(a) In this section, “date of disapproval” means:
(1) the date of the decision of the district council; or
(2) in case of judicial review, the date of the final judgment of the circuit court.
(b) If the district council wholly or partly disapproves an application for a map amendment, it may not act on a subsequent application for any portion of the same land:
(1) within 18 months after the date of the first disapproval; and
(2) within 24 months after the date of any subsequent disapproval.
(c) In any subsequent application for any portion of the same land and for the same zoning classification or the same purpose for special exception, by the same applicant, the district council may not base its findings solely on any fact or circumstance that was presented at the hearing on the prior application.
Structure Maryland Statutes
Division II - Maryland-National Capital Park and Planning Commission
Title 25 - Prince George's County Provisions
Subtitle 2 - Land Use Controls -- in General
Section 25-201 - Association Represented by Nonattorney
Section 25-202 - Continuance of Zoning Hearing
Section 25-203 - Examination of Witnesses
Section 25-204 - Written Findings and Conclusions Required
Section 25-205 - Record of Hearing
Section 25-206 - Petition for Judicial Review -- People's Zoning Counsel
Section 25-207 - Hearings for Subsequent Applications for Same Parcel
Section 25-208 - Special Exception -- Rubble Landfill
Section 25-209 - Special Exception -- Sand and Gravel Mining
Section 25-210 - Site Plan Review -- District Council
Section 25-211 - Zoning Classification of Beltsville Agricultural Research Center on Sale