69-14-605. Time for completion of crossing. It shall be the duty of a railroad company to construct a crossing ordered by the board of county commissioners of any county within 60 days after service of such order; provided, however, that in case any crossing shall be ordered requiring any extended period of construction, such additional time as is reasonably necessary to complete the same shall be allowed by the commission upon the proper application for such extension.
History: En. Sec. 4, Ch. 148, L. 1919; re-en. Sec. 6628, R.C.M. 1921; re-en. Sec. 6628, R.C.M. 1935; amd. Sec. 20, Ch. 315, L. 1974; R.C.M. 1947, 72-704.
Structure Montana Code Annotated
Title 69. Public Utilities and Carriers
Part 6. Railroad Highway Crossings
69-14-601. Definition of railroad company
69-14-603. Railroad crossings in unincorporated towns or villages
69-14-604. Procedure to order construction of crossing
69-14-605. Time for completion of crossing
69-14-606. Role of public service commission with respect to crossings
69-14-607. Overhead or underground crossings
69-14-608. Court action to determine justness and reasonableness of commission order
69-14-609. Extension of time to comply with order
69-14-610. Effect of railroad crossing provisions on liability of railroad
69-14-611. Penalty for failure to comply with crossing order
69-14-612. Reflectorized material on crossing signs required
69-14-613. through 69-14-619 reserved
69-14-620. Establishment of railroad quiet zones
69-14-626. Prohibition on extended obstruction of highway crossings