Sec. 2269.3615. IDENTIFICATION OF PROJECT TEAM. (a) A governmental entity may require a design-build firm responding to a request for detailed proposals to identify companies that will:
(1) fill key project roles, including project management, lead design firm, quality control management, and quality assurance management; and
(2) serve as key task leaders for geotechnical, hydraulics and hydrology, structural, environmental, utility, and right-of-way issues.
(b) If a design-build firm required to identify companies under Subsection (a) is selected for a design-build agreement, the firm may not make changes to the identified companies unless an identified company:
(1) is no longer in business, is unable to fulfill its legal, financial, or business obligations, or can no longer meet the terms of the teaming agreement with the design-build firm;
(2) voluntarily removes itself from the team;
(3) fails to provide a sufficient number of qualified personnel to fulfill the duties identified during the proposal stage; or
(4) fails to negotiate in good faith in a timely manner in accordance with provisions established in the teaming agreement proposed for the project.
(c) If the design-build firm makes team changes in violation of Subsection (b), any cost savings resulting from the change accrue to the governmental entity and not to the design-build firm.
Added by Acts 2013, 83rd Leg., R.S., Ch. 1127 (H.B. 1050), Sec. 5(b), eff. September 1, 2013.
Structure Texas Statutes
Subtitle F - State and Local Contracts and Fund Management
Chapter 2269 - Contracting and Delivery Procedures for Construction Projects
Subchapter H. Design-Build Procedures for Certain Civil Works Projects
Section 2269.352. Applicability
Section 2269.353. Contracts for Civil Works Projects: Design-Build
Section 2269.354. Limitation on Number of Projects
Section 2269.355. Use of Engineer
Section 2269.356. Use of Other Professional Services
Section 2269.357. Request for Qualifications
Section 2269.358. Contents of Design Criteria Package
Section 2269.359. Evaluation of Design-Build Firms
Section 2269.360. Selection of Design-Build Firm
Section 2269.361. Procedures for Combination of Technical and Cost Proposals
Section 2269.3615. Identification of Project Team
Section 2269.363. Assumption of Risks
Section 2269.364. Stipend Amount for Unsuccessful Offerors
Section 2269.365. Completion of Design