Sec. 2269.362. NEGOTIATION. After selecting the highest-ranked design-build firm under Section 2269.361, the governmental entity shall first attempt to negotiate a contract with the selected firm. If the governmental entity is unable to negotiate a satisfactory contract with the selected firm, the entity shall, formally and in writing, end all negotiations with that firm and proceed to negotiate with the next firm in the order of the selection ranking until a contract is reached or negotiations with all ranked firms end.
Added by Acts 2011, 82nd Leg., R.S., Ch. 1129 (H.B. 628), Sec. 2.08, eff. September 1, 2011.
Redesignated from Government Code, Chapter 2267 by Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.001(23), eff. September 1, 2013.
Amended by:
Acts 2013, 83rd Leg., R.S., Ch. 161 (S.B. 1093), Sec. 22.002(17), eff. September 1, 2013.
Structure Texas Statutes
Subtitle F - State and Local Contracts and Fund Management
Chapter 2269 - Contracting and Delivery Procedures for Construction Projects
Subchapter H. Design-Build Procedures for Certain Civil Works Projects
Section 2269.352. Applicability
Section 2269.353. Contracts for Civil Works Projects: Design-Build
Section 2269.354. Limitation on Number of Projects
Section 2269.355. Use of Engineer
Section 2269.356. Use of Other Professional Services
Section 2269.357. Request for Qualifications
Section 2269.358. Contents of Design Criteria Package
Section 2269.359. Evaluation of Design-Build Firms
Section 2269.360. Selection of Design-Build Firm
Section 2269.361. Procedures for Combination of Technical and Cost Proposals
Section 2269.3615. Identification of Project Team
Section 2269.363. Assumption of Risks
Section 2269.364. Stipend Amount for Unsuccessful Offerors
Section 2269.365. Completion of Design