Subdivision 1. Requirements. (a) The managers may initiate a project by resolution of at least a majority of the managers if:
(1) the project is financed by grants totaling at least 50 percent of the estimated project cost; and
(2) the engineer's estimate of costs to parties affected by the watershed district, including assessments against benefited properties but excluding state, federal, or other grants, is not more than $750,000 for the project.
(b) A resolution under this subdivision may not be used to establish a project that has drainage as its essential nature and purpose.
Subd. 2. Preliminary resolution hearing notice. (a) The managers must set the time and location for a preliminary resolution hearing on the proposed resolution for the project.
(b) The managers must give notice of the preliminary resolution hearing by publication in a legal newspaper published in the counties affected by the watershed district. The last publication must occur at least ten days before the preliminary resolution hearing.
(c) The preliminary resolution hearing notice must contain:
(1) the date, time, and place of hearing;
(2) the substance of the proposed project resolution;
(3) the means of financing the project; and
(4) a statement that all persons who might be affected by the proposed project or who may be interested in the proposed project may appear and be heard.
(d) Defects in the notice do not invalidate the proceedings.
Subd. 3. Preliminary report and information. (a) The managers must have the watershed district engineer or another competent person prepare a preliminary report advising the managers whether the proposed project is feasible and estimating the cost of the project. An error or omission in the preliminary report does not invalidate the proceeding.
(b) The managers may have other helpful information prepared that will aid in determining the desirability and feasibility of the project.
Subd. 4. Unfavorable preliminary report. If the preliminary report is unfavorable, the managers must set a time and location for a hearing in the manner provided for the preliminary resolution. After the hearing, the project may be referred back to the watershed district engineer or another competent person for further study and report, or the managers may dismiss the proceeding.
Subd. 5. Final resolution. If, after the hearing, the managers determine that the proposed project promotes the public interest and welfare and is practicable and in conformity with the watershed management plan of the watershed district, the managers must adopt a final resolution approving the project and identify the proceeding by name and number.
Subd. 6. Further procedure. (a) When a final resolution is adopted, the proceeding must continue as provided for a project initiated by a petition.
(b) After the managers file a statement listing the property benefited, damaged, or otherwise affected by a project with the auditors of counties affected by the project, the proceedings for the project must continue under section 103D.901.
1990 c 391 art 4 s 44
Structure Minnesota Statutes
Chapter 103D — Watershed Districts
Section 103D.011 — Definitions.
Section 103D.501 — Construction And Administration.
Section 103D.505 — Reference To Other Drainage Laws.
Section 103D.511 — Certain Condemnation Provisions; Applicability.
Section 103D.515 — Preexisting And Improved Water Rights.
Section 103D.521 — Rights Assured Due Process Of Law.
Section 103D.525 — Proceedings After Faulty Notices.
Section 103D.531 — Continuance Of Hearings.
Section 103D.535 — Appellate Procedures And Review.
Section 103D.537 — Appeals Of Rules, Permit Decisions, And Orders.
Section 103D.539 — Informal Resolution Of Disputes.
Section 103D.541 — Appeal Of Court Order.
Section 103D.545 — Enforcement.
Section 103D.551 — Enforcing Rules And Orders.
Section 103D.101 — Board Of Water And Soil Resources.
Section 103D.105 — Board Hearings.
Section 103D.111 — Appeal Of Board Orders.
Section 103D.201 — Watershed District Purposes.
Section 103D.205 — Establishment Petition.
Section 103D.211 — Auditor's Certification Of Petitioners.
Section 103D.215 — Director's Report.
Section 103D.221 — Establishment Hearing; Notice.
Section 103D.225 — Hearing And Order To Establish.
Section 103D.231 — Dismissing Establishment Proceedings.
Section 103D.251 — Watershed District Boundary Changes.
Section 103D.255 — Withdrawing Territory.
Section 103D.261 — Proceedings To Enlarge Watershed District.
Section 103D.265 — Consolidating Districts.
Section 103D.271 — Procedure For Terminating Watershed District.
Section 103D.301 — Distribution Of Manager Positions.
Section 103D.305 — Increasing Number Of Managers.
Section 103D.311 — Appointing Managers.
Section 103D.321 — Principal Place Of Business.
Section 103D.331 — Advisory Committee.
Section 103D.335 — District And Managers' Powers.
Section 103D.337 — Technical Advisory Committees.
Section 103D.351 — Annual Report.
Section 103D.355 — Annual Audit.
Section 103D.401 — Watershed Management Plan.
Section 103D.405 — Revised Watershed Management Plan.
Section 103D.411 — Amendment Of Watershed Management Plan And Revised Watershed Management Plan.
Section 103D.601 — Project Initiated By Managers.
Section 103D.605 — Project Constructed With Government Aid Or As Part Of Plan.
Section 103D.611 — Construction By Government Agencies.
Section 103D.615 — Emergency Projects.
Section 103D.621 — Drainage Improvements.
Section 103D.625 — Drainage Systems In Watershed District.
Section 103D.631 — Maintaining Projects.
Section 103D.635 — Repairs And Improvements Exceeding Normal Maintenance.
Section 103D.641 — Work Without Bid.
Section 103D.701 — Project Initiation.
Section 103D.705 — Project Petition.
Section 103D.711 — Engineer's Report.
Section 103D.715 — Appraisers; Determining Benefits And Damages.
Section 103D.721 — Managers; Determining Benefits And Damages.
Section 103D.725 — Benefited Property; Determination.
Section 103D.729 — Water Management District.
Section 103D.730 — Stormwater Facilities.
Section 103D.731 — Appraisers' Report; Examination.
Section 103D.735 — Hearing On Petition And Reports.
Section 103D.741 — Final Hearing Notice.
Section 103D.745 — Final Hearing.
Section 103D.801 — Procedure When Contract Is Not Let.
Section 103D.805 — Filing Managers' Order Establishing Project.
Section 103D.811 — Bids For Construction.
Section 103D.815 — Controlling Contracts.
Section 103D.821 — Bridge Or Grade Removal; Passage Of Equipment.
Section 103D.901 — Assessments; Levies.
Section 103D.905 — Funds Of Watershed District.
Section 103D.921 — District Court To Create Preliminary Fund.