§22-21-12. Review of Application; Issuance of Permit in the Absence of Objections; Copy of Permits to County Assessor

The chief shall review each application for a permit and shall determine whether or not a permit shall be issued.
No permit shall be issued less than fifteen days after the filing date of the application for any well work except plugging or replugging; and no permit for plugging or replugging shall be issued less than five days after the filing date of the application except a permit for plugging or replugging a dry hole: Provided, That if the applicant certifies that all persons entitled to notice of the application under the provisions of this article have been served in person or by certified mail, return receipt requested, with a copy of the permit application, including the erosion and sediment control plan, if required, and the plat required by section six of this article, and further files written statements of no objection by all such persons, the chief may issue the permit at any time.
The chief may cause such inspections to be made of the proposed location as to assure adequate review of the application. The permit shall not be issued, or shall be conditioned, including conditions with respect to the location of the well and access roads, prior to issuance if the chief determines that:
(1) The proposed well work will constitute a hazard to the safety of persons; or
(2) The plan for soil erosion and sediment control is not adequate or effective; or
(3) Damage would occur to publicly owned lands or resources; or
(4) The proposed well work fails to protect fresh water sources or supplies. Upon the issuance of any permit pursuant to the provisions of this article, the chief shall transmit a copy of such permit to the office of the assessor for the county in which the well is located.

Structure West Virginia Code

West Virginia Code

Chapter 22. Environmental Resources

Article 21. Coalbed Methane Wells and Units

§22-21-1. Declaration of Public Policy; Legislative Findings

§22-21-2. Definitions

§22-21-3. Application of Article; Exclusions; Application of Chapter Twenty-Two-B to Coalbed Methane Wells

§22-21-4. Chief; Powers and Duties Generally

§22-21-5. Duties of the Coalbed Methane Review Board; Meetings; Notice, Powers and Duties Generally

§22-21-6. Permit Required for Coalbed Methane Well; Permit Fee; Application; Soil Erosion Control Plan; Penalties

§22-21-7. Consent and Agreement of Coal Owner or Operator

§22-21-8. Performance Bonds; Corporate Surety or Other Security

§22-21-9. Notice to Owners

§22-21-10. Procedure for Filing Comments

§22-21-11. Objections or Comments to Coalbed Methane Wells by Coal Owner or Operator; Hearings

§22-21-12. Review of Application; Issuance of Permit in the Absence of Objections; Copy of Permits to County Assessor

§22-21-13. Review Board Hearing; Findings; Order

§22-21-14. Protective Devices Required When a Coalbed Methane Well Penetrates Workable Coalbed; When a Coalbed Methane Well Is Drilled Through Horizon of Coalbed From Which Coal Has Been Removed; Notice of Stimulation; Results of Stimulation

§22-21-15. Drilling Units and Pooling of Interests

§22-21-16. Notice to Owners

§22-21-17. Review of Application; Hearing; Pooling Order; Spacing; Operator; Elections; Working Interests, Royalty Interests, Carried Interests, Escrow Account for Conflicting Claims, Division Order

§22-21-18. Operation on Drilling Units

§22-21-19. Validity of Unit Agreements

§22-21-20. Spacing

§22-21-21. Dry or Abandoned Wells

§22-21-22. Notice of Plugging and Reclamation of Well; Right to Take Well; Objection; Plugging Order; Plugging for Mine-Through

§22-21-23. Method of Plugging

§22-21-24. Existing Mining Rights

§22-21-25. Judicial Review; Appeal to Supreme Court of Appeals; Legal Representation for Review Board

§22-21-26. Limitation on Actions in Trespass

§22-21-27. Injunctive Relief

§22-21-28. Penalties

§22-21-29. Construction