779.47 Plastics fabricator's lien.
(1) Definitions. In this section:
(a) “Plastics fabricator" means a person who uses toolings to fabricate or manufacture plastic products or a person who makes or provides toolings for use in the fabrication or manufacture of plastic products.
(b) “Toolings" includes masters, models, patterns, tools, dies, molds, jigs, fixtures, forms and designs that are used in the fabrication or manufacture of plastic products.
(2) Lien. Subject to sub. (2m), a plastics fabricator shall have a lien on all toolings and plastic products in the plastics fabricator's possession that belong to the customer for the amount owed the plastics fabricator by the customer for toolings or for plastics fabrication processing or work. The plastics fabricator may retain possession of the toolings until the amount owed is paid or satisfied.
(2m) Attachment and perfection. A lien under sub. (2) attaches and is perfected 30 days after the date on which plastic products are delivered to the customer unless the customer notifies the plastics fabricator within that time period that the products failed to meet an approved quality control plan, the products deviated from approved samples or the products deviated from previously accepted parts and the customer returns the products within 60 days after the date on which the products are delivered to the customer.
(3) Priority. A lien under sub. (2) does not take priority over an existing perfected security interest.
History: 1993 a. 328.
Structure Wisconsin Statutes & Annotations
Wisconsin Statutes & Annotations
779.03 - Lien valid unless waived by claimant personally, or unless payment bond furnished.
779.035 - Form of contract; payment bond; remedy.
779.036 - Contracts with payment bond; lien; notice; duty of owner and lender.
779.04 - Claims assignable; notice; prior payment.
779.07 - Judgment and lien docket.
779.08 - Release of lien; undertaking.
779.09 - Foreclosure of lien; procedure; parties.
779.11 - Distribution of proceeds of sale.
779.12 - Sale; notice and report; deficiency judgment; writ of assistance.
779.13 - Satisfaction of judgment or lien; correction of errors.
779.135 - Construction contracts, form of contract.
779.14 - Public works, form of contract, bond, remedy.
779.155 - Judgment creditors, attachment of funds due to public contractors.
779.16 - Theft by contractors.
779.17 - Release of funds on filing bond.
779.19 - Petition for log lien; filing same.
779.20 - Action to enforce log lien; parties; costs; change of venue.
779.21 - Attachment, affidavit for; undertaking; service of writ.
779.24 - Lien for camp supplies.
779.25 - Lien for joint log driving.
779.26 - Lien of improvement companies.
779.30 - Undertaking by intervenor; procedure.
779.36 - Extent of lien; filing claim.
779.37 - Satisfaction of lien.
779.40 - Liens for labor in quarry.
779.413 - Liens on aircraft and aircraft engines.
779.415 - Liens on vehicles for towing and storage.
779.42 - Obtaining mechanic's services by misrepresentation of interest in personal property.
779.43 - Liens of keepers of hotels, livery stables, garages, marinas and pastures.
779.45 - Liens of factors, brokers, etc.
779.47 - Plastics fabricator's lien.
779.49 - Lien of owner of breeding animal or methods.
779.50 - Lien for threshing, husking, baling; enforcement.
779.71 - Disposition of articles left for laundering, dry cleaning, repair, storage.
779.87 - Escrow account or bond requirement.
779.88 - Prepaid maintenance lien.
779.89 - Attachment and preservation.
779.90 - Notice of existence of lien.
779.92 - Enforceability of lien.
779.93 - Duties of the department of agriculture, trade and consumer protection.