14 - Assignment of Lien.

ยง 14. Assignment of lien. A lien, filed as prescribed in this article,
may be assigned by a written instrument signed and acknowledged by the
lienor, at any time before the discharge thereof. Such assignment shall
contain the names and places of residence of the assignor and assignee,
the amount of the lien and the date of filing the notice of lien, and be
filed in the office where the notice of the lien assigned is filed. The
facts relating to such an assignment and the names of the assignee shall
be entered by the proper officer in the book where the notice of lien is
entered and opposite the entry thereof. Unless such assignment is filed,
the assignee need not be made a defendant in an action to foreclose a
mortgage, lien or other incumbrance. A payment made by the owner of the
real property subject to the lien assigned or by his agent or
contractor, or by the contractor of a public corporation, to the
original lienor, on account of such lien, without notice of such
assignment and before the same is filed, shall be valid and of full
force and effect. Except as prescribed herein, the validity of an
assignment of a lien shall not be affected by a failure to file the
same.

Structure New York Laws

New York Laws

LIE - Lien

Article 2 - Mechanics' Liens

3 - Mechanic's Lien on Real Property.

4 - Extent of Lien.

4-A - Insurance Proceeds Liable for Demands.

5 - Liens Under Contracts for Public Improvements.

6 - Liens for Labor on Railroads.

7 - Liability for Advance Payments, Collusive Mortgages and Incumbrances.

8 - Terms of Contract May Be Demanded.

9 - Contents of Notice of Lien.

10 - Filing of Notice of Lien.

11 - Service of Copy of Notice of Lien.

11-A - Notice of Completion and Acceptance May Be Demanded.

11-B - Copy of Notice of Lien to a Contractor or Subcontractor.

11-C - Copy of Notice of Lien to a Contractor or Subcontractor With Respect to Public Improvements Liens.

12 - Notice of Lien on Account of Public Improvements.

12-A - Amendment.

13 - Priority of Liens.

14 - Assignment of Lien.

15 - Assignments of Contracts and Orders to Be Filed.

16 - Assignment of Contracts and Orders for Public Improvement to Be Filed.

17 - Duration of Lien.

18 - Duration of Lien Under Contract for a Public Improvement.

19 - Discharge of Lien for Private Improvement.

20 - Discharge of Lien After Notice of Lien Filed by Payment of Money Into Court.

21 - Discharge of Lien for Public Improvement.

21-A - Vacating Lien for a Public Improvement, by Order of Court.

22 - Building Loan Contract.

23 - Construction of Article.

24 - Enforcement of Mechanic's Lien.

25 - Priority of Liens and Assignments Under Contracts for Public Improvements.

26 - Subordination of Liens After Agreement With Owner.

28 - Lien of Certain Judgments Postponed.

29 - Subordination of Liens to Subsequent Mortgage.

30 - Subordination of Notices of Lis Pendens.

31 - Discharge of Liens on Sale of Real Property.

32 - Certain Liens and Claims Not to Be Affected.

33 - Certain Sections Not to Apply to Laborers' Liens.

34 - Waiver of Lien.

35 - Waiver of Arbitration; Arbitrators' Award Conclusive.

37 - Bond to Discharge All Liens.

38 - Itemized Statement May Be Required of Lienor.

39 - Lien Wilfully Exaggerated Is Void.

39-A - Liability of Lienor Where Lien Has Been Declared Void on Account of Wilful Exaggeration.

39-C - Repossession of Materials Not Used.