ยง 39. Lien wilfully exaggerated is void. In any action or proceeding
to enforce a mechanic's lien upon a private or public improvement or in
which the validity of the lien is an issue, if the court shall find that
a lienor has wilfully exaggerated the amount for which he claims a lien
as stated in his notice of lien, his lien shall be declared to be void
and no recovery shall be had thereon. No such lienor shall have a right
to file any other or further lien for the same claim. A second or
subsequent lien filed in contravention of this section may be vacated
upon application to the court on two days' notice.
Structure New York Laws
3 - Mechanic's Lien on Real Property.
4-A - Insurance Proceeds Liable for Demands.
5 - Liens Under Contracts for Public Improvements.
6 - Liens for Labor on Railroads.
7 - Liability for Advance Payments, Collusive Mortgages and Incumbrances.
8 - Terms of Contract May Be Demanded.
9 - Contents of Notice of Lien.
10 - Filing of Notice of Lien.
11 - Service of Copy of Notice of Lien.
11-A - Notice of Completion and Acceptance May Be Demanded.
11-B - Copy of Notice of Lien to a Contractor or Subcontractor.
12 - Notice of Lien on Account of Public Improvements.
15 - Assignments of Contracts and Orders to Be Filed.
16 - Assignment of Contracts and Orders for Public Improvement to Be Filed.
18 - Duration of Lien Under Contract for a Public Improvement.
19 - Discharge of Lien for Private Improvement.
20 - Discharge of Lien After Notice of Lien Filed by Payment of Money Into Court.
21 - Discharge of Lien for Public Improvement.
21-A - Vacating Lien for a Public Improvement, by Order of Court.
24 - Enforcement of Mechanic's Lien.
25 - Priority of Liens and Assignments Under Contracts for Public Improvements.
26 - Subordination of Liens After Agreement With Owner.
28 - Lien of Certain Judgments Postponed.
29 - Subordination of Liens to Subsequent Mortgage.
30 - Subordination of Notices of Lis Pendens.
31 - Discharge of Liens on Sale of Real Property.
32 - Certain Liens and Claims Not to Be Affected.
33 - Certain Sections Not to Apply to Laborers' Liens.
35 - Waiver of Arbitration; Arbitrators' Award Conclusive.
37 - Bond to Discharge All Liens.
38 - Itemized Statement May Be Required of Lienor.
39 - Lien Wilfully Exaggerated Is Void.
39-A - Liability of Lienor Where Lien Has Been Declared Void on Account of Wilful Exaggeration.