Sec. 2253.045. NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIAL UNDER WRITTEN UNIT PRICE AGREEMENT. The notice for a claim for public work labor performed or public work material delivered by a payment bond beneficiary who is a subcontractor or materialman to the prime contractor or to a subcontractor and who has a written unit price agreement that is wholly or partially completed is sufficient if the beneficiary attaches to the sworn statement of account:
(1) a list of units and unit prices set by the contract; and
(2) a statement of those completed and partially completed units.
Added by Acts 1993, 73rd Leg., ch. 268, Sec. 1, eff. Sept. 1, 1993.
Structure Texas Statutes
Subtitle F - State and Local Contracts and Fund Management
Chapter 2253 - Public Work Performance and Payment Bonds
Subchapter C. Notice Requirements
Section 2253.041. Notice Required for Claim for Payment for Labor or Material
Section 2253.042. Copy of Agreement as Notice of Claim for Unpaid Labor or Material
Section 2253.043. Notice of Claim for Unpaid Labor or Material When Written Agreement Does Not Exist
Section 2253.044. Notice of Claim for Multiple Items of Labor or Material
Section 2253.045. Notice of Claim for Unpaid Labor or Material Under Written Unit Price Agreement
Section 2253.046. Notice Required for Claim for Payment of Retainage