Ohio Revised Code
Chapter 4928 | Competitive Retail Electric Service
Section 4928.23 | Definitions for Standards for Securitization of Costs for Electric Distribution Utilities.

Effective: March 22, 2012
Latest Legislation: House Bill 364 - 129th General Assembly
As used in sections 4928.23 to 4928.2318 of the Revised Code:
(A) "Ancillary agreement" means any bond insurance policy, letter of credit, reserve account, surety bond, swap arrangement, hedging arrangement, liquidity or credit support arrangement, or other similar agreement or arrangement entered into in connection with the issuance of phase-in-recovery bonds that is designed to promote the credit quality and marketability of the bonds or to mitigate the risk of an increase in interest rates.
(B) "Assignee" means any person or entity to which an interest in phase-in-recovery property is sold, assigned, transferred, or conveyed, other than as security, and any successor to or subsequent assignee of such a person or entity.
(C) "Bond" includes debentures, notes, certificates of participation, certificates of beneficial interest, certificates of ownership or other evidences of indebtedness or ownership that are issued by an electric distribution utility or an assignee under a final financing order, the proceeds of which are used directly or indirectly to recover, finance, or refinance phase-in costs and financing costs, and that are secured by or payable from revenues from phase-in-recovery charges.
(D) "Bondholder" means any holder or owner of a phase-in-recovery bond.
(E) "Financing costs" means any of the following:
(1) Principal, interest, and redemption premiums that are payable on phase-in-recovery bonds;
(2) Any payment required under an ancillary agreement;
(3) Any amount required to fund or replenish a reserve account or another account established under any indenture, ancillary agreement, or other financing document relating to phase-in-recovery bonds;
(4) Any costs of retiring or refunding any existing debt and equity securities of an electric distribution utility in connection with either the issuance of, or the use of proceeds from, phase-in-recovery bonds;
(5) Any costs incurred by an electric distribution utility to obtain modifications of or amendments to any indenture, financing agreement, security agreement, or similar agreement or instrument relating to any existing secured or unsecured obligation of the electric distribution utility in connection with the issuance of phase-in-recovery bonds;
(6) Any costs incurred by an electric distribution utility to obtain any consent, release, waiver, or approval from any holder of an obligation described in division (E)(5) of this section that are necessary to be incurred for the electric distribution utility to issue or cause the issuance of phase-in-recovery bonds;
(7) Any taxes, franchise fees, or license fees imposed on phase-in-recovery revenues;
(8) Any costs related to issuing or servicing phase-in-recovery bonds or related to obtaining a financing order, including servicing fees and expenses, trustee fees and expenses, legal, accounting, or other professional fees and expenses, administrative fees, placement fees, underwriting fees, capitalized interest and equity, and rating-agency fees;
(9) Any other similar costs that the public utilities commission finds appropriate.
(F) "Financing order" means an order issued by the public utilities commission under section 4928.232 of the Revised Code that authorizes an electric distribution utility or an assignee to issue phase-in-recovery bonds and recover phase-in-recovery charges.
(G) "Final financing order" means a financing order that has become final and has taken effect as provided in section 4928.233 of the Revised Code.
(H) "Financing party" means either of the following:
(1) Any trustee, collateral agent, or other person acting for the benefit of any bondholder;
(2) Any party to an ancillary agreement, the rights and obligations of which relate to or depend upon the existence of phase-in-recovery property, the enforcement and priority of a security interest in phase-in-recovery property, the timely collection and payment of phase-in-recovery revenues, or a combination of these factors.
(I) "Financing statement" has the same meaning as in section 1309.102 of the Revised Code.
(J) "Phase-in costs" means costs, inclusive of carrying charges incurred before, on, or after the effective date of this section, authorized by the commission before, on, or after the effective date of this section to be securitized or deferred as regulatory assets in proceedings under section 4909.18 of the Revised Code, sections 4928.141 to 4928.143, or 4928.144 of the Revised Code, or section 4928.14 of the Revised Code as it existed prior to July 31, 2008, pursuant to a final order for which appeals have been exhausted. "Phase-in costs" excludes the following:
(1) With respect to any electric generating facility that, on and after the effective date of this section, is owned, in whole or in part, by an electric distribution utility applying for a financing order under section 4928.231 of the Revised Code, costs that are authorized under division (B)(2)(b) or (c) of section 4928.143 of the Revised Code;
(2) Costs incurred after the effective date of this section related to the ongoing operation of an electric generating facility, but not environmental clean-up or remediation costs incurred by an electric distribution utility because of its ownership or operation of an electric generating facility prior to the effective date of this section, which such clean-up or remediation costs are imposed or incurred pursuant to federal or state law rules, or regulations and for which the commission approves recovery in accordance with section 4909.18 of the Revised Code, sections 4928.141 to 4928.143, or 4928.144 of the Revised Code, or section 4928.14 of the Revised Code as it existed prior to July 31, 2008.
(K) "Phase-in-recovery property" means the property, rights, and interests of an electric distribution utility or an assignee under a final financing order, including the right to impose, charge, and collect the phase-in-recovery charges that shall be used to pay and secure the payment of phase-in-recovery bonds and financing costs, and including the right to obtain adjustments to those charges, and any revenues, receipts, collections, rights to payment, payments, moneys, claims, or other proceeds arising from the rights and interests created under the final financing order.
(L) "Phase-in-recovery revenues" means all revenues, receipts, collections, payments, moneys, claims, or other proceeds arising from phase-in-recovery property.
(M) "Successor" means, with respect to any entity, another entity that succeeds by operation of law to the rights and obligations of the first legal entity pursuant to any bankruptcy, reorganization, restructuring, or other insolvency proceeding, any merger, acquisition, or consolidation, or any sale or transfer of assets, regardless of whether any of these occur as a result of a restructuring of the electric power industry or otherwise.

Structure Ohio Revised Code

Ohio Revised Code

Title 49 | Public Utilities

Chapter 4928 | Competitive Retail Electric Service

Section 4928.01 | Competitive Retail Electric Service Definitions.

Section 4928.02 | State Policy.

Section 4928.03 | Identification of Competitive Services and Noncompetitive Services.

Section 4928.04 | Additional Competitive Services.

Section 4928.05 | Extent of Exemptions.

Section 4928.06 | Commission to Ensure Competitive Retail Electric Service.

Section 4928.07 | Separate Pricing of Services on Bill.

Section 4928.08 | Certification to Provide Retail Electric Competitive Service.

Section 4928.09 | Consent to Jurisdiction - Appointment of Statutory Agent.

Section 4928.10 | Minimum Service Requirements for Competitive Services.

Section 4928.11 | Minimum Service Requirements for Noncompetitive Services.

Section 4928.111 | Review of Distribution and Transmission Infrastructure.

Section 4928.112 | Priority to Hospitals in Case of Outage.

Section 4928.12 | Qualifying Transmission Entities.

Section 4928.13 | Nuclear Generation Facilities Decommissioning.

Section 4928.14 | Failure of Supplier to Provide Service.

Section 4928.141 | Distribution Utility to Provide Standard Service Offer.

Section 4928.142 | Standard Generation Service Offer Price - Competitive Bidding.

Section 4928.143 | Application for Approval of Electric Security Plan - Testing.

Section 4928.144 | Phase-in of Electric Distribution Utility Rate or Price.

Section 4928.145 | Availability of Contract or Agreement Relevant to Proceeding.

Section 4928.146 | Electric Service Within Territory of Another Utility.

Section 4928.148 | Nonbypassable Rate Mechanism for Recovery of Costs.

Section 4928.15 | Schedules for Provision of Noncompetitive Service.

Section 4928.151 | Uniform Policy Regarding Electric Transmission Facilities.

Section 4928.16 | Commission Jurisdiction.

Section 4928.17 | Corporate Separation Plans.

Section 4928.18 | Jurisdiction and Powers of Commission Concerning Utility or Affiliate.

Section 4928.19 | Consumer Education.

Section 4928.20 | Local Aggregation of Retail Electric Loads - Limitations.

Section 4928.21 | Do Not Aggregate List - Registration - Removal of Current Enrollee.

Section 4928.23 | Definitions for Standards for Securitization of Costs for Electric Distribution Utilities.

Section 4928.231 | Financing Order for Issuance of Bonds to Recover Phase-in Costs and Carrying Charges.

Section 4928.232 | Proceedings; Review of Application; Disposition.

Section 4928.233 | Rehearing; When Order Becomes Final.

Section 4928.234 | Phase-in-Recovery Property.

Section 4928.235 | Duration of Final Financing Order.

Section 4928.236 | Subsequent Financing Orders.

Section 4928.237 | Public Utilities Commission - Prohibited Acts.

Section 4928.238 | Request for Approval of Adjustments to Charges.

Section 4928.239 | Nonbypassable Charges; Collection.

Section 4928.2310 | Default; Sequestration and Payment of Revenues for Benefit of Bondholders, Assignees, and Financing Parties.

Section 4928.2311 | Successors.

Section 4928.2312 | Security Interest in Phase-in-Recovery Property.

Section 4928.2313 | Sale, Assignment, or Transfer of Phase-in-Recovery Property.

Section 4928.2314 | Exemption From Taxes and Other Charges.

Section 4928.2315 | Prohibition of State Interference.

Section 4928.2316 | Governing Law.

Section 4928.2317 | Repealed Laws Have No Effect on Actions Taken.

Section 4928.2318 | Assignee or Financing Party Not Considered an Electric Distribution Utility.

Section 4928.24 | Federal Energy Advocate, Duties.

Section 4928.31 | Transition Plan.

Section 4928.32 | Procedures for Expedited Discovery in Proceeding Initiated to Consider Transition Plan.

Section 4928.33 | Transition Plan Approval.

Section 4928.34 | Determinations for Approval or Prescribing of Plan.

Section 4928.35 | Schedules Containing Unbundled Rate Components Set in Approved Plan.

Section 4928.36 | Complaint Concerning Transition Plan.

Section 4928.37 | Receiving Transition Revenues.

Section 4928.38 | Commencing and Terminating Transition Revenues.

Section 4928.39 | Determining Total Allowable Transition Costs.

Section 4928.40 | Establishing Transition Charge for Each Customer Class.

Section 4928.43 | Assisting Employees Affected by Electric Industry Restructuring.

Section 4928.47 | Customer Sited Renewable Energy Resource.

Section 4928.51 | Universal Service Fund.

Section 4928.52 | Universal Service Rider.

Section 4928.53 | Director of Development to Administer Low-Income Customer Assistance Programs.

Section 4928.54 | Aggregate Percentage of Income Payment Plan Program Customers.

Section 4928.541 | Duration of Competitive Procurement Process.

Section 4928.542 | Winning Bids; Requirements.

Section 4928.543 | Rules.

Section 4928.544 | Design, Management, and Supervision of Competitive Procurement Process.

Section 4928.55 | Energy Efficiency and Weatherization Program.

Section 4928.56 | Education Program for Consumers Eligible to Participate in Low-Income Customer Assistance Programs.

Section 4928.57 | Biennial Report to General Assembly.

Section 4928.58 | Public Benefits Advisory Board.

Section 4928.581 | Report on Universal Service Fund.

Section 4928.582 | Authority to Obtain Professional Services.

Section 4928.583 | Response to Requests.

Section 4928.61 | Energy Efficiency Revolving Loan Fund.

Section 4928.62 | Energy Efficiency Revolving Loan Program.

Section 4928.621 | Creating an Advanced Energy Manufacturing Center.

Section 4928.63 | Purpose of Energy Efficiency Program.

Section 4928.64 | Electric Distribution Utility to Provide Electricity From Qualifying Renewable Energy Resources.

Section 4928.641 | Costs Being Recovered Through Bypassable Charge.

Section 4928.642 | Reduction From Compliance Amount.

Section 4928.643 | Baselines for Compliance With Qualified Renewable Energy Resource Requirements.

Section 4928.644 | Adjustments to Baselines.

Section 4928.645 | Use of Renewable Energy Credits.

Section 4928.65 | Adoption of Rules Governing Disclosure of Costs to Customers of the Renewable Energy Resource, Energy Efficiency Savings, and Peak Demand Reduction Requirements.

Section 4928.66 | Implementing Energy Efficiency Programs.

Section 4928.661 | Low-Income Customer Portfolio Plan Re-Established.

Section 4928.662 | Measurement and Determination of Compliance With Demand Reduction Requirements.

Section 4928.6610 | Definitions for Sections 4928.6611 to 4928.6615.

Section 4928.6611 | Opting Out of Portfolio Plan.

Section 4928.6612 | Notice of Intent.

Section 4928.6613 | Effect of Election to Opt Out.

Section 4928.6614 | Opting In.

Section 4928.6615 | Notice of Intent to Opt In.

Section 4928.67 | Standard Contract or Tariff Providing for Net Energy Metering.

Section 4928.68 | Rules Establishing Greenhouse Gas Emission Reporting Requirements.

Section 4928.69 | No Surcharge, Service Termination Charge, Exit Fee, or Transition Charge.

Section 4928.70 | Review of Green Pricing Programs.

Section 4928.71 | Study Regarding Customer Choice; Report.

Section 4928.72 | Multi-State Study on the Development of Compressed Natural Gas Infrastructures for Transportation.

Section 4928.75 | Waiver Request.

Section 4928.80 | Rate Schedule Applicable to County Fairs and Agricultural Societies.