Revised Code of Washington
Chapter 80.50 - Energy Facilities—Site Locations.
80.50.060 - Energy facilities to which chapter applies—Applications for certification—Forms—Council's duties—Potential effects to tribal cultural resources.

RCW 80.50.060
Energy facilities to which chapter applies—Applications for certification—Forms—Council's duties—Potential effects to tribal cultural resources.

(1)(a) The provisions of this chapter apply to the construction of energy facilities which includes the new construction of energy facilities and the reconstruction or enlargement of existing energy facilities where the net increase in physical capacity or dimensions resulting from such reconstruction or enlargement meets or exceeds those capacities or dimensions set forth in RCW 80.50.020 (14) and (29). No construction or reconstruction of such energy facilities may be undertaken, except as otherwise provided in this chapter, without first obtaining certification in the manner provided in this chapter.
(b) If applicants proposing the following types of facilities choose to receive certification under this chapter, the provisions of this chapter apply to the construction, reconstruction, or enlargement of these new or existing facilities:
(i) Facilities that produce refined biofuel, but which are not capable of producing 25,000 barrels or more per day;
(ii) Alternative energy resource facilities;
(iii) Electrical transmission facilities: (A) Of a nominal voltage of at least 115,000 volts; and (B) located in more than one jurisdiction that has promulgated land use plans or zoning ordinances;
(iv) Clean energy product manufacturing facilities; and
(v) Storage facilities.
(c) All of the council's powers with regard to energy facilities apply to all of the facilities in (b) of this subsection and these facilities are subject to all provisions of this chapter that apply to an energy facility.
(2)(a) The provisions of this chapter must apply to the construction, reconstruction, or modification of electrical transmission facilities when the facilities are located in a national interest electric transmission corridor as specified in RCW 80.50.045.
(b) For the purposes of this subsection, "modification" means a significant change to an electrical transmission facility and does not include the following: (i) Minor improvements such as the replacement of existing transmission line facilities or supporting structures with equivalent facilities or structures; (ii) the relocation of existing electrical transmission line facilities; (iii) the conversion of existing overhead lines to underground; or (iv) the placing of new or additional conductors, supporting structures, insulators, or their accessories on or replacement of supporting structures already built.
(3) The provisions of this chapter shall not apply to normal maintenance and repairs which do not increase the capacity or dimensions beyond those set forth in RCW 80.50.020 (14) and (29).
(4) Applications for certification of energy facilities made prior to July 15, 1977, shall continue to be governed by the applicable provisions of law in effect on the day immediately preceding July 15, 1977, with the exceptions of RCW 80.50.071 which shall apply to such prior applications and to site certifications prospectively from July 15, 1977.
(5) Applications for certification shall be upon forms prescribed by the council and shall be supported by such information and technical studies as the council may require.
(6) Upon receipt of an application for certification under this chapter, the chair of the council shall notify:
(a) The appropriate county legislative authority or authorities where the proposed facility is located;
(b) The appropriate city legislative authority or authorities where the proposed facility is located;
(c) The department of archaeology and historic preservation; and
(d) The appropriate federally recognized tribal governments that may be affected by the proposed facility.
(7) The council must work with local governments where a project is proposed to be sited in order to provide for meaningful participation and input during siting review and compliance monitoring.
(8) The council must consult with all federally recognized tribes that possess resources, rights, or interests reserved or protected by federal treaty, statute, or executive order in the area where an energy facility is proposed to be located to provide early and meaningful participation and input during siting review and compliance monitoring. The chair and designated staff must offer to conduct government-to-government consultation to address issues of concern raised by such a tribe. The goal of the consultation process is to identify tribal resources or rights potentially affected by the proposed energy facility and to seek ways to avoid, minimize, or mitigate any adverse effects on tribal resources or rights. The chair must provide regular updates on the consultation to the council throughout the application review process. The report from the council to the governor required in RCW 80.50.100 must include a summary of the government-to-government consultation process that complies with RCW 42.56.300, including the issues and proposed resolutions.
(9) The department of archaeology and historic preservation shall coordinate with the affected federally recognized tribes and the applicant in order to assess potential effects to tribal cultural resources, archaeological sites, and sacred sites.

[ 2022 c 183 § 6; 2021 c 317 § 18; 2007 c 325 § 2; 2006 c 196 § 4; 2001 c 214 § 2; 1977 ex.s. c 371 § 5; 1975-'76 2nd ex.s. c 108 § 34; 1970 ex.s. c 45 § 6.]
NOTES:

Effective date—2022 c 183: See note following RCW 80.50.010.


Severability—2021 c 317: See note following RCW 70A.535.005.


Severability—Effective date—2001 c 214: See notes following RCW 80.50.010.


Findings—2001 c 214: See note following RCW 39.35.010.


Severability—Effective date—1975-'76 2nd ex.s. c 108: See notes following RCW 43.21F.010.

Structure Revised Code of Washington

Revised Code of Washington

Title 80 - Public Utilities

Chapter 80.50 - Energy Facilities—Site Locations.

80.50.010 - Legislative finding—Policy—Intent.

80.50.020 - Definitions.

80.50.030 - Energy facility site evaluation council—Created—Membership—Quorum.

80.50.040 - Energy facility site evaluation council—Powers enumerated.

80.50.045 - Recommendations to secretary, federal energy regulatory commission—Siting electrical transmission corridors—Council designated as state authority for siting transmission facilities.

80.50.060 - Energy facilities to which chapter applies—Applications for certification—Forms—Council's duties—Potential effects to tribal cultural resources.

80.50.071 - Council to receive applications—Payment of costs incurred by the council—Notification requirements.

80.50.075 - Expedited processing of applications.

80.50.080 - Counsel for the environment.

80.50.085 - Council staff to assist applicants, make recommendations.

80.50.090 - Public hearings—Opportunity for public comment.

80.50.100 - Recommendations to governor—Expedited processing—Approval or rejection of certification—Reconsideration.

80.50.105 - Transmission facilities for petroleum products—Recommendations to governor.

80.50.110 - Chapter governs and supersedes other law or regulations—Preemption of regulation and certification by state.

80.50.120 - Effect of certification.

80.50.130 - Revocation or suspension of certification—Grounds.

80.50.140 - Review.

80.50.150 - Enforcement of compliance—Penalties.

80.50.155 - Additional penalties—Appeal procedures.

80.50.160 - Availability of information.

80.50.175 - Council's powers.

80.50.180 - Proposals and actions by other state agencies and local political subdivisions pertaining to energy facilities exempt from "detailed statement" required by RCW 43.21C.030.

80.50.300 - Unfinished nuclear power projects—Transfer of all or a portion of a site to a political subdivision or subdivisions of the state—Water rights.

80.50.310 - Council actions—Exemption from chapter 43.21C RCW.

80.50.320 - Governor to evaluate council efficiency, make recommendations.

80.50.330 - Preapplication—Siting electrical transmission facilities—Corridors.

80.50.340 - Preapplication—Fees—Plans.

80.50.360 - Duties of chair and director.

80.50.370 - Clean energy product manufacturing facilities.

80.50.380 - Preapplication review of a proposed project—Fees.

80.50.390 - Energy facility site evaluation council account.

80.50.400 - Transfer of authority from the utilities and transportation commission to the council.