(a) The permittee shall file an operations and progress report with the Department by March 31 of each year, on a form prescribed and furnished by the Department, which shall cover the preceding calendar year and shall:
(1) Identify the mine, the permittee, and the permit number;
(2) Identify the location of the operation as to county, district, nearest municipality, and nearest public road;
(3) Report the type of mineral produced, the volume produced, and the value of production of each for the previous year. Individual company data is confidential and may be released only with the permittee’s written consent;
(4) State the acreage disturbed by surface mining during the previous year;
(5) State and describe the amount and type of reclamation carried out during the previous year;
(6) Estimate the acreage to be newly disturbed by mining in the next year; and
(7) Provide any additional information or maps which the Department reasonably requires.
(b) In addition, at the end of each calendar year the permittee shall furnish to the Department a new surveyed map, showing the status of the operation and indicating the area affected and reclaimed during the preceding year, particularly with relation to the property lines and boundaries shown on the map and survey furnished with the original application. A registered professional engineer or professional surveyor is not required to prepare this progress report map. However, if prepared by the permittee, the map shall be of reasonable quality, accuracy, and legibility, and acceptable to the Department.
Structure Maryland Statutes
Section 15-802 - Legislative Intent
Section 15-804 - Review of Mineral Resources Plans
Section 15-805 - Surface Mined Land Reclamation Fund
Section 15-806 - Surface Mine Inspectors
Section 15-807 - Surface Mining License
Section 15-808 - Surface Mining Permit Generally
Section 15-809 - Review of Application and Accompanying Documents; Notice; Hearing
Section 15-810 - Approval or Denial of Permit
Section 15-811 - Conditions for a Permit
Section 15-813 - Permit Conditions for Dewatering a Pit in Karst Terrain
Section 15-814 - Length of Term of Permit
Section 15-815 - Permit Modification
Section 15-816 - Permit Renewal
Section 15-817 - Effective Date of Modification or Renewal
Section 15-818 - New Permit in Lieu of Modification or Renewal
Section 15-819 - Transfer of Permit
Section 15-820 - Departmental Modification of Permit or of Mining and Reclamation Plan
Section 15-821 - Suspension or Revocation of a Permit
Section 15-822 - Mining and Reclamation Plan
Section 15-823 - Performance Bonds or Cash Deposits
Section 15-824 - Release of Bond
Section 15-825 - Forfeiture of Bond
Section 15-826 - Mining After Forfeiture of Bond
Section 15-827 - Annual Mining and Reclamation Reports
Section 15-828 - Inspection and Approval of Reclamation
Section 15-829 - Abandoned or Halted Operations
Section 15-830 - Final Completion Inspection and Report
Section 15-831 - Specifications for Construction Projects
Section 15-832 - Civil Action and Injunction