sec. 46.14.265. Emission control permit receipts account.
Sec. 46.14.270. Clean air protection account.
Sec. 46.14.275. Timely and complete application as shield.
Sec. 46.14.285. Amendment and modification of permit upon request of permittee.