Minnesota Statutes
Chapter 216B — Public Utilities
Section 216B.2422 — Resource Planning; Renewable Energy.

Subdivision 1. Definitions. (a) For purposes of this section, the terms defined in this subdivision have the meanings given them.
(b) "Utility" means an entity with the capability of generating 100,000 kilowatts or more of electric power and serving, either directly or indirectly, the needs of 10,000 retail customers in Minnesota. Utility does not include federal power agencies.
(c) "Renewable energy" means electricity generated through use of any of the following resources:
(1) wind;
(2) solar;
(3) geothermal;
(4) hydro;
(5) trees or other vegetation;
(6) landfill gas; or
(7) predominantly organic components of wastewater effluent, sludge, or related by-products from publicly owned treatment works, but not including incineration of wastewater sludge.
(d) "Resource plan" means a set of resource options that a utility could use to meet the service needs of its customers over a forecast period, including an explanation of the supply and demand circumstances under which, and the extent to which, each resource option would be used to meet those service needs. These resource options include using, refurbishing, and constructing utility plant and equipment, buying power generated by other entities, controlling customer loads, and implementing customer energy conservation.
(e) "Refurbish" means to rebuild or substantially modify an existing electricity generating resource of 30 megawatts or greater.
(f) "Energy storage system" means a commercially available technology that:
(1) uses mechanical, chemical, or thermal processes to:
(i) store energy, including energy generated from renewable resources and energy that would otherwise be wasted, and deliver the stored energy for use at a later time; or
(ii) store thermal energy for direct use for heating or cooling at a later time in a manner that reduces the demand for electricity at the later time;
(2) is composed of stationary equipment;
(3) if being used for electric grid benefits, is operationally visible and capable of being controlled by the distribution or transmission entity managing it, to enable and optimize the safe and reliable operation of the electric system; and
(4) achieves any of the following:
(i) reduces peak or electrical demand;
(ii) defers the need or substitutes for an investment in electric generation, transmission, or distribution assets;
(iii) improves the reliable operation of the electrical transmission or distribution systems, while ensuring transmission or distribution needs are not created; or
(iv) lowers customer costs by storing energy when the cost of generating or purchasing it is low and delivering it to customers when the costs are high.
Subd. 2. Resource plan filing and approval. (a) A utility shall file a resource plan with the commission periodically in accordance with rules adopted by the commission. The commission shall approve, reject, or modify the plan of a public utility, as defined in section 216B.02, subdivision 4, consistent with the public interest.
(b) In the resource plan proceedings of all other utilities, the commission's order shall be advisory and the order's findings and conclusions shall constitute prima facie evidence which may be rebutted by substantial evidence in all other proceedings. With respect to utilities other than those defined in section 216B.02, subdivision 4, the commission shall consider the filing requirements and decisions in any comparable proceedings in another jurisdiction.
(c) As a part of its resource plan filing, a utility shall include the least cost plan for meeting 50 and 75 percent of all energy needs from both new and refurbished generating facilities through a combination of conservation and renewable energy resources.
Subd. 2a. Historical data and advance forecast. Each utility required to file a resource plan under this section shall include in the filing all applicable annual information required by section 216C.17, subdivision 2, and the rules adopted under that section. To the extent that a utility complies with this subdivision, it is not required to file annual advance forecasts with the department under section 216C.17, subdivision 2.
Subd. 2b. Optional integrated resource plan compliance for certain cooperatives. For the purposes of this subdivision, a "cooperative" means a generating and transmission cooperative electric association that has at least 80 percent of its member distribution cooperatives located outside of Minnesota and that provides less than four percent of the electricity annually sold at retail in the state of Minnesota. A cooperative may, in lieu of filing a resource plan under subdivision 2, elect to file a report to the commission under this subdivision. The report must include projected demand levels for the next 15 years and generation resources to meet any projected generation deficiencies. To supply the information required in a report under this subdivision, a cooperative may use reports submitted under section 216C.17, subdivision 2, reports to regional reliability organizations, or similar reports submitted to other state utility commissions. A report must be submitted annually by July 1, but the commission may extend the time if it finds the extension in the public interest. Presentation of the annual report shall be done in accordance with procedures established by the commission. Data in a report under this subdivision may be aggregate data and need not be separately reported for individual distribution cooperative members of the cooperative. The commission may take whatever action in response to a report under this subdivision that it could take with respect to a report by a cooperative under subdivision 2.
Subd. 2c. Long-range emission reduction planning. Each utility required to file a resource plan under subdivision 2 shall include in the filing a narrative identifying and describing the costs, opportunities, and technical barriers to the utility continuing to make progress on its system toward achieving the state greenhouse gas emission reduction goals established in section 216H.02, subdivision 1, and the technologies, alternatives, and steps the utility is considering to address those opportunities and barriers.
Subd. 2d. Plan to minimize impacts to workers due to facility retirement. A utility required to file a resource plan under subdivision 2 that has scheduled the retirement of an electric generating facility located in Minnesota must include in the filing a narrative describing the utility's efforts, in conjunction with the utility's workers and the workers' designated representatives, to develop a plan to minimize the dislocations employees may suffer as a result of the facility's retirement. The narrative must address, at a minimum, plans to:
(1) minimize financial losses to workers;
(2) provide a transition timeline to ensure certainty for workers;
(3) protect pension benefits;
(4) extend or replace health insurance, life insurance, and other employment benefits;
(5) provide training and skill development for workers who must or choose to leave the utility;
(6) create targeted transition plans for workers at all locations impacted by the facility retirement; and
(7) quantify any additional costs the utility would incur and specifying what costs, if any, the utility would request be recovered in the utility's rates as a result of efforts made under this subdivision to minimize impacts to workers.
Subd. 3. Environmental costs. (a) The commission shall, to the extent practicable, quantify and establish a range of environmental costs associated with each method of electricity generation. A utility shall use the values established by the commission in conjunction with other external factors, including socioeconomic costs, when evaluating and selecting resource options in all proceedings before the commission, including resource plan and certificate of need proceedings.
(b) The commission shall establish interim environmental cost values associated with each method of electricity generation by March 1, 1994. These values expire on the date the commission establishes environmental cost values under paragraph (a).
Subd. 4. Preference for renewable energy facility. The commission shall not approve a new or refurbished nonrenewable energy facility in an integrated resource plan or a certificate of need, pursuant to section 216B.243, nor shall the commission allow rate recovery pursuant to section 216B.16 for such a nonrenewable energy facility, unless the utility has demonstrated that a renewable energy facility is not in the public interest. When making the public interest determination, the commission must consider:
(1) whether the resource plan helps the utility achieve the greenhouse gas reduction goals under section 216H.02, the renewable energy standard under section 216B.1691, or the solar energy standard under section 216B.1691, subdivision 2f;
(2) impacts on local and regional grid reliability;
(3) utility and ratepayer impacts resulting from the intermittent nature of renewable energy facilities, including but not limited to the costs of purchasing wholesale electricity in the market and the costs of providing ancillary services; and
(4) utility and ratepayer impacts resulting from reduced exposure to fuel price volatility, changes in transmission costs, portfolio diversification, and environmental compliance costs.
Subd. 5. Bidding; exemption from certificate of need proceeding. (a) A utility may select resources to meet its projected energy demand through a bidding process approved or established by the commission. A utility shall use the environmental cost estimates determined under subdivision 3 in evaluating bids submitted in a process established under this subdivision.
(b) Notwithstanding any other provision of this section, if an electric power generating plant, as described in section 216B.2421, subdivision 2, clause (1), is selected in a bidding process approved or established by the commission, a certificate of need proceeding under section 216B.243 is not required.
(c) A certificate of need proceeding is also not required for an electric power generating plant that has been selected in a bidding process approved or established by the commission, or such other selection process approved by the commission, to satisfy, in whole or in part, the wind power mandate of section 216B.2423 or the biomass mandate of section 216B.2424.
Subd. 6. Consolidation of resource planning and certificate of need. A utility shall indicate in its resource plan whether it intends to site or construct a large energy facility. If the utility's resource plan includes a proposed large energy facility and construction of that facility is likely to begin before the utility files its next resource plan, the commission shall conduct the resource plan proceeding consistent with the requirements of section 216B.243 with respect to the proposed facility. If the commission approves the proposed facility in the resource plan, a separate certificate of need proceeding is not required.
Subd. 7. Energy storage systems assessment. (a) Each public utility required to file a resource plan under subdivision 2 must include in the filing an assessment of energy storage systems that analyzes how the deployment of energy storage systems contributes to:
(1) meeting identified generation and capacity needs; and
(2) evaluating ancillary services.
(b) The assessment must employ appropriate modeling methods to enable the analysis required in paragraph (a).
1993 c 356 s 3; 1994 c 644 s 4; 1997 c 176 s 2; 1997 c 198 s 1; 2008 c 258 s 3; 2012 c 268 s 1; 2013 c 132 s 3; 2014 c 254 s 12; 2017 c 94 art 10 s 18,19; 1Sp2019 c 7 art 11 s 4,5; 1Sp2021 c 4 art 8 s 19

Structure Minnesota Statutes

Minnesota Statutes

Chapters 216 - 217 — Utilities

Chapter 216B — Public Utilities

Section 216B.01 — Legislative Findings.

Section 216B.02 — Definitions.

Section 216B.022 — Submetering.

Section 216B.025 — Municipal Regulation Option.

Section 216B.026 — Cooperative Electric Association; Election On Regulation.

Section 216B.027 — Cooperative Electric Association Stockholder Rights.

Section 216B.029 — Standards For Distribution Utilities.

Section 216B.03 — Reasonable Rate.

Section 216B.04 — Standard Of Service.

Section 216B.045 — Regulation Of Intrastate Natural Gas Pipeline.

Section 216B.05 — Filing Schedules, Rules, And Service Agreements.

Section 216B.06 — Receiving Different Compensation.

Section 216B.07 — Rate Preference Prohibited.

Section 216B.075 — Meter Reading; Customer Scheduling Needs.

Section 216B.08 — Duties Of Commission.

Section 216B.09 — Standards; Classifications; Rules; Practices.

Section 216B.091 — Monthly Reports.

Section 216B.0951 — Propane Prepurchase Program.

Section 216B.096 — Cold Weather Rule; Public Utility.

Section 216B.097 — Cold Weather Rule; Cooperative Or Municipal Utility.

Section 216B.0975 — Disconnection During Extreme Heat Conditions.

Section 216B.0976 — Notice Of Utility Disconnection.

Section 216B.098 — Residential Customer Protections.

Section 216B.0991 — Definitions.

Section 216B.0992 — Price And Fee Disclosure.

Section 216B.0993 — Budget Payment Plan.

Section 216B.0994 — Propane Purchase Contracts.

Section 216B.0995 — Terms Of Sale.

Section 216B.10 — Accounting.

Section 216B.105 — Customer Share Of Mercury Control Costs.

Section 216B.11 — Depreciation Rates And Practices.

Section 216B.12 — Right Of Entrance; Inspection.

Section 216B.13 — Production And Examination Of Records.

Section 216B.14 — Investigation.

Section 216B.15 — Hearings; Examiner.

Section 216B.16 — Rate Change; Procedure; Hearing.

Section 216B.161 — Area Development Rate Plan.

Section 216B.1611 — Interconnection Of On-site Distributed Generation.

Section 216B.1613 — Standardized Contract.

Section 216B.1614 — Electric Vehicle Charging Tariff.

Section 216B.162 — Competitive Rate For Electric Utility.

Section 216B.1621 — Electric Service Agreement.

Section 216B.163 — Flexible Tariff.

Section 216B.1635 — Recovery Of Gas Utility Infrastructure Costs.

Section 216B.1636 — Recovery Of Electric Utility Infrastructure Costs.

Section 216B.1638 — Recovery Of Natural Gas Extension Project Costs.

Section 216B.164 — Cogeneration And Small Power Production.

Section 216B.1641 — Community Solar Garden.

Section 216B.1642 — Solar Site Management.

Section 216B.1645 — Power Purchase Contract Or Investment.

Section 216B.1646 — Rate Reduction; Property Tax Reduction.

Section 216B.1647 — Property Tax Adjustment; Cooperative Association.

Section 216B.166 — Cogenerating Power Plant.

Section 216B.167 — Performance-based Gas Purchasing Plan.

Section 216B.1675 — Performance Regulation Plan For Gas Utility Service.

Section 216B.1681 — Curtailment Payments.

Section 216B.169 — Renewable And High-efficiency Energy Rate Options.

Section 216B.1691 — Renewable Energy Objectives.

Section 216B.1692 — Emissions-reduction Rider.

Section 216B.1694 — Innovative Energy Project.

Section 216B.1695 — Environmental Projects; Advance Determination Of Prudence.

Section 216B.1696 — Competitive Rate For Energy-intensive, Trade-exposed Electric Utility Customer.

Section 216B.17 — Complaint Investigation And Hearing.

Section 216B.18 — Service Of Notice.

Section 216B.19 — Joint Hearing And Investigation.

Section 216B.20 — Separate Rate Hearing.

Section 216B.21 — Summary Investigation.

Section 216B.22 — Municipality; Amicus Curiae Authority.

Section 216B.23 — Lawful Rate; Reasonable Service.

Section 216B.24 — Construction Of Major Facility; Filing Plans.

Section 216B.2401 — Energy Savings And Optimization Policy Goal.

Section 216B.2402 — Definitions.

Section 216B.2403 — Consumer-owned Utilities; Energy Conservation And Optimization.

Section 216B.241 — Public Utilities; Energy Conservation And Optimization.

Section 216B.2411 — Distributed Energy Resources.

Section 216B.2412 — Decoupling Of Energy Sales From Revenues.

Section 216B.2421 — Definition Of Large Energy Facility.

Section 216B.2422 — Resource Planning; Renewable Energy.

Section 216B.2423 — Wind Power Mandate.

Section 216B.2424 — Biomass Power Mandate.

Section 216B.2425 — State Transmission And Distribution Plan.

Section 216B.2426 — Opportunities For Distributed Generation.

Section 216B.2427 — Natural Gas Utility Innovation Plans.

Section 216B.2428 — Lifecycle Greenhouse Gas Emissions Accounting Framework; Cost-benefit Test For Innovative Resources.

Section 216B.243 — Certificate Of Need For Large Energy Facility.

Section 216B.244 — Nuclear Plant Capacity Requirements.

Section 216B.2445 — Decommissioning Nuclear Plant; Storing Used Fuel.

Section 216B.245 — Pump And Store Hydropower Facility; Prohibition.

Section 216B.246 — Federally Approved Transmission Lines; Incumbent Transmission Lineowner Rights.

Section 216B.25 — Further Action On Previous Order.

Section 216B.26 — Order; Effective Date.

Section 216B.27 — Rehearing; Condition Precedent To Judicial Review.

Section 216B.28 — Subpoena; Witness Fee And Mileage.

Section 216B.29 — Hearing And Subpoena Compliance Powers.

Section 216B.30 — Deposition.

Section 216B.31 — Testimony And Production Of Records; Perjury.

Section 216B.32 — Certified Copy Of Document As Evidence.

Section 216B.33 — Commission Ruling Written, Filed, And Certified.

Section 216B.34 — Public Records.

Section 216B.35 — Transcribed Record.

Section 216B.36 — Municipal Regulatory And Taxing Powers.

Section 216B.361 — Township Agreement With Natural Gas Utility.

Section 216B.37 — Assigned Service Area; Electric Utility; Legislative Policy.

Section 216B.38 — Definitions.

Section 216B.39 — Assigned Service Area.

Section 216B.40 — Exclusive Service Right; Service Extension.

Section 216B.41 — Effect Of Incorporation, Annexation, Or Consolidation.

Section 216B.42 — Service Extension In Certain Situations.

Section 216B.421 — Homestead; Option Of Electric Service.

Section 216B.43 — Hearing On Complaint.

Section 216B.44 — Municipal Service Territory Extension.

Section 216B.45 — Municipal Purchase Of Public Utility.

Section 216B.46 — Municipal Acquisition Procedures; Notice; Election.

Section 216B.465 — Voter Ratification Of Municipal Purchase; Limited Application.

Section 216B.47 — Acquisition By Eminent Domain.

Section 216B.48 — Relations With Affiliated Interest.

Section 216B.49 — Securities; Public Financing.

Section 216B.50 — Restrictions On Property Transfer And Merger.

Section 216B.51 — Stock Purchase.

Section 216B.52 — Appeal.

Section 216B.53 — Suspension Of Commission Order.

Section 216B.54 — Legal Action Against Violation.

Section 216B.56 — Burden Of Proof.

Section 216B.57 — Penalty For Violation Of Act.

Section 216B.58 — Penalties; Construing Act, Omission, And Failure.

Section 216B.59 — Continuing Violation.

Section 216B.60 — Penalties Cumulative.

Section 216B.61 — Actions To Recover Penalties.

Section 216B.62 — Regulatory Expenses.

Section 216B.63 — Interest On Assessment.

Section 216B.64 — Attorney General's Responsibilities.

Section 216B.65 — Department To Employ Necessary Staff.

Section 216B.66 — Construction.

Section 216B.67 — Citation.

Section 216B.68 — Definitions; Mercury Emissions Reduction.

Section 216B.681 — Monitoring Mercury Emissions.

Section 216B.682 — Mercury Emissions-reduction Plans.

Section 216B.683 — Mercury Emissions Reduction; Cost Recovery, Financial Incentives.

Section 216B.684 — Environmental Assessment Of Mercury Emissions-reduction Plan.

Section 216B.685 — Mercury Emissions-reduction Plan Approval.

Section 216B.6851 — Utility Option.

Section 216B.686 — Other Environmental Improvement Plans.

Section 216B.687 — Mercury Emissions Reduction Implementation, Operation.

Section 216B.688 — Relationship To Other State Financial Requirements.

Section 216B.79 — Preventative Maintenance.

Section 216B.82 — Local Power Quality Zones.