Effective: October 29, 1995
Latest Legislation: Senate Bill 162 - 121st General Assembly
The method of mining followed in any coal mine shall not expose the miner to unusual dangers from roof falls caused by excessive widths of rooms and entries or faulty pillar recovery methods.
(A) The method of mining shall provide widths of openings and pillar dimensions compatible with effective roof control. These widths and dimensions shall be incorporated into the roof control plan submitted for approval.
Where excessive widths result from poor mining practices, additional roof support shall be installed before any travel or other work is done in such area. If excessive widths of openings are a result of coal sloughing, additional support shall be installed and the mining system reevaluated to determine changes that are necessary to minimize such occurrences.
(B) In addition to the criteria set forth in division (E) of section 1563.35 of the Revised Code, the following shall apply to pillar recovery:
(1) The overall pillar recovery system shall be designed to minimize the possibility of outbursts or squeezes. The manner and sequence of recovery shall be included in the roof control plan submitted for approval.
(2) Where full pillar recovery is being done, extraction shall be such as to allow total caving of the main roof in the pillared area.
(3) During partial pillar recovery sufficient coal shall be left in place to support the main roof to the extent that the possibility of undue forces overriding the working places will be minimized.
(4) A combination of full and partial pillar recovery shall not be conducted on the same pillar line.
(5) If full extraction of pillars is being done and physical conditions such as standing water, adverse roof conditions, and falls of roof, or law requirements concerning oil and gas wells or surface subsidence dictate that some pillars of coal are to be left in place, a sufficient amount of coal shall be left to support the main roof so as to minimize the possibility of undue forces overriding the working places.
(6) Where full recovery of pillars is planned, the design of the pillars shall be compatible with the planned method of extraction.
(7) Pillaring methods shall eliminate pillar points and pillars that project inby the brakeline.
(8) When recovering adjacent pillars left and right from the same opening, mining shall be completed in one such pillar left and the openings posted off with at least two rows of breaker posts on not more than four foot centers before operations are started in the second pillar.
(C) Longwall mining shall be considered as modification of the open-end method of pillar extraction and the support system for the longwall shall be approved on an individual basis.
(D) No person shall refuse or neglect to comply with this section.
Structure Ohio Revised Code
Title 15 | Conservation of Natural Resources
Chapter 1563 | Mine Construction, Maintenance, Abandonment
Section 1563.01 | Chapter Does Not Apply to Chapter 1514 Activities.
Section 1563.02 | Gaseous Mine Defined.
Section 1563.03 | Map of New Mine.
Section 1563.04 | Survey - Copies of Map and Survey - Certification.
Section 1563.05 | Failure to Make and File Map or Addition.
Section 1563.06 | Right of Entry.
Section 1563.07 | Examination or Survey of Mine by Adjoining Landowner - Notice.
Section 1563.08 | Surveying Party - Fees.
Section 1563.09 | Examination or Survey - Liability for Damage.
Section 1563.10 | Refusal to Permit Survey - Judgment.
Section 1563.11 | Mining Near Public Roads.
Section 1563.111 | Mining Near Oil or Gas Well.
Section 1563.12 | Construction Regulations to Be Observed in Opening Mine.
Section 1563.13 | Maintenance of Means of Egress From Mine.
Section 1563.14 | Two Openings Required - Exceptions.
Section 1563.15 | Additional Opening for Protection Against Inundation.
Section 1563.17 | Break-Throughs and Brattices.
Section 1563.18 | Separate Traveling Ways.
Section 1563.19 | Slopes and Mechanical Haulageways - Refuge Holes.
Section 1563.20 | Track in Mines - Minimum Clearance.
Section 1563.21 | Location of Boilers.
Section 1563.24 | Mine Foreperson of Gaseous Mine - Powers and Duties.
Section 1563.25 | Accumulation of Combustible Materials Prohibited.
Section 1563.26 | Rock Dusting - Testing of Dust Samples.
Section 1563.27 | Examination of Working Place by Mine Foreman.
Section 1563.28 | Examination of Working Place by Fire Boss.
Section 1563.29 | Examination of Working Place by Miner.
Section 1563.30 | Unsafe Working Place.
Section 1563.31 | Work to Cease When Working Place Found Dangerous.
Section 1563.32 | Fencing of Dangerous Places - Danger Signs.
Section 1563.33 | Roof Control System and Plan.
Section 1563.34 | Operator Program for Improving Roof Control Systems.
Section 1563.35 | Criteria or Specifications Applied to Plans.
Section 1563.36 | Excessive Widths of Rooms and Entries or Faulty Pillar Recovery Methods.
Section 1563.37 | Operator to Supply Roof Support Materials - Roof Bolts - Testing of Danger Areas.
Section 1563.39 | Precautions When Working Place Approaches Completed or Abandoned Workings.
Section 1563.40 | Closing of Openings to Abandoned Mines - Closing Abandoned Vertical Shafts.
Section 1563.41 | Sealing Off Abandoned Workings.
Section 1563.42 | Filing of Map of Abandoned Mine.
Section 1563.43 | When Notice to Chief Required.