2021 Oregon Revised Statutes
Chapter 279C - Public Contracting - Public Improvements and Related Contracts
Section 279C.580 - Contractor’s relations with subcontractors.


(2) A dispute between a contractor and first-tier subcontractor relating to the amount or entitlement of a first-tier subcontractor to a payment or a late payment interest penalty under a clause included in the subcontract under subsection (3) or (4) of this section does not constitute a dispute to which the contracting agency is a party. The contracting agency may not be included as a party in any administrative or judicial proceeding involving such a dispute.
(3) Each public improvement contract awarded by a contracting agency must include a clause that requires the contractor to include in each subcontract for property or services the contractor enters into with a first-tier subcontractor, including a material supplier, for the purpose of performing a construction contract:
(a) A payment clause that obligates the contractor to pay the first-tier subcontractor for satisfactory performance under the subcontract within 10 days out of amounts the contracting agency pays to the contractor under the public improvement contract.
(b) A clause that requires the contractor to provide a first-tier subcontractor with a standard form that the first-tier subcontractor may use as an application for payment or as another method by which the subcontractor may claim a payment due from the contractor.
(c) A clause that requires the contractor, except as otherwise provided in this paragraph, to use the same form and regular administrative procedures for processing payments during the entire term of the subcontract. A contractor may change the form or the regular administrative procedures the contractor uses for processing payments if the contractor:
(A) Notifies the subcontractor in writing at least 45 days before the date on which the contractor makes the change; and
(B) Includes with the written notice a copy of the new or changed form or a description of the new or changed procedure.
(d) An interest penalty clause that obligates the contractor, if the contractor does not pay the first-tier subcontractor within 30 days after receiving payment from the contracting agency, to pay the first-tier subcontractor an interest penalty on amounts due in each payment the contractor does not make in accordance with the payment clause included in the subcontract under paragraph (a) of this subsection. A contractor or first-tier subcontractor is not obligated to pay an interest penalty if the only reason that the contractor or first-tier subcontractor did not make payment when payment was due is that the contractor or first-tier subcontractor did not receive payment from the contracting agency or contractor when payment was due. The interest penalty:
(A) Applies to the period that begins on the day after the required payment date and that ends on the date on which the amount due is paid; and
(B) Is computed at the rate specified in ORS 279C.515 (2).
(4) A public improvement contract that the contracting agency awards shall obligate the contractor, in each of the contractor’s subcontracts, to require the first-tier subcontractor to include a payment clause and an interest penalty clause that conforms to the standards of subsection (3) of this section in each of the first-tier subcontractor’s subcontracts and to require each of the first-tier subcontractor’s subcontractors to include such clauses in the first-tier subcontractors’ subcontracts with each lower-tier subcontractor or supplier.
(5)(a) The clauses required by subsections (3) and (4) of this section do not impair the right of a contractor or a subcontractor at any tier to negotiate, and to include in the subcontract, provisions that:
(A) Permit the contractor or a subcontractor to retain, in the event of a good faith dispute, an amount not to exceed 150 percent of the amount in dispute from the amount due a subcontractor under the subcontract without incurring any obligation to pay a late payment interest penalty, in accordance with terms and conditions the parties to the subcontract agree upon, giving such recognition as the parties consider appropriate to the ability of a subcontractor to furnish a performance bond and a payment bond;
(B) Permit the contractor or subcontractor to make a determination that part or all of the subcontractor’s request for payment may be withheld in accordance with the subcontract; and
(C) Permit such withholdings without incurring any obligation to pay a late payment interest penalty if:
(i) A notice that conforms to the standards of subsection (8) of this section has been previously furnished to the subcontractor; and
(ii) A copy of any notice a contractor issues under sub-subparagraph (i) of this subparagraph has been furnished to the contracting agency.
(b) As used in this subsection, "good faith dispute" means a documented dispute concerning:
(A) Unsatisfactory job progress.
(B) Defective work not remedied.
(C) Third-party claims filed or reasonable evidence that claims will be filed.
(D) Failure to make timely payments for labor, equipment and materials.
(E) Damage to the contractor or subcontractor.
(F) Reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum.
(6) If, after applying to a contracting agency for payment under a public improvement contract but before paying a subcontractor for the subcontractor’s performance covered by the application, a contractor discovers that all or a portion of the payment otherwise due the subcontractor is subject to withholding from the subcontractor in accordance with the subcontract, the contractor shall:
(a) Furnish to the subcontractor a notice conforming to the standards of subsection (8) of this section as soon as practicable after ascertaining the cause for the withholding, but before the due date for payment to the subcontractor;
(b) Furnish to the contracting agency, as soon as practicable, a copy of the notice furnished to the subcontractor under paragraph (a) of this subsection;
(c) Reduce the progress payment to the subcontractor by an amount not to exceed the amount specified in the notice of withholding furnished under paragraph (a) of this subsection;
(d) Pay the subcontractor as soon as practicable after the correction of the identified subcontract performance deficiency;
(e) Make such payment within:
(A) Seven days after correction of the identified subcontract performance deficiency unless the funds for the payment must be recovered from the contracting agency because of a reduction under paragraph (f)(A) of this subsection; or
(B) Seven days after the contractor recovers the funds from the contracting agency;
(f) Notify the contracting agency upon:
(A) Reduction of the amount of any subsequent certified application for payment; or
(B) Payment to the subcontractor of any withheld amounts of a progress payment, specifying:
(i) The amounts of the progress payments withheld under paragraph (a) of this subsection; and
(ii) The dates on which the withholding began and ended; and
(g) Be obligated to pay to the contracting agency an amount equal to interest on the withheld payments computed in the manner provided in ORS 279C.570 from the 11th day after receiving the withheld amounts from the contracting agency until:
(A) The day the identified subcontractor performance deficiency is corrected; or
(B) The date that any subsequent payment is reduced under paragraph (f)(A) of this subsection.
(7)(a) If a contractor, after paying a first-tier subcontractor, receives from a supplier or subcontractor of the first-tier subcontractor a written notice asserting a deficiency in the first-tier subcontractor’s performance under the public improvement contract for which the contractor may be ultimately liable and the contractor determines that all or a portion of future payments otherwise due the first-tier subcontractor is subject to withholding in accordance with the subcontract, the contractor may, without incurring an obligation to pay a late payment interest penalty under subsection (6)(e) of this section:
(A) Furnish to the first-tier subcontractor a notice that conforms to the standards of subsection (8) of this section as soon as practicable after making the determination; and
(B) Withhold from the first-tier subcontractor’s next available progress payment or payments an amount not to exceed the amount specified in the notice of withholding furnished under subparagraph (A) of this paragraph.
(b) As soon as practicable, but not later than 10 days after receiving satisfactory written notice that the identified subcontract performance deficiency has been corrected, the contractor shall pay the amount withheld under paragraph (a)(B) of this subsection to the first-tier subcontractor, or shall incur an obligation to pay a late payment interest penalty to the first-tier subcontractor computed at the rate specified in ORS 279C.570.
(8) A written notice of any withholding must be issued to a subcontractor, with a copy to the contracting agency, that specifies:
(a) The amount to be withheld;
(b) The specified causes for the withholding under the terms of the subcontract; and
(c) The remedial actions the subcontractor must take in order to receive payment of the amounts withheld.
(9) Except as provided in subsection (2) of this section, this section does not limit or impair any contractual, administrative or judicial remedies otherwise available to a contractor or a subcontractor in the event of a dispute involving a contractor’s late payment or nonpayment or a subcontractor’s deficient performance or nonperformance.
(10) A contractor’s obligation to pay a late payment interest penalty to a subcontractor under the clause included in a subcontract under subsection (3) or (4) of this section is not an obligation of the contracting agency. A contract modification may not be made for the purpose of providing reimbursement of a late payment interest penalty. A cost reimbursement claim may not include any amount for reimbursement of a late payment interest penalty. [2003 c.794 §151; 2005 c.103 §34; 2012 c.4 §2]

Structure 2021 Oregon Revised Statutes

2021 Oregon Revised Statutes

Volume : 07 - Public Facilities and Finance

Chapter 279C - Public Contracting - Public Improvements and Related Contracts

Section 279C.100 - Definitions for ORS 279C.100 to 279C.125.

Section 279C.105 - Contracts for architectural, engineering, photogrammetric mapping, transportation planning or land surveying and related services; procedures.

Section 279C.107 - Public disclosure of contents of proposals for architectural, engineering, photogrammetric mapping, transportation planning or land surveying services; treatment of trade secrets and confidential information.

Section 279C.110 - Selection procedures for consultants to provide services; use of pricing proposals; compensation; protests; applicability; rules.

Section 279C.115 - Direct contracts for services of consultants.

Section 279C.120 - Selection procedure for related services.

Section 279C.125 - Architectural, engineering, photogrammetric mapping, transportation planning and land surveying services selection process for local public improvements procured through state agency; rules.

Section 279C.305 - Least-cost policy for public improvements; requirement to file list of planned projects and estimated costs and to identify projects contracting agency intends to complete with own personnel and resources; required analysis; except...

Section 279C.306 - Administrative enforcement of least-cost policy for public improvements; procedure; civil action.

Section 279C.307 - Limitations in procurement of personal services; exceptions; procedure for obtaining exception from appropriate authority; basis for approving exception.

Section 279C.308 - Community benefit contract; permitted provisions; required contents of solicitation; powers and duties of contracting agency and local contract review board; rules.

Section 279C.315 - Waiver of damages for unreasonable delay by contracting agency against public policy.

Section 279C.320 - Contracts for construction other than public improvements.

Section 279C.330 - "Findings" defined.

Section 279C.332 - Definitions for ORS 279A.065, 279C.307, 279C.335, 279C.337 and 279C.380.

Section 279C.335 - Competitive bidding requirement; exceptions; exemptions.

Section 279C.337 - Procurement of constructions manager/general contractor services.

Section 279C.345 - Specifications for contracts; exemptions.

Section 279C.350 - Exemption procedure; appeal.

Section 279C.355 - Evaluation of public improvement projects not contracted by competitive bidding.

Section 279C.360 - Requirement for public improvement advertisements.

Section 279C.365 - Requirements for solicitation documents and bids and proposals.

Section 279C.370 - First-tier subcontractor disclosure.

Section 279C.375 - Award and execution of contract; determination of responsibility of bidder; bonds; impermissible exclusions.

Section 279C.380 - Performance bond; payment bond; waiver of bonds.

Section 279C.385 - Return or retention of bid security.

Section 279C.390 - Exemption of contracts from bid security and bonds.

Section 279C.400 - Competitive proposals; procedure.

Section 279C.405 - Requests for information, interest or qualifications; requirements for requests for proposals.

Section 279C.410 - Receipt of proposals; evaluation and award.

Section 279C.412 - Competitive quotes for intermediate procurements.

Section 279C.414 - Requirements for competitive quotes.

Section 279C.430 - Prequalification of bidders; rules.

Section 279C.440 - Disqualification from consideration for award of contracts.

Section 279C.445 - Appeal of disqualification.

Section 279C.450 - Appeal procedure for decision to deny, revoke or revise prequalification; hearing; costs; judicial review.

Section 279C.460 - Action by or on behalf of adversely affected bidder or proposer; exception for personal services contract.

Section 279C.465 - Action against successful bidder; amount of damages; when action to be commenced; defenses.

Section 279C.470 - Compensation for contractor on contract declared void by court; exceptions; applicability.

Section 279C.505 - Conditions concerning payment, contributions, liens, withholding, drug testing.

Section 279C.510 - Demolition contracts to require material salvage; lawn and landscape maintenance contracts to require composting or mulching.

Section 279C.515 - Conditions concerning payment of claims by public officers, payment to persons furnishing labor or materials and complaints.

Section 279C.520 - Condition concerning hours of labor; compliance with pay equity provisions; employee discussions of rate of pay or benefits.

Section 279C.525 - Provisions concerning environmental and natural resources laws; remedies.

Section 279C.527 - Inclusion of amount for green energy technology or woody biomass energy technology in public improvement contract; written determination of appropriateness; conditions, exemptions and limitations; rules.

Section 279C.528 - State Department of Energy requirements and specifications; record keeping requirements; rules.

Section 279C.530 - Condition concerning payment for medical care and providing workers’ compensation.

Section 279C.533 - Condition concerning employment of apprentices to perform percentage of work hours that workers in apprenticeable occupations perform on public improvements.

Section 279C.534 - Advisory committee for monitoring implementation of apprenticeship condition in public improvement contracts.

Section 279C.537 - Condition concerning use of diesel engines in motor vehicles used in performing certain public improvement contracts; rules.

Section 279C.540 - Maximum hours of labor on public contracts; holidays; exceptions; liability to workers; rules.

Section 279C.545 - Time limitation on claim for overtime; posting of circular by contractor.

Section 279C.560 - Form of retainage; procedures for holding and payment.

Section 279C.570 - Prompt payment policy; progress payments; retainage; interest; exception; settlement of compensation disputes.

Section 279C.580 - Contractor’s relations with subcontractors.

Section 279C.585 - Authority to substitute undisclosed first-tier subcontractor; circumstances; rules.

Section 279C.590 - Complaint process for substitutions of subcontractors; civil penalties.

Section 279C.600 - Right of action on payment bond or public works bond of contractor or subcontractor; notice of claim.

Section 279C.605 - Notice of claim.

Section 279C.610 - Action on contractor’s public works bond or payment bond; time limitation.

Section 279C.625 - Joint liability when payment bond not executed.

Section 279C.660 - Compensation when contract terminated due to public interest.

Section 279C.800 - Definitions for ORS 279C.800 to 279C.870.

Section 279C.805 - Policy.

Section 279C.807 - Workforce diversity for public works projects.

Section 279C.810 - Exemptions; rules.

Section 279C.815 - Determination of prevailing wage; sources of information; comparison of state and federal prevailing wage; other powers of commissioner.

Section 279C.817 - Determination of applicability of prevailing wage rate; time limitation; hearing; rules.

Section 279C.820 - Advisory committee to assist commissioner.

Section 279C.825 - Fees; rules.

Section 279C.827 - Division of public works project; applicability of prevailing wage rate to divided projects.

Section 279C.830 - Provisions concerning prevailing rate of wage in specifications, contracts and subcontracts; applicability of prevailing wage; bond.

Section 279C.836 - Public works bond; rules.

Section 279C.838 - Applicability of state and federal rates of wage; determination of site of project; determination of applicability of wage to transportation workers; waiver.

Section 279C.840 - Payment of prevailing rate of wage; posting of rates and fringe benefit plan provisions.

Section 279C.845 - Certified statements regarding payment of prevailing rates of wage; retainage.

Section 279C.850 - Inspection to determine whether prevailing rate of wage being paid; civil action for failure to pay prevailing rate of wage or overtime.

Section 279C.855 - Liability for violations.

Section 279C.860 - Ineligibility for public works contracts for failure to pay or post notice of prevailing rates of wage; certified payroll reports to commissioner.

Section 279C.865 - Civil penalties.

Section 279C.870 - Civil action to enforce payment of prevailing rates of wage.

Section 279C.875 - Criminal liability for intentional failure to pay prevailing wage; rules.