RCW 36.70B.080
Development regulations—Requirements—Report on implementation costs.
(1) Development regulations adopted pursuant to RCW 36.70A.040 must establish and implement time periods for local government actions for each type of project permit application and provide timely and predictable procedures to determine whether a completed project permit application meets the requirements of those development regulations. The time periods for local government actions for each type of complete project permit application or project type should not exceed one hundred twenty days, unless the local government makes written findings that a specified amount of additional time is needed to process specific complete project permit applications or project types.
The development regulations must, for each type of permit application, specify the contents of a completed project permit application necessary for the complete compliance with the time periods and procedures.
(2)(a) Counties subject to the requirements of RCW 36.70A.215 and the cities within those counties that have populations of at least twenty thousand must, for each type of permit application, identify the total number of project permit applications for which decisions are issued according to the provisions of this chapter. For each type of project permit application identified, these counties and cities must establish and implement a deadline for issuing a notice of final decision as required by subsection (1) of this section and minimum requirements for applications to be deemed complete under RCW 36.70B.070 as required by subsection (1) of this section.
(b) Counties and cities subject to the requirements of this subsection also must prepare annual performance reports that include, at a minimum, the following information for each type of project permit application identified in accordance with the requirements of (a) of this subsection:
(i) Total number of complete applications received during the year;
(ii) Number of complete applications received during the year for which a notice of final decision was issued before the deadline established under this subsection;
(iii) Number of applications received during the year for which a notice of final decision was issued after the deadline established under this subsection;
(iv) Number of applications received during the year for which an extension of time was mutually agreed upon by the applicant and the county or city;
(v) Variance of actual performance, excluding applications for which mutually agreed time extensions have occurred, to the deadline established under this subsection during the year; and
(vi) The mean processing time and the number standard deviation from the mean.
(c) Counties and cities subject to the requirements of this subsection must:
(i) Provide notice of and access to the annual performance reports through the county's or city's website; and
(ii) Post electronic facsimiles of the annual performance reports through the county's or city's website. Postings on a county's or city's website indicating that the reports are available by contacting the appropriate county or city department or official do not comply with the requirements of this subsection.
If a county or city subject to the requirements of this subsection does not maintain a website, notice of the reports must be given by reasonable methods, including but not limited to those methods specified in RCW 36.70B.110(4).
(3) Nothing in this section prohibits a county or city from extending a deadline for issuing a decision for a specific project permit application for any reasonable period of time mutually agreed upon by the applicant and the local government.
(4) The *department of community, trade, and economic development shall work with the counties and cities to review the potential implementation costs of the requirements of subsection (2) of this section. The department, in cooperation with the local governments, shall prepare a report summarizing the projected costs, together with recommendations for state funding assistance for implementation costs, and provide the report to the governor and appropriate committees of the senate and house of representatives by January 1, 2005.
[ 2004 c 191 § 2; 2001 c 322 § 1; 1995 c 347 § 410; (1995 c 347 § 409 expired July 1, 2000); 1994 c 257 § 3. Formerly RCW 36.70A.065.]
NOTES:
*Reviser's note: The "department of community, trade, and economic development" was renamed the "department of commerce" by 2009 c 565.
Findings—Intent—2004 c 191: "The legislature finds that the timely issuance of project permit decisions by local governments serves the public interest. When these decisions, that are often responses to land use and building permit applications, are issued according to specific and locally established time periods and without unnecessary or inappropriate delays, the public enjoys greater efficiency, consistency, and predictability in the permitting process.
The legislature also finds that full access to relevant performance data produced annually by local governments for each type of permit application affords elected officials, project proponents, and the general public the opportunity to review and compare the permit application and processing performance of jurisdictions. Furthermore, the legislature finds that the review and comparison of this data, and the requirement to provide convenient and direct internet access to germane and consistent reports, will likely foster improved methods for processing applications, and issuing project permit decisions in a timely manner.
The legislature, therefore, intends to continue and clarify the requirements for certain jurisdictions to produce and provide access to annual permitting performance reports." [ 2004 c 191 § 1.]
Effective date—1995 c 347 § 410: "Section 410, chapter 347, Laws of 1995 shall take effect July 1, 2000." [ 1998 c 286 § 10; 1995 c 347 § 412.]
Expiration date—1995 c 347 § 409: "The amendments to RCW 36.70B.080 contained in section 409, chapter 347, Laws of 1995 shall expire July 1, 2000." [ 1998 c 286 § 9; 1995 c 347 § 411.]
Severability—1994 c 257: See note following RCW 36.70A.270.
Development regulations must provide sufficient land capacity for development: RCW 36.70A.115.
Structure Revised Code of Washington
Chapter 36.70B - Local Project Review.
36.70B.010 - Findings and declaration.
36.70B.030 - Project review—Required elements—Limitations.
36.70B.040 - Determination of consistency.
36.70B.050 - Local government review of project permit applications required—Objectives.
36.70B.070 - Project permit applications—Determination of completeness—Notice to applicant.
36.70B.080 - Development regulations—Requirements—Report on implementation costs.
36.70B.100 - Designation of person or entity to receive determinations and notices.
36.70B.120 - Permit review process.
36.70B.130 - Notice of decision—Distribution.
36.70B.140 - Project permits that may be excluded from review.
36.70B.150 - Local governments not planning under the growth management act may use provisions.
36.70B.160 - Additional project review encouraged—Construction.
36.70B.170 - Development agreements—Authorized.
36.70B.180 - Development agreements—Effect.
36.70B.190 - Development agreements—Recording—Parties and successors bound.
36.70B.200 - Development agreements—Public hearing.
36.70B.210 - Development agreements—Authority to impose fees not extended.
36.70B.220 - Permit assistance staff.
36.70B.230 - Planning regulations—Copies provided to county assessor.
36.70B.900 - Finding—Severability—Part headings and table of contents not law—1995 c 347.