Sec. 36.401. SECURITIZATION FOR RECOVERY OF SYSTEM RESTORATION COSTS; PURPOSE. (a) The purpose of this subchapter is to enable an electric utility to obtain timely recovery of system restoration costs and to use securitization financing to recover these costs, because that type of debt will lower the carrying costs associated with the recovery of these costs, relative to the costs that would be incurred using conventional financing methods. The proceeds of the transition bonds may be used only for the purposes of reducing the amount of recoverable system restoration costs, as determined by the commission in accordance with this subchapter, including the refinancing or retirement of utility debt or equity.
(b) It is the intent of the legislature that:
(1) securitization of system restoration costs will be accomplished using the same procedures, standards, and protections for securitization authorized under Subchapter G, Chapter 39, as in effect on the effective date of this section, except as provided by this subchapter; and
(2) the commission will ensure that securitization of system restoration costs provides greater tangible and quantifiable benefits to ratepayers than would have been achieved without the issuance of transition bonds.
Added by Acts 2009, 81st Leg., R.S., Ch. 1 (S.B. 769), Sec. 1, eff. April 16, 2009.
Structure Texas Statutes
Title 2 - Public Utility Regulatory Act
Subtitle B - Electric Utilities
Subchapter I. Securitization for Recovery of System
Section 36.401. Securitization for Recovery of System Restoration Costs; Purpose
Section 36.402. System Restoration Costs; Standards and Definitions
Section 36.404. Nonbypassable Charges